The Boßler Tunnel is a railway tunnel currently under construction as part of the new Wendlingen–Ulm high-speed railway. The tunnel is approximately long, built as two parallel single-track tunnels. The tunnel runs between
Aichelberg Aichelberg is a municipality in the district of Göppingen in Baden-Württemberg in southern Germany. Aichelberg is between Stuttgart and Ulm at the ''Albaufstieg'', the slope of the Swabian Jura in 357–615 meters altitude. Characteristic of t ...
and Mühlhausen im Täle under the ''Roter Wasen'' and the Boßler mountain. It is one of a series of tunnels underneath the
Swabian Jura The Swabian Jura (german: Schwäbische Alb , more rarely ), sometimes also named Swabian Alps in English, is a mountain range in Baden-Württemberg, Germany, extending from southwest to northeast and in width. It is named after the region of ...
range. When completed, it will be the longest tunnel on the line and the fifth longest tunnel in Germany (after the
Landrücken Tunnel The Landrücken Tunnel is a railway tunnel on the Hanover-Würzburg high-speed rail line. With a length of it is the longest tunnel in Germany. Geography The tunnel is in east Hessen between the stations of Fulda and Würzburg. Between the nor ...
, the Münden Tunnel, the Filder Tunnel and the
Katzenberg Tunnel The Katzenberg Tunnel is a railway tunnel on the Karlsruhe–Basel high-speed railway that opened in December 2012. The tunnel was built to increase the capacity and speed of the Mannheim–Karlsruhe–Basel railway (Rhine Valley Railway, or ' ...
).


Route

The north-west portal (portal ''Aichelberg'', track location marker 39.720 km, ), situated northeast of Weilheim an der Teck, is the border of one of the line's planning sections. The line approaches this portal from the west, parallel to the A8 motorway. The tunnel runs in a straight line towards the southeast, passing under the ''Roter Wasen'' and the ''Boßler''. Hany Azer, B. Engel: ''Stuttgart 21 und NBS Wendlingen–Ulm''. In: ''Tunnel'', Heft 7/2009, , S. 12–24
PDF
290 kB).
Peter Marquart: ''Die Geologie weist ihren Weg – Tunnelbau in den Gebirgsformationen rund um Stuttgart und auf der Schwäbischen Alb''. In: ''geotechnik'', 27 (2004), Nr. 2, S. 99–103, . The tunnel climbs about to the southeast portal, with a gradient of about 25% (1 in 40). The maximum overburden depth is . The south-east portal (portal ''Buch im Filstal'', 48.076 km, ) is situated between Mühlhausen im Täle and Wiesensteig. The line exits the portal onto the Fils Viaduct across the A8.


