Environmental stress screening (ESS) refers to the process of exposing a newly manufactured or repaired product or component (typically
electronic Electronic may refer to: *Electronics, the science of how to control electric energy in semiconductor * ''Electronics'' (magazine), a defunct American trade journal *Electronic storage, the storage of data using an electronic device *Electronic co ...
) to stresses such as thermal cycling and
vibration Vibration is a mechanical phenomenon whereby oscillations occur about an equilibrium point. The word comes from Latin ''vibrationem'' ("shaking, brandishing"). The oscillations may be periodic function, periodic, such as the motion of a pendulum ...
in order to force latent defects to manifest themselves by permanent or
catastrophic failure A catastrophic failure is a sudden and total failure from which recovery is impossible. Catastrophic failures often lead to cascading systems failure. The term is most commonly used for structural failures, but has often been extended to many oth ...
during the screening process. The surviving population, upon completion of screening, can be assumed to have a higher reliability than a similar unscreened population.


Overview

Developed to help electronics manufacturers detect
product defect A product defect is any characteristic of a product which hinders its usability for the purpose for which it was designed and manufactured. Product defects arise most prominently in legal contexts regarding product safety, where the term is applie ...
s and production flaws, ESS is widely used in military and aerospace applications, less so for commercial products. The tests need not be elaborate, for example, switching an electronic or electrical system on and off a few times may be enough to catch some simple defects that would otherwise be encountered by the end user very soon after the product was first used. Tests typically include the following: * Temperature variations * Vibration tests * Pressure * Flexibility tests ESS can be performed as part of the
manufacturing process Manufacturing is the creation or production of goods with the help of equipment, labor, machines, tools, and chemical or biological processing or formulation. It is the essence of secondary sector of the economy. The term may refer to a ran ...
or it can be used in new product qualification testing. An ESS system usually consists of a
test chamber An environmental chamber, also called a climatic chamber or climate chamber, is an enclosure used to test the effects of specified environmental conditions on biological items, industrial products, materials, and electronic devices and components ...
, controller, fixturing, interconnect and wiring, and a functional tester. These systems can be purchased from a variety of companies in the environmental test industry. The stress screening from this process will help find infant mortality in the product. Finding these failures before the product reaches the customer yields better quality and lower warranty expenses. Associated military terminology includes an operational requirements document (ORD) and
ongoing reliability test The ongoing reliability test (ORT) is a hardware test process usually used in manufacturing to ensure that quality of the products is still of the same specifications as the day it first went to production or general availability. The products cu ...
ing (ORT).


Standardized Definitions and Methods

The following is extracted from a paper on ESS testing prepared by the
U.S. Air Force The United States Air Force (USAF) is the air service branch of the United States Armed Forces, and is one of the eight uniformed services of the United States. Originally created on 1 August 1907, as a part of the United States Army Sign ...
to provide standardized definitions and methods.


Introduction

The purpose of this paper is to provide standardized definitions and a roadmap of test processes for the Environmental Stress Screening (ESS) of replacement and repaired components used on Air Force systems. The term “component” is used interchangeably with the term “unit” and includes
Line-replaceable unit A line-replaceable unit (LRU), lower line-replaceable unit (LLRU), line-replaceable component (LRC), or line-replaceable item (LRI) is a modular component of an airplane, ship or spacecraft (or any other manufactured device) that is designed to b ...
(LRU) and sub-units (SRU). A component selected for testing is a Unit Under Test (UUT). Operational Safety, Suitability, and Effectiveness (OSS&E) policy and instructions require consistency in the disciplined engineering process used to ensure that activities such as maintenance repairs and part substitutions do not degrade system or end-item baselined characteristics over their operational life. Baselined characteristics are highly dependent on reliability, which is verified and maintained by ESS testing. OSS&E policy and instructions also require consistent engineering processes to ensure manufacturing and repair entities are accountable for delivering quality products, and to provide selection and qualification criteria for new sources of supply. Determinations of product quality and source capabilities usually require ESS testing. While considerable information concerning ESS methods and procedures is available including
United States Military Standard A United States defense standard, often called a military standard, "MIL-STD", "MIL-SPEC", or (informally) "MilSpecs", is used to help achieve standardization objectives by the U.S. Department of Defense. Standardization is beneficial in achievin ...
s, handbooks, guides, and the original equipment manufacturer's test plans, often these publications use differing and confusing definitions for the testing phases where ESS is applied. Lengthy explanations were needed to clarify contract clauses citing these publications. This paper ensures testing requirements are uniformly applied and clearly understood in writing source qualification requirements and contracts.


Visual Inspection


Purpose

To ensure that good workmanship has been employed and that the UUT is free of obvious physical defects.


Method

Visually inspect UUT before and after each manufacturing, repair, and test operation. *Verify proper labeling, weight, and dimensions. *With the unaided eye, inspect all accessible areas of the UUT. *Under 10X minimum magnification, inspect all critical surfaces and interfaces of the UUT.


Pass/Fail Criteria

Workmanship shall meet the applicable standards including T.O. 00-25-234https://www.robins.af.mil/Portals/59/documents/technicalorders/00-25-234.pdf?ver=2018-09-05-144121-517 and shall be free of obvious physical defects. A unit that exhibits any sign that a part is stressed beyond its design limit (cracked circuit boards, loose connectors and/or screws, bent clamps and/or screws, worn parts, etc.) is considered to have failed even if the UUT passes the Functional Testing.


Functional Testing


Purpose

Done before, during, and after ESS testing to verify that the UUT is functioning within design tolerances.


Method

Applying an input signal or stimulus and measuring the output.


Pass/Fail Criteria

Output responses/signals must be within technical data specifications, and the UUT must operate satisfactorily in the next higher assembly.


Environmental Stress Screening (ESS)


Purpose

Testing at the physical environmental conditions (shock, vibration, temperature, altitude, humidity, etc.) that simulate those encountered over the operational life of the component. Random vibration and temperature cycling have proven to be the most successful forms of ESS in terms of effective flaw precipitation.


Method

A stress profile is developed and applied to the UUT. The profile simulates the environmental conditions encountered during transportation, storage, handling, and operational use phases. The UUT is configured to match the phase, e.g. transportation shocks are applied with the UUT in the shipping container, operational use temperature cycles are applied with the UUT operating.


Pass/Fail Criteria

The UUT (Unit Under Test) must pass Functional Testing and Visual Inspection before, during, and after ESS.


Qualification ESS

The testing of a production-representative unit to demonstrate that the design, manufacturing, assembly, and repair processes have resulted in hardware that conforms to the specification. Satisfactory completion of Qualification Testing denotes readiness for further stages of testing. Limited flight testing may be acceptable before completion of all phases of Qualification Testing.


