Lake Turkana Wind Power Project (LTWP) is a wind farm in Kenya. It is located in Loiyangalani District, in Marsabit County, approximately by road north of
Nairobi Nairobi ( ) is the capital and largest city of Kenya. The name is derived from the Maasai phrase ''Enkare Nairobi'', which translates to "place of cool waters", a reference to the Nairobi River which flows through the city. The city proper ha ...
, Kenya's capital city. The wind farm covers and has a capacity of 310 MW, enough to supply one million homes. It comprises 365 wind turbines, each with a capacity of 850 kilowatts. The associated overhead electric grid distribution system and a high voltage substation that connect it to the national grid. The KSh.70 billion/= wind farm is the single largest private investment in Kenya’s history. The power produced is bought at a fixed price by Kenya Power (KPLC) over a 20-year period in accordance with the Power Purchase Agreement (PPA) with the latter. The project was completed in January 2017, however the line evacuating the power generated was not completed until July 2019.


Location

The wind farm is located approximately , north of the town of
South Horr South Horr is a settlement in Kenya's former Rift Valley Province. It is located in Laisamis Constituency, of Marsabit County. The A4 Road from Maralal and Baragoi Baragoi is a market town in Kenya, lying north of Maralal and east of the Suguta ...
, in Loyiangalani sub-county, in the extreme western part of Marsabit County, in the former Eastern Province. This location lies approximately , by road, west of Marsabit, where the county headquarters are located. The geographical coordinates of the wind farm are: 02°30'44.0"N, 36°49'00.0"E (Latitude:2.512222; Longitude:36.816667). The wind is strongest in the morning and in October, and weakest in the afternoon and in February, contrasting with Ngong Hills Wind Power Station.


Land rights

The project is on
trust land Trust often refers to: * Trust (social science), confidence in or dependence on a person or quality It may also refer to: Business and law * Trust law, a body of law under which one person holds property for the benefit of another * Trust (bus ...
owned by local authorities, used by indigenous pastoralists. This means that all the land is held by the relevant local authority, ostensibly in trust for the local inhabitants. The tribes that communally use land in this area include
El Molo The El Molo, also known as Elmolo, Dehes, Fura-Pawa and Ldes, are an ethnic group mainly inhabiting the northern Eastern Province of Kenya. They historically spoke the El Molo language as a mother tongue, an Afro-Asiatic language of the Cushitic ...
, Rendille, Samburu, Turkana and other indigenous and pastoralist communities in the South-East of Marsabit County.


History

LTWP was created in 2006 out of the partnering of ''Anset Africa Limited'' (a company involved in project development and management in the areas of tourism, biogas energy, telecommunications, solid waste management, and road construction) and KP&P (a company that develops and operates wind energy projects). In 2005, discussions with the Kenyan government began regarding the development of a wind power project near to
Lake Turkana Lake Turkana (), formerly known as Lake Rudolf, is a lake in the Kenyan Rift Valley, in northern Kenya, with its far northern end crossing into Ethiopia. It is the world's largest permanent desert lake and the world's largest alkaline lake. B ...
and as a result, extensive wind assessments were conducted. Later in 2007 environmental fieldwork was undertaken. A Memorandum of Understanding (MOU) was signed between LTWP and Kenya Power on 10 April 2008. Land permits IR Number 6395/1 (L.R. 28031) and IR Number 6396/1 (L.R. 28031/2) were signed with the Kenyan government in March 2009, which caused problems when local communities only came to know the plans in April 2014. Construction began in October 2014 and was expected to be completed in June 2017. In March 2016, the first shipment of 30 wind turbines arrived in the country, in anticipation of the first 50 MW coming online in September 2016. At 9 March 2017, Lake Turkana Wind Power Station was ready to produce 33% of the targeted of 310 MW. At that time, all 365 wind turbines had been erected. On 19 July 2019,
Uhuru Kenyatta Uhuru Muigai Kenyatta (born 26 October 1961) is a Kenyan politician who served as the fourth president of Kenya from 2013 to 2022. Kenyatta was chosen by Daniel Arap Moi as his preferred successor, but Kenyatta was defeated by opposition le ...
, the president of Kenya, officially commissioned the , 400kV Loiyangalani-Suswa High Voltage Power Line that transmits the generated power for integration into the national grid. At that time, the power station was averaging generation of 199 megawatts (64 percent of its installed capacity of 310.25 megawatts).


Specification

The wind farm site, covers approximately . The farm has 365 turbines (type Vestas V52), each with capacity of 850 kW. The V52 had gone out of production, but was updated with
nested ''Nested'' is the seventh studio album by Bronx-born singer, songwriter and pianist Laura Nyro, released in 1978 on Columbia Records. Following on from her extensive tour to promote 1976's ''Smile'', which resulted in the 1977 live album ''Season ...
towers for transport on the road from
Mombasa Mombasa ( ; ) is a coastal city in southeastern Kenya along the Indian Ocean. It was the first capital of the British East Africa, before Nairobi was elevated to capital city status. It now serves as the capital of Mombasa County. The town is ...
port, of which are new gravel roads. The power generated from the wind turbines will be transmitted via 33 kV overhead electric wires to a substation which will be located on the premises. From the substation, power will be transmitted via a 400 kV high voltage electric power lines to a substation in
Suswa Suswa is a small town along the main road from Nairobi to Narok town and at the foot of Mount Suswa in Narok County. Suswa is also a ward in Narok East sub-county. The Suswa sub-station is located just outside town and electricity that is generate ...
, approximately , south of Loyangalani, where it will be integrated into the national power grid. The electricity will be bought by Kenya Power Company at a fixed price for 20 years from the time of commissioning. As part of the development, the road from
Laisamis Laisamis is a small town in Kenya's Marsabit County Marsabit County is a county in Kenya. Covering a surface area of 66,923.1 square kilometres. Marsabit is the second largest county in Kenya. Its capital is Marsabit and its largest town Moy ...
to the project site, a distance of approximately , is slated to be upgraded. Construction began in 2015 and full operation is expected to commence in 2018. As of April 2015, construction had begun. The first 90 MW was expected online in October 2016 with full commissioning of the full 300 MW planned for July 2017.


Developers and funding

The company that owns and is developing the wind farm is called Lake Turkana Wind Power Limited. The consortium which owns LTWP Limited includes the following entities: ; Equity partners In February 2020, it became public that Google Inc. would not become an investor in the project. Vestas, the
Danish Danish may refer to: * Something of, from, or related to the country of Denmark People * A national or citizen of Denmark, also called a "Dane," see Demographics of Denmark * Culture of Denmark * Danish people or Danes, people with a Danish ance ...
turbine supplier, which owns 12.5 percent of the holding company, said in Danish media that delays in completing the high voltage transmission line led to the cancellation of the transfer contract in 2019. ;Financial partners The lead arranger for the US$853.12 million syndicated financing package is the
African Development Bank The African Development Bank Group (AfDB) or (BAD) is a multilateral development finance institution headquartered in Abidjan, Ivory Coast, since September 2014. The AfDB is a financial provider to African governments and private companies i ...
, with Standard Bank and Nedbank Capital of
South Africa South Africa, officially the Republic of South Africa (RSA), is the southernmost country in Africa. It is bounded to the south by of coastline that stretch along the South Atlantic and Indian Oceans; to the north by the neighbouring countri ...
as co-arrangers. The following have provided financing to the project. ;Donors The following entities made outright donations to the project: * Government of the Netherlands - €10 million * EU Africa Infrastructure Trust Fund (part of the
European Commission The European Commission (EC) is the executive of the European Union (EU). It operates as a cabinet government, with 27 members of the Commission (informally known as "Commissioners") headed by a President. It includes an administrative body o ...
) - €25 million.


Transmission line and substation

In 2010, the Spanish government offered to finance the construction of a 427 km double circuit transmission line southwards from the site to Suswa, approximately 100 km west of Nairobi. The $150 million offer comprises: * A 'concessional loan' of €55 million ($74 million) at an interest of 0.10 percent, with a repayment period of 30 years, including a 14-year grace period. The loan will be supported by a 'Financial Co-operation Agreement' between Kenya’s Ministry of Finance and Spain’s Ministry of Industry, Tourism and Trade; * €55 million in 'commercial credit' with support from the Spanish Export Credit Insurance Company on
OECD The Organisation for Economic Co-operation and Development (OECD; french: Organisation de coopération et de développement économiques, ''OCDE'') is an intergovernmental organisation with 38 member countries, founded in 1961 to stimulate e ...
terms; * A 'sovereign guarantee' by the Kenyan Government. This means that the
Kenya Electricity Transmission Company Kenya Electricity Transmission Company Limited, commonly referred to as KETRACO, is a wholly-owned parastatal of the Government of Kenya which serves as the primary Transmission System Operator in the Republic of Kenya. Location The headquart ...
(Ketraco), a Government-owned entity created in 2008, will also partly fund the transmission line and the substation by means of a tolling arrangement with Kenya Power. Spanish company
Isolux Corsán Luis Delso Heras (born 1952) is a Spanish business management professional. He served as president of Isolux Corsán (2004–2016), in which capacity he has been alleged to have been involved in the Gürtel case. The company is involved in const ...
won a $208.1 million tender for this construction.


World Bank pulls out of project

LTWP suffered a setback in 2012 when the
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Interna ...
withdrew its support for the project. Bank officials were reported to have concerns that the electricity produced would outweigh demand. The World Bank Group’s country director in Kenya, Johannes Zutt, stated that Kenya could be left with excess power on the grid worth up to KSh.8.5 billion/= (equivalent to $100 million) per year. Originally, the project was expected to be fully operational by the end of 2014. From the project perspective, the withdrawal of the World Bank could be seen in a positive light as it allowed LTWP to move forward to financial close. A source at power transmission firm Ketraco indicated that the agency was happy with the World Bank’s decision to quit. "We are happy that the World Bank has withdrawn. They were putting a lot of hurdles in our way but now we can go ahead."


Economic impacts

LTWP will be the largest single private investment in Kenya at the time it is made. LTWP claims the wind farm will reduce and possibly eliminate Kenya's dependency on diesel and heavy fuel power stations, however, this claim is unsubstantiated. Fuel imports to power thermal power stations, cost the Kenyan taxpayer KSh.17 billion/= (US$150 million) annually. It is anticipated that the project will contribute KSh.3 billion/= (US$35 million) annually, and KSh.58.6 billion/= (US$673 million), in tax revenue over a period 20 years. During construction, approximately 2,500 workers will be hired. Once commissioned, the power station will employ 200 full-time staff.


Impacts on Kenyan State and consumers

The Project is of significant strategic benefit to Kenya, and at KSh.70 billion/= (€625 million) will be the largest single private investment in Kenya’s history. With a power tariff of Euro 7.52 cents per kWh (11 KSh/kWh), LTWP is one of the lowest power tariffs in Kenya along with geothermal power at KSh.9/=. Other prices are KSh.3/= for hydro and KSh.18/= for oil. It is estimated that Kenya will save up to $120 million a year in fuel cost by reducing reliance on diesel power plants. LTWP’s contract (Power Purchase Agreement) with government-owned Kenya Power obliges the utility to buy all electricity produced by the wind farm, even if it is not needed, or if more economic electricity sources are available; "The power produced will be bought at a fixed price by Kenya Power (KPLC) over a 20-year period in accordance with the signed Power Purchase Agreement (PPA)." Furthermore, the Kenyan Government has signed guarantees with LTWP to cover costs in case Kenya Power cannot afford to pay for excess electricity for the duration of the PPA. In order to mitigate this risk the
African Development Fund The African Development Bank Group (AfDB) or (BAD) is a multilateral development finance institution headquartered in Abidjan, Ivory Coast, since September 2014. The AfDB is a financial provider to African governments and private companies in ...
has provided a 'partial risk guarantee' up to the value of €20 million. The Kenyan Government is also liable for losses incurred by delay due to political causes or project failure, as happened with the power line. These costs, as well as the expenses for the transmission line, are therefore likely to be passed on to Kenyan taxpayers and electricity consumers on top of the electricity produced. Before the power station opened, some feared that this could result in higher prices for electricity users than previous rates. For the fiscal year of 2019, Kenya Power paid KSh.11 billion/= to LTWP for 1.1 TWh.


Grid stability

The LTWP project is of such a large scale that it will provide up to 20% of the Kenyan power grid’s capacity to absorb wind energy. It is generally accepted in wind technology research that intermittent resources can destabilise a small grid such as that in Kenya, especially if it is concentrated all in one location. Denmark has over 19% wind power (wind capacity of 4,885MW) connected to the grid, but this capacity is supplied across thousands of projects. While LTWP aims to provide 310 MW of reliable, low cost wind power to the Kenya national grid, equivalent to approximately 18% of Kenya’ current installed electricity generating capacity. As of 2018, Kenya had a total installed capacity of 2300 MW, largely being generated by hydro (46.3%) and thermal (37.4%). The Government targets to increase generating capacity to 6762 MW in 2017. Kenya also plans to change the energy generation mix, with a view of reducing dependency on hydro and thermal. LTWP will play a key role in balancing the energy generation mix. In January 2021 ''Clir Renewables'', a Canadian software company based in
Vancouver, British Columbia Vancouver ( ) is a major city in western Canada, located in the Lower Mainland region of British Columbia. As the List of cities in British Columbia, most populous city in the province, the 2021 Canadian census recorded 662,248 people in the ...
, signed a contract with LTWP, to optimise power generation at the power station. The software company will analyse data from each of the 365 turbines at the power station. Fluctuations in wind speed at each turbine will be detected and mapped. Causes of underperformance at each turbine will be identified and solutions suggested. The overall objective is to improve the efficiency of the power plant and improve power output and grid stability.


Controversies


Indigenous rights issues

LTWP commenced its community engagement activities in 2005, nine years before construction started in October 2014. Local Turkana communities filed a lawsuit against LTWP in October 2014 at Meru High Court, Kenya to nullify the titles obtained by the company and return the land to its original status as community land. In November 2016 Justice Peter Njoroge of the Meru High Court rejected the application filed by Marsabit residents, requesting the court to stop the Wind Power project. In 2015 the intertribal Sarima Indigenous Peoples’ Land Forum (SIPLF) was created as an attempt to bring indigenous communities together in order to stop the wind power project. The forum is named after the village of Sarima that was displaced by the project. In their ''Declaration of 7th February 2015'' the SIPLF stated the "
El Molo The El Molo, also known as Elmolo, Dehes, Fura-Pawa and Ldes, are an ethnic group mainly inhabiting the northern Eastern Province of Kenya. They historically spoke the El Molo language as a mother tongue, an Afro-Asiatic language of the Cushitic ...
, Rendille, Samburu, Turkana and other indigenous and
pastoralist Pastoralist may refer to: * Pastoralism, raising livestock on natural pastures * Pastoral farming, settled farmers who grow crops to feed their livestock * People who keep or raise sheep, sheep farming Sheep farming or sheep husbandry is the r ...
communities of
Laisamis Constituency Laisamis Constituency is an electoral constituency in Kenya. It is one of four constituencies in Marsabit County Marsabit County is a county in Kenya. Covering a surface area of 66,923.1 square kilometres. Marsabit is the second largest count ...
and Karare Ward, in Marsabit County, Northern Kenya, reject the illegal privatization of of our ancestral land by the European consortium 'Lake Turkana Wind Power Limited'". The SIPLF stated they were not against wind farm development, if they own and lead the business: "We are determined to make this happen on the basis of our communities' ownership and leadership. We won't allow the theft of our land under any circumstance".