History


Deciding between alternative routes

The tunnel is part of the ''Albaufstieg'' section of the line (track section 2.2), which involves an ascent of the Swabian Jura (also known in German as the ''Alb''). 25 alternative routes were initially considered for this section.''Planfeststellungsbeschluss gemäß § 18 Allgemeines Eisenbahngesetz (AEG) für die Aus- und Neubaustrecke Stuttgart – Augsburg Bereich Wendlingen – Ulm Planfeststellungsabschnitt 2.2, Albaufstieg km 39,270 – km 53,834''
(PDF; 1.3 MB). Stuttgart, 20. September 2011, S. 68, 78.
A plan drawn up in 1993 included an tunnel.Anonymous: ''Geplante Tunnel im Zuge der Neubaustrecke Stuttgart–Ulm''. In: ''Tunnel'', Volume 5/1993, , S. 288–292. A later, 1995 plan included an tunnel. Many alternative routes were considered for the Aichelberg to Widderstall corridor. As well as routes involving a combined rail and motorway tunnel and a direct route, local variations of the route in the Neidlingen, Wiesensteig and Westerheim districts were also considered. Peter Marquart: ''Die Entwicklung des Projektplanung''. In:
Regierungspräsidium Stuttgart Stuttgart is one of the four administrative districts (Regierungsbezirke) of Baden-Württemberg, Germany, located in the north-east of the state of Baden-Württemberg, in the southwestern part of Germany. It is sub-divided into the three regions: ...
(Hrsg.): ''Projekt Stuttgart 21 und NBS Wendlingen – Ulm: Die Berücksichtigung der Wasserwirtschaft in der Planung – eine Zwischenbilanz''. Tagungsband, 26. September 2006,
PDF
8 MB), S. 6–13.
The spatial planning provisions required to consider possible alternative routes for the ''Albaufstieg''. Eight different routes were examined in detail. In 1999 a hydrological evaluation of these variants was conducted. After a planning stop in 2000, a new integrated assessment was carried out in 2006 in the context of paths for combined traffic routes.Helmut Kobus: ''Die Entwicklung wasserwirtschaftlicher Probleme im Planungsprozess''. In:
Regierungspräsidium Stuttgart Stuttgart is one of the four administrative districts (Regierungsbezirke) of Baden-Württemberg, Germany, located in the north-east of the state of Baden-Württemberg, in the southwestern part of Germany. It is sub-divided into the three regions: ...
(Hrsg.):''Projekt Stuttgart 21 und NBS Wendlingen – Ulm: Die Berücksichtigung der Wasserwirtschaft in der Planung – eine Zwischenbilanz''. Tagungsband, 26. September 2006,
PDF
, 8 MB), S. 14–27.
In the middle of 1991 an early road design proposed the beginning of the tunnel already in Weilheim an der Teck.Deutsche Bundesbahn, Projektgruppe NBS der Bahnbauzentrale (Hrsg.): ''Information Ausbau- und Neubaustrecke Stuttgart – Augsburg''. Zwölfseitiges Leporello, Stuttgart, Juni 1991. while a length of 9 km was allotted for this part of ''Albaufstieg''. According to the planning status of 1993, an 8.8 km long tunnel was provided in this area. As of 2004 and 2007, the planned length was 8710 m. Plans of 2007 envisaged the building of an exploratory tunnel within the cross-section of the later final tunnel due to the prevalent geological conditions.Wolfgang Feldwisch: ''Großprojekte der Bahn als Herausforderung für den Tunnelbau''. In: ''Geotechnik'', 30 (2007), Nr. 4, , S. 217–225. In mid-August 2009, the consultation process for the 14.5 km long zoning section ''Albaufstieg'' to which the tunnel belongs, was completed by the regional council of
Stuttgart Stuttgart (; Swabian: ; ) is the capital and largest city of the German state of Baden-Württemberg. It is located on the Neckar river in a fertile valley known as the ''Stuttgarter Kessel'' (Stuttgart Cauldron) and lies an hour from the ...
and handed over to the Federal Railway Authority for final approval. In the process leading to approval, 82 public agencies were consulted, and 1150 private reservations were handled. The principal resulting changes affected the site logistics.''Der neue ICE-Trassenabschnitt "Albaufstieg" wird ab 2010 gebaut''.
In:
Der Teckbote Der Teckbote is a German daily newspaper for the Swabian town of Kirchheim unter Teck. History The Teckbote was founded in 1832 under the title ''Wochenblatt für den Oberamtsbezirk Kirchheim unter Teck'' (''Weekly Newspaper for the district of K ...
(Onlineausgabe), 22. August 2009.
In mid-2009, construction work was scheduled to start in 2010.


Dispute on use of tunnel boring machines

Due to the unstable rock, planning decisions initially ruled out the use of tunnel boring machines. However, according to entrepreneur Martin Herrenknecht their use could save 70 to 100 million euros over the originally tendered conventional methodKonstantin Schwarz: ''Herrenknecht greift die Bahn-Planer an''. In:
Stuttgarter Nachrichten ''Stuttgarter Nachrichten'' (''Stuttgart News'') is a newspaper that is published in Stuttgart-Möhringen, Germany. It sells together with the ''Stuttgarter Zeitung The ''Stuttgarter Zeitung'' ("Stuttgart newspaper") is a German-language ...
, Nr. 185, 11. August 2012, S. 22
online
.
The company obtained expert opinion at their own cost, and thus achieved the approval of mechanical tunneling. Together with the excavation of Filder tunnel, 80 to 100 million euros could thus been saved.Martin-Werner Buchenau: ''Die Bahn ist immer noch wie eine Behörde''. In: '' Handelsblatt''. Nr. 241, 12. Dezember 2012, , S. 18. A 2830 m long section was advanced using tunnel boring machines (TBM) in both tubes. Although Deutsche Bahn had stipulated conventional shotcrete tunneling in the tender documents, alternative proposals for TBM excavation were welcomed. This proved an economic solution.


Award of contract

On 8 November 2011, the tunnel shell of Boßler- and Steinbühltunnel was put out for tender in Europe. The Boßlertunnel construction was subdivided into two lots of approximately 3670 m and approximately 5100 m in length; the Steinbühltunnel forms a third, independent lot. The contract also involved around 1.32 million cubic meters of excavated material or to be used during the project or disposed of, and the construction of four temporary connection points on the Autobahn 8''D-Frankfurt: Bauarbeiten für Tunnel''
Dokument ''2011/S 214-349672'' vom 8. November 2011 im Elektronischen Amtsblatt der Europäischen Union.
The calculation documents were sent to bidders in February 2012. Volker Kefer: ''Stuttgart 21 und NBS Wendlingen-Ulm Unterlage für den Prüfungs- und Complianceausschuss (PCA) der DB und den Lenkungskreis (LK) S21''. Berlin/Stuttgart, 23. März 201
PDF
(880 kB), S. 28.
The contract was awarded in October 2012, together with the Steinbühltunnel construct. The cost for both tunnels came to 635 million euros, believed to be significantly below the planned cost ''Bahn vergibt auf der Neubaustