The MRT Orange Line ( th, รถไฟฟ้ามหานคร สายสีส้ม) is a
rapid transit line of the
Mass Rapid Transit Authority of Thailand (MRTA) in the
Bangkok Metropolitan Area,
Thailand. When fully completed, the MRT Orange line will be 35.9 km long with 29
stations
Station may refer to:
Agriculture
* Station (Australian agriculture), a large Australian landholding used for livestock production
* Station (New Zealand agriculture), a large New Zealand farm used for grazing by sheep and cattle
** Cattle statio ...
(7 stations will be elevated for 8.9 km and 22 will be underground for 27 km), including an interchange with the current
Thailand Cultural Centre Station of
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
).
The line is divided into two sections; the 22.5 km Eastern section from Suwinthawong to Thailand Cultural Centre and the 2nd phase, 13.4 km Western section from Thailand Cultural Centre to Bang Khun Non. Construction of the 22.5 km Eastern Section started in June 2017. The line is scheduled to open in 2023.
By the end of November 2022, construction had progressed to 98.31%.
Western extension tender delayed
On 3 July 2020, the MRTA released the tender for the design and construction of the Western extension.
However in late August 2020, the tender submission deadline was subsequently delayed.
and the MRTA amended the tender assessment criteria resulting in a lawsuit and an injunction suspending the tender decision.
The tender was subsequently cancelled by the MRTA in February 2021 given ongoing litigation by the BTSC.
After approval by the Administrative Court given ongoing litigation, a new tender issued in October has a deadline for bids of January 2022.
The Criminal Court - Corruption and Malfeasance Division hearing into the cancelled tender process was conducted in late December 2021 which further delayed the reissued tender timeframe. Subject to court approval, the MRTA planned to review tender bids for a period of 3 months before seeking Cabinet approval for a reissued tender in April or May 2022. The MRTA reissued the new tender on 24 May 2022 with tender packages available for purchase until 10 June.
14 different companies purchased the auction envelopes.
The 141 billion baht western extension consists of 86 billion baht for civil works, 14 billion for land appropriation and 31 billion for systems installation, rolling stock and maintenance. The winning bidder is expected to be announced in August 2022.
Route Alignment
The MRT Orange Line starts at Suwinthawong rd in
Min Buri District in Bangkok's eastern suburbs as an elevated line running along Ramkhamhaeng Road. It will interchange with the future
MRT Yellow Line at Lam Sali station. It then proceeds underground near Lam Sali intersection in
Bang Kapi District
Bang Kapi ( th, บางกะปิ, ) is one of the 50 districts (''khet'') of Bangkok, Thailand. It is bounded by other Bangkok districts (from north clockwise): Bueng Kum, Saphan Sung, Prawet, Suan Luang, Huai Khwang, Wang Thonglang, and ...
, where there will be a transfer to the
MRT Yellow Line. It continues southwest along Ramkhamhaeng Road, passing
Hua Mak Stadium and
Ramkhamhaeng University
Ramkhamhaeng University (RU) ( th, มหาวิทยาลัยรามคำแหง) is Thailand's largest public university. It was named in honour of King Ramkhamhaeng the Great of Sukhothai. The university provides an effective and e ...
to Rama IX rd intersection. The line then proceeds west along Rama IX rd and crosses Pradit Manutham Road to the current
Mass Rapid Transit Authority of Thailand (MRTA) Headquarters and MRT Blue line depot. Then it routes north to the
Thailand Cultural Centre Station to interchange with the
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
.
The western section of the MRT Orange Line, runs west from
Thailand Cultural Centre Station via Din Daeng housing estates and Bangkok City Hall 2 to
Vibhavadi Rangsit Road, Sam Liam Din Daeng Junction. Then turns left into Ratchaprarop Road towards Pratu Nam and turns right into Phetchaburi Road then interchanges with BTS
Sukhumvit Line
The Sukhumvit line ( th, รถไฟฟ้า สายสุขุมวิท) or Light Green line, is an elevated metro rail line of the BTS Skytrain in Bangkok, Thailand. From the central Siam Station, where it connects with the Silom Lin ...
at
Ratchathewi Station
Ratchathewi station ( th, สถานีราชเทวี, ) is a BTS skytrain station, on the Sukhumvit Line in Ratchathewi District, Bangkok, Thailand. The station is located on Phaya Thai Road to the south of Ratchathewi intersection, abo ...
. It continues along Lan Luang Road and
Ratchadamnoen Avenue
Ratchadamnoen Avenue ( th, ถนนราชดำเนิน, , , also spelled Rajdamnern) is a historic road in the Phra Nakhon and Dusit Districts of Bangkok, Thailand. Ratchadamnoen Avenue may be the most politically charged thoroughfare ...
, then crosses the
Chao Phraya River
The Chao Phraya ( or ; th, แม่น้ำเจ้าพระยา, , or ) is the major river in Thailand, with its low alluvial plain forming the centre of the country. It flows through Bangkok and then into the Gulf of Thailand.
Et ...
near
Phra Pinklao Bridge, passes
Siriraj Hospital
Siriraj Hospital ( th, โรงพยาบาลศิริราช; ) is the oldest and largest hospital in Thailand. It is in Bangkok on the west bank of the Chao Phraya River, opposite Thammasat University's Tha Phrachan campus. It is the ...
and goes along
Bangkok Noi Rail line and terminates at Bang Khun Non at Charan Sanitwong rd, where it interchanges with the
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
.
History
The original plan of the MRT Orange Line aimed to serve travel demand between the northwestern area of
Thonburi, at Bang Bamru Railway Station in
Bang Phlat District, and the east of
Bangkok in
Bang Kapi District
Bang Kapi ( th, บางกะปิ, ) is one of the 50 districts (''khet'') of Bangkok, Thailand. It is bounded by other Bangkok districts (from north clockwise): Bueng Kum, Saphan Sung, Prawet, Suan Luang, Huai Khwang, Wang Thonglang, and ...
. It was planned to run along Ramkhamhaeng Road and
Ratchawithi Road, passing many public places like
Hua Mak Stadium,
Dusit Zoo and
Victory Monument, and provide access to universities including
Ramkhamhaeng University
Ramkhamhaeng University (RU) ( th, มหาวิทยาลัยรามคำแหง) is Thailand's largest public university. It was named in honour of King Ramkhamhaeng the Great of Sukhothai. The university provides an effective and e ...
, Suan Sunandha and Suan Dusit
Rajabhat University
The Rajabhat Universities (, ) mean normal universities in Thailand.
They were formerly called ''Rajabhat Institutes'' and originally formed the teachers college system. In 2005, King Bhumibol Adulyadej collectively elevated them to be universit ...
and many government offices.
In 2009, the proposed MRT Brown line from Bang Kapi District, elevated along Ram Khamhaeng Road, to the eastern
suburb
A suburb (more broadly suburban area) is an area within a metropolitan area, which may include commercial and mixed-use, that is primarily a residential area. A suburb can exist either as part of a larger city/urban area or as a separate ...
in
Saphan Sung District
Saphan Sung ( th, สะพานสูง, ) is one of the 50 districts (''khet'') of Bangkok, Thailand. Located on the eastern part of the capital, it is bounded by other Bangkok districts (from north clockwise): Khan Na Yao, Min Buri, Lat Kra ...
and
Min Buri District, was merged with the Orange Line in Bangkok's mass rapid transit master plan. In July 2011, the section from Bang Khun Non to Taling Chan was finally scrapped in favour of the
SRT Light Red Line
The SRT Light Red Line, or Nakhon Withi Line ( th, รถไฟชานเมือง นครวิถี) is part of the SRT Red Lines suburban railway system serving the greater Bangkok Metropolitan Region running for 15 km between K ...
spur line which duplicates the same route.
In 2012, there were further notable changes made to the central and western sections of the Orange Line. The section from
Din Daeng District to Bang Bamru was rerouted away from Victory Monument and Ratchawithi road route to further run south to
Pratunam
Pratunam, written as Pratu Nam ( th, ประตูน้ำ, ), is an intersection and neighborhood in Bangkok. It is located in Thanon Phaya Thai sub-district, Ratchathewi district. It is the intersection of Phetchaburi, Ratchadamri and Ratch ...
and then west along Petchaburi Road and Larn Luang Road. Continuing farther west along
Ratchadamnoen Klang Road
Ratchadamnoen Avenue ( th, ถนนราชดำเนิน, , , also spelled Rajdamnern) is a historic road in the Phra Nakhon and Dusit Districts of Bangkok, Thailand. Ratchadamnoen Avenue may be the most politically charged thoroughfar ...
and
Sanam Luang before passing under the
Chao Praya river and finally terminating at Bang Khun Non to interchange with the
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
extension.
The MRT Orange line Eastern section was originally planned to be tendered by the end of 2013. However, due to protests by residents regarding station footprint and compulsory land acquisition around stations at Pratunam, Ratchaprarop, Pracha Songkhro and Soesim stations the MRTA needed another 12 months to redesign sections of the line. Subsequently, political protests against the Thai government led to the metro transport funding bill lapsing when parliament was dissolved in December 2013. On 9 December 2015, Cabinet finally approved the Orange Line. On 19 April 2016, the Cabinet further approved a budget of 82.9 billion baht for Phase 1 Eastern section to build 17 stations and 22.5 km of rail from the Thailand Cultural Centre to Minburi, of which 12.2 km will be underground and 9 km will be elevated.
Construction Progress
Construction contracts were signed on 9 February 2017 between the MRTA and CKST Joint Venture consortium. Construction finally started in June 2017 with a 1980 day construction period with a scheduled opening in October 2022. Project construction is divided into 4 contracts. The eastern section new planned opening date is 2023.
As of 31 December 2017, the progress of civil works construction was at 4.66% according to the MRTA. As of July 2018, overall construction progress was 13.57%. As of August 2018, overall construction progress was 16.21%. By 30 September 2018, overall construction had progressed to 18.33%. At the end of March 2019, construction had progressed to 32.12%. At the end of July 2019, civil construction was at 42.27%. At the end of October 2019, construction had progressed to 49.05%. At the end of January 2020, construction had progressed to 54.93%. By the end of May 2020, construction had progressed to 62.42%. At the end of July 2020, construction had progressed to 66.06%. On 5 October 2020, TBM number 2 finished tunneling and reached Ramkhamhaeng 12 station box as part of contract 2. At the end of September 2020, was at 69.82%. At the end of January 2020, construction had progressed to 76.09%. Construction progress was 79.44% complete by the end of March 2021. Construction progress was 81.03% by the end of April 2021. Construction progress was 87.24% by the end of October 2021. Construction progress was 88.46% by the end of November 2021. By the end of March 2022, construction progress was at 92.69%.
By the end of May 2022, construction had progressed to 94.51%.
[https://www.facebook.com/MRTOrangeLineEast/photos/a.258445614634797/1357270614752286 ''MRTA Press'', 8 June 2022 ]
Construction contracts
Construction is divided into four separate contracts.
Contract 1 is for 6.29 km underground and 4 underground stations from Thai Cultural Centre interchange station to Rankhamhaeng 12 station.
Contract 2 is for 3.44 km underground and 4 underground stations from Ramkhamheang 12 station to Hua Mark station.
Contract 3 is for 4.04 km underground and 3 underground stations from Hua Mark station to Klong Ban Ma station.
Contract 4 is 8.8 km and 7 elevated stations from Klong Ban Ma to Suwinthawong terminus station.
Rolling stock
The tender for operation of the line and purchase of rolling stock for both the eastern and western sections was issued in May 2022, along with the construction of the western section.
Phase 2 Western Extension
The Phase 2 Western extension of the Orange line will run from Thailand Cultural Centre to Bang Khun Non via Pratunam. The 13.4 km western section will run underground with 12 stations.
The Thai Cabinet was expected to approve the 121 billion baht budget for the Western extension in mid 2017 with a tender due for the 2nd half of 2017. However, this decision was delayed until 2018 as Cabinet requested options to be considered for a joint public and private investment proposal. There were further delays into 2019, but the MRTA finalised a joint PPP plan for Cabinet to approve in mid 2019. On 28 January 2020, the Cabinet approved the 142 billion baht extension. It is expected to open in February 2026 and serve 439,000 passengers daily.
On 3 July 2020, the MRTA released the tender for the design, construction and operation of the Western extension as a Public-Private Partnership project on a 30 year lease.
The tender deadline was 23 September 2020 with the successful bidder to be announced in early October 2020. The tender specified a construction period of 3 and a half years.
There were 10 tenderers that purchased the request for proposal (RFP) form with two major consortiums that submitted final bids:
* Bangkok Expressway and Metro Public Company Limited (BEM) - operator of the
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
and
MRT Purple Lines.
* BSR Consortium, led by Bangkok Mass Transit System Public Company Limited (BTSC), and supported by BTS Group Holdings (BTS Group) and Sino-Thai Engineering and Construction (STECON). BTSC is the future operator of the
MRT Pink Line and
MRT Yellow Lines which are both under construction.
However, in late August 2020 the tender submission deadline was subsequently delayed by the MRTA.
Thereafter, the MRTA amended the tender assessment criteria resulting in a lawsuit being lodged by the BTSC in the Administrative Court on 17 September 2020 with the Court imposing an injunction suspending the tender decision.
The tender was subsequently cancelled by the MRTA in February 2021 due to litigation by the BTSC.
After approval by the Administrative Court given ongoing litigation, a new tender issued in October has a deadline for bids of January 2022.
The Criminal Court Corruption and Malfeasance division hearings into the cancelled tender process were conducted from 14 to 24 December 2021 and have delayed the reissued tender timeframe. Subject to court approval, the MRTA plans to review tender bids for a period of 3 months before seeking final Cabinet approval of the winning bid in April 2022. However, there are construction budget concerns for the extension as steel prices have increased by 40% since the previous budget was approved. The EIA for the western extension was also updated in December 2021 as Din Daeng station was moved north by 500m, Pracha Songkhro station was moved east by 450m and Yommarat station was redesigned.
The MRTA reissued the new tender auction on 24 May with tender packages available for purchase until 10 June.
The 141 billion baht western extension consists of 86 billion baht for civil works, 14 billion for land appropriation and 31 billion for systems installation, rolling stock and maintenance. The MRTA announced in September 2022 that the BEM-led consortium had submitted the most financially favorable bid of the two remaining bidders.
Stations
Network Map
See also
*
Mass Rapid Transit Master Plan in Bangkok Metropolitan Region
The Mass Rapid Transit Master Plan in Bangkok Metropolitan Region, or M-Map, is the latest version in a series of Thai government plans for the development of an urban rail transit network serving the Greater Bangkok area. It was drafted under the ...
*
MRT (Bangkok)
*
MRT Blue Line
The MRT Blue Line ( th, รถไฟฟ้า สายสีน้ำเงิน) or MRT Chaloem Ratchamongkon Line ( th, รถไฟฟ้ามหานคร สายเฉลิมรัชมงคล) is Bangkok's third rapid transit li ...
*
MRT Brown Line
*
MRT Grey Line
*
MRT Light Blue Line
The Light Blue Line (Din Daeng – Sathon) is a planned monorail line to be built in Bangkok, Thailand. Its path runs along a north–south axis. This line would link the Din Daeng housing community areas, Bangkok City Hall 2, Makkasan Station ( ...
*
MRT Pink Line
*
MRT Purple Line
*
MRT Yellow Line
*
BTS Skytrain
The Bangkok Mass Transit System, commonly known as the BTS Skytrain ( th, รถไฟฟ้าบีทีเอส '' TS'), is an elevated rapid transit system in Bangkok, Thailand. It is operated by Bangkok Mass Transit System PCL (BTSC), a ...
*
Sukhumvit Line
The Sukhumvit line ( th, รถไฟฟ้า สายสุขุมวิท) or Light Green line, is an elevated metro rail line of the BTS Skytrain in Bangkok, Thailand. From the central Siam Station, where it connects with the Silom Lin ...
*
Silom Line
*
Airport Rail Link (Bangkok)
The Airport Rail Link (ARL) ( th, รถไฟฟ้าแอร์พอร์ต เรล ลิงก์) is an express and commuter rail line in Bangkok, Thailand. The line provides an airport rail link from Suvarnabhumi Airport, via Mak ...
*
SRT Dark Red Line
The SRT Dark Red Line, or Thani Ratthaya Line ( th, รถไฟชานเมือง สายธานีรัถยา) is part of the SRT Red Line suburban railway system to serve the greater Bangkok Metropolitan Region running for 26 ...
*
SRT Light Red Line
The SRT Light Red Line, or Nakhon Withi Line ( th, รถไฟชานเมือง นครวิถี) is part of the SRT Red Lines suburban railway system serving the greater Bangkok Metropolitan Region running for 15 km between K ...
*
Bangkok BRT
*
BMA Gold Line
*
BMA Bang Na-Airport Line
References
External links
"MRT Orange Line Eastern Section"MRTA
{{DEFAULTSORT:Mrt Orange Line
Proposed public transport in Thailand
Orange line
2024 in rail transport