Social and Environmental Impacts

Negative
social Social organisms, including human(s), live collectively in interacting populations. This interaction is considered social whether they are aware of it or not, and whether the exchange is voluntary or not. Etymology The word "social" derives from ...
and
environmental A biophysical environment is a biotic and abiotic surrounding of an organism or population, and consequently includes the factors that have an influence in their survival, development, and evolution. A biophysical environment can vary in scale f ...
impacts have also been highlighted in LTWP’s own ''Environmental and Social Impact Assessment'' (ESIA) which would have serious implications for the social, cultural, economic and political well-being of the communities affected. LTWP documents detail plans for the construction of a new "camp" for 2,500 construction site workers. LTWP states that these workers will be employed local workers, trained for the job. However, this part of Northern Kenya lacks enough people to provide the labour so LTWP will need to employ most of these workers from outside the local area. According to the ESIA, there are a number of potential negative local impacts due to the arrival of the 2,500 workers and the construction work in general. These include: cultural contamination, increased risk of disease, community conflicts, challenges of labour force management, occupational hazards, increase in antisocial behavior, increased demand for wood resources in an area with an already "acute shortage", sanitation and waste disposal problems, and a decreased
livestock Livestock are the domesticated animals raised in an agricultural setting to provide labor and produce diversified products for consumption such as meat, eggs, milk, fur, leather, and wool. The term is sometimes used to refer solely to animals ...
grazing In agriculture, grazing is a method of animal husbandry whereby domestic livestock are allowed outdoors to roam around and consume wild vegetations in order to convert the otherwise indigestible (by human gut) cellulose within grass and other ...
area. However, the project's positive social impacts have outweighed the negative ones and the project continues to share project benefits with the local communities through its Winds of Change Foundation. Some locals were informed about the project in 2007, while others expressed a lack of information. 1180 people of the Sarima village were relocated and compensated with KSh.13,000/= (approximately €113), while Samburu people expressed appreciation of the project.


Capacity charge

In August 2017, the
Daily Nation The ''Daily Nation'' is the highest circulation Kenyan independent newspaper with 170,000 copies. History The ''Daily Nation'' was started in the year 1958 as a Swahili language, Swahili weekly called ''Taifa'' by the Englishman Charles Hay ...
reported that the owners of this power station had, in January 2017, started to bill the Kenya Power Company a monthly "capacity charge" of KSh.700 million/= (approx. US$7 million), for power produced by the power station that cannot be evacuated due to lack of a high voltage line to transmit it to the substation at Suswa. Following negotiations, in September 2017, the
government of Kenya , image = , caption = Coat of arms of Kenya , date = 1963 , jurisdiction = Republic of Kenya , url = http://www.mygov.go.ke/ , legislature = Parliament of Kenya , meeting_place = ...
agreed to pay the developers of Lake Turkana Wind Power station, a total of KSh.5.7 billion/= (approx. US$55.83 million), in monthly installments, spread over a six-year period. The monthly payment will amount to KSh.78,600,000/= (approx. US$769,833). The monthly surcharge will be passed on to the consumers, beginning in May 2018, when the high-voltage power line is expected to be completed. The transmission line was completed and connected to the national grid on 24 September 2018. The delays attracted total penalties of KSh.14.5 billion/= (€127 million at that time). In a deal struck in 2017, Kenya committed to pay KSh.5.7 billion/= (€46 million at the time) of the total penalty in lump sum, while the balance of KSh.9.25 billion/= (€81 million under prevailing rates) was to be paid over a period of six years through a tariff increase to the electricity consumers.


See also


References


External links


Oh no! Not the World Bank again!
As of 21 October 2012.
Lake Turkana Wind Power

Ministry of Energy and Petroleum (Kenya)


* [http://cdm.unfccc.int/Projects/DB/SGS-UKL1298369167.94/view United Nations Framework Conventions on Climate Change (UNFCCC)- Clean Development Mechanism (CDM) Project 4513 : Lake Turkana 310 MW Wind Power Project]
Current wind conditions
{{Africa topic, Renewable energy in Marsabit County Wind farms in Kenya Power stations in Kenya Energy infrastructure in Africa 2018 establishments in Kenya Energy infrastructure completed in 2018