Production Unit Qualification Testing

*Purpose: Done for qualification of a new manufacturer, design, process, or facility to ensure the adequacy and suitability of the design to reliably operate during and after exposure to environmental stresses that exceed operational environment predictions by a prescribed margin. *Method: Per
Mil-Std-810 MIL-STD-810, U S Department of Defense Test Method Standard, Environmental Engineering Considerations and Laboratory Tests, is a United States Military Standard that emphasizes tailoring an equipment's environmental design and test limits to the ...
G for LRUs and SRUs, per Mil-Std-202G for electronic piece parts, per Mil-Std-1540 for space systems, and per
Mil-Std-883 The MIL-STD-883 standard establishes uniform methods, controls, and procedures for testing microelectronic devices suitable for use within military and aerospace electronic systems including basic environmental tests to determine resistance to dele ...
H for microelectronic devices. EMI/RFI Testing is usually included in ESS Qualification Testing and requires application of
MIL-STD 461 MIL-STD-461 is a United States Military Standard A United States defense standard, often called a military standard, "MIL-STD", "MIL-SPEC", or (informally) "MilSpecs", is used to help achieve standardization objectives by the U.S. Department of ...
E. These Military Standards require tailoring. Mil-HDBKs-340, 343, 344 and 2164 provide detailed guidance. Sequence of First Production Article testing: Visual Inspection and Functional – Preconditioning – Acceptance ESS – Acceptance Reliability – Visual Inspection & Functional – Qualification ESS – Visual Inspection & Functional –Qualification Reliability – Visual Inspection & Functional. *Note: Qualification Testing usually includes ‘aggravated’ ESS testing, i.e. test to actual environmental levels and duration plus a margin (typically 10 °C, 6 dB). Adding margin is required due to the statistically small sample size and uncertainties in actual environmental levels. Since this is a
destructive test In destructive testing (or destructive physical analysis, DPA) tests are carried out to the specimen's failure, in order to understand a specimen's performance or material behavior under different loads. These tests are generally much easier to car ...
, the UUT shall never be fielded in operational systems. *Note: Must do Acceptance Testing including Pre-Conditioning first. This is because these tests are done on all production units and so become parts of the environmental stress profile. *Note: Another manufacturer (second-source) building the same unit or a replacement unit that is intended as a form-fit-and-function replacement for the original unit or unit sub-assembly must be qualified to specifications equivalent to those used for the original source.


Repaired Unit Qualification Testing

*Purpose: Performed on First Repaired Article or Pre-Qualification Repaired Article units to qualify a new repair source or repair method. It is also performed to evaluate substitute piece parts. *Method: If the repair parts and processes are equivalent to the original manufacturing parts and processes, then use the Repaired Unit Acceptance Test performed by the contractor, followed by Government inspection and operation in the next higher assembly. If the parts and processes are not known to be equivalent, then use applicable areas of the Production Unit Qualification Testing. Sequence of PreQual Repaired Article / First Repaired Article testing: Visual Inspection & Functional – Preconditioning – Acceptance ESS – Visual Inspection & Functional – Gov't Inspection & Functional. *Note: Due to Diminishing Manufacturing Sources (DMS), substitutions of piece parts are often necessary. Substitute parts that appear under ambient test bench conditions to function like the original parts can exhibit unsatisfactory performance in the operational environment. *Qualification by Similarity. Qualification of a replacement or repaired unit by similarity to the original unit requires that the units are essentially identical. In addition, the replacement unit must have previously been qualified by testing to environmental and operational performance requirements meeting or exceeding the environmental and operational requirements of the original unit.


Acceptance ESS

Formal tests conducted to demonstrate acceptability of the individual unit for delivery. They demonstrate performance to purchase specification requirements and act as quality control screens to detect deficiencies of workmanship and materials. The successful completion of such tests denotes acceptance of the unit by the procurement agency.


Production Unit Acceptance Testing

*Purpose: Done on 100% of new units to detect workmanship and process errors. Inspection of some microelectronic devices is destructive so lot sampling is used for acceptance testing (see paragraph 8.3.2). * Method: Tailored down from applicable Production Qualification Test but done to workmanship levels, no more severe than actual environmental levels and of shortened duration. Usually these tests are structured to include the Pre-Conditioning and Reliability Acceptance Testing requirements. Sequence for Components testing: Visual Inspection & Functional – Preconditioning – Acceptance ESS – Acceptance Reliability – Visual Inspection & Functional. *Note: Production Unit Acceptance Testing performance data is also used to evaluate "in-family" performance. While a UUT may meet all other Acceptance Test pass/fail criteria, results which deviate significantly from other units within the production lot shall require rejection of that unit.


Repaired Unit Acceptance Testing

*Purpose: Performed on 100% of repaired units to detect workmanship and process errors. *Method: Tailored down from applicable Production Acceptance Tests. To maintain the specified reliability criteria, Pre-Conditioning Testing should be included if the repair parts are not pre-conditioned or the repair workmanship can be expected to induce failures. Sequence for Components testing: Visual Inspection & Functional – Preconditioning – Acceptance ESS – Visual Inspection & Functional. *Note: Test levels are low and not destructive so testing may be repeated for test failures and subsequent repairs without significantly aging the UUT. *Note: Types and levels of testing may have to be increased if infant mortality failures are occurring in operational use. Conversely, if a statistically significant sampling demonstrates that infant mortality failures are not occurring, ESS tests may be reduced or eliminated. Functional Testing is still required. *Note: Testing must strike a balance between the probability that the repairs have induced a defect, and the probability that the testing can detect that defect. For example, a reduced number of temperature cycles has a lower probability of detecting a defect, but may be appropriate if the repair is minor and has little risk of inducing a defect. *Note: Repaired Unit Acceptance Testing performance data is also used to evaluate "in-family" performance. While a UUT may meet all other Acceptance Test pass/fail criteria, results which deviate significantly from other repaired units or from the original Production Unit Acceptance Test data shall require rejection of the UUT.


Reliability ESS

This should be part of the Qualification and Acceptance ESS when verification of reliability is required.


Reliability Qualification Testing

*Purpose: Done on the production qualification UUT to demonstrate life-cycle compliance with the reliability specifications per Mil-Std-781, and the original manufacturer's development specifications. *Method: Use Mil-Hdbk-781A. The UUT is usually tested to actual environmental levels, but margin is added if accelerated aging is required. *Note: Must do Acceptance Testing including Pre-Conditioning first. This is because these tests are done on all production units and so become parts of the environmental stress profile. *Note: The presence of redundancy in the design is not reason to eliminate reliability tests. Redundancy is used to compensate for any unknown and untested failure modes, and for damage tolerance. Redundancy only increases reliability by a small amount.


Reliability Acceptance Testing

*Purpose: Done on all production units to find any unit with reliability degradation due to daily variations in the production process and workmanship. *Method: Vibration (typically 0.04 G2/Hz for 5 minutes/axis) and temperature for 3+ cycles, last one failure-free. *Note: Usually only done on high reliability (3-sigma) and safety of flight items.


Pre-Conditioning Testing. Also called Burn-In Testing

*Purpose: Done on all active unit LRUs, SRUs, and piece parts (production, spare, and repair) to find ‘infant mortality’ of parts and workmanship. *Method: per Mil-Std-750D,
Mil-Std-883 The MIL-STD-883 standard establishes uniform methods, controls, and procedures for testing microelectronic devices suitable for use within military and aerospace electronic systems including basic environmental tests to determine resistance to dele ...
E, and Mil-Std-202G. *Note: Most mil-spec piece parts have not been pre-conditioned by the part manufacturer.


UUT Categories


Passive Unit

*Examples: chassis, antenna coupler, optics without moving parts, wiring harness. *Note: Requires Qualification ESS of the design and processes, usually in the next higher assembly. Acceptance Testing is limited to Visual Inspection and Operational Testing in the next higher assembly.


Active Unit

*Examples: PC board with solid state devices, electric motor, cathode ray tube, pressure vessel. *Note: Usually requires Qualification ESS and Acceptance ESS.


One-Shot and Limited Use Devices

*Examples: explosive, rocket propellant, gas generator, squib, battery. *Method: Qualification ESS is by exposure to qualification environmental levels, then operated to demonstrate capacity plus a margin. Acceptance ESS is typically done on 10% of the production lot (but not less than 10 units) by exposure to qualification environmental levels, then operated to demonstrate capacity plus a margin. Failure of one UUT requires rejection of the production lot. For explosive devices, test requirements and methods are tailored from MIL-HDBK-1512 and NATO AOP-7. For batteries, guidance on test requirements is in RCC-Doc-319-99. *Note: Surveillance Testing is a periodic repeat of the Acceptance Testing using trending or accelerated aging to authorize shelf life extensions. Trending involves frequent sampling and comparison to previous results to predict degradation. Accelerated aging involves stimulating known failure modes to detect degradation.


First Production Article

This is the UUT for Qualification ESS (typically three UUT are required). The UUT must be representative of the design, production line processes, materials, and workmanship.


First Repaired Article

Also called First Article. This is the UUT (typically four are required) that demonstrates that the repair source has the capability and processes to perform a satisfactory repair.


Pre-Qualification Article

*Pre-Qualification Production Article. Also called Pre-production Article. This is the UUT used for program risk reduction and to qualify key processes, technologies, etc. *Pre-Qualification Repaired Article. Also called Qual Article. This is the UUT (typically two are required) repaired by a potential repair contractor to meet, in part, the criteria to be on a Qualified Bidders List.


Tailoring

Tailoring is the formal engineering task of using existing technical data (requirements, standards, specifications, test plans, etc.) and selecting or modifying applicable areas to meet the requirements unique to the type of unit undergoing test. Non-applicable requirements are deleted. Other requirements may be added due to changes in Federal standards, identification of new hazards, modifications to the item, or changes in the mission/ESS profile. All areas of non-compliance with the technical data shall be identified by the contractor and a Requirements Tailoring Request (RTR) shall be submitted to the Government for each area. The RTR shall include thorough justification. Only the Government Engineering Authority for the component can accept an RTR.


Specifications and Standards Tailoring

Tailoring generally is to select the applicable areas, best test methods, or for use of an equivalent requirement.


Test Plan Tailoring

Tailoring generally is to change the test levels and durations, sequence of tests, or reporting requirements. Tailoring shall also identify any test requirements that are to be accomplished through analysis, similarity, or inspection.


MIC, Waiver, and Deviation

Each RTR shall be classified as a MIC, Waiver, or Deviation. *MIC. An RTR that still meets the intent of the specified technical data is classified as a Meets Intent Compliance (MIC). *Waiver. If an RTR potentially increases the safety hazards, it is classified as a Waiver and must also be accepted by the cognizant Government and contractor safety offices. The intent of a Waiver is to grant temporary approval to proceed while the hazard is being corrected. A series of unlikely, unrelated simultaneous failures is not considered a hazard. *Deviation. An RTR that does not increase safety hazards and is not a MIC is classified as a Deviation.


Relevant standards

* * * * * * * *


See also

*
Accelerated aging Accelerated aging is testing that uses aggravated conditions of heat, humidity, oxygen, sunlight, vibration, etc. to speed up the normal aging processes of items. It is used to help determine the long-term effects of expected levels of stress wit ...
*
Environmental chamber An environmental chamber, also called a climatic chamber or climate chamber, is an enclosure used to test the effects of specified environmental conditions on biological items, industrial products, materials, and electronic devices and components ...
*
Environmental tests {{noref, date=January 2021 Environmental testing is the measurement of the performance of equipment under specified environmental conditions, such as: * extremely high and low temperatures * large, swift variations in temperature * blown and settli ...
*
Failure analysis Failure analysis is the process of collecting and analyzing data to determine the cause of a failure, often with the goal of determining corrective actions or liability. According to Bloch and Geitner, ”machinery failures reveal a reaction chain o ...
*
United States Military Standard A United States defense standard, often called a military standard, "MIL-STD", "MIL-SPEC", or (informally) "MilSpecs", is used to help achieve standardization objectives by the U.S. Department of Defense. Standardization is beneficial in achievin ...
*
MIL-STD-810 MIL-STD-810, U S Department of Defense Test Method Standard, Environmental Engineering Considerations and Laboratory Tests, is a United States Military Standard that emphasizes tailoring an equipment's environmental design and test limits to the ...
"Department of Defense Test Method Standard for Environmental Engineering Considerations and Laboratory Tests" *
Highly accelerated stress screen A highly accelerated life test (HALT) is a stress testing methodology for enhancing product reliability in which prototypes are stressed to a much higher degree than expected from actual use in order to identify weaknesses in the design or manufa ...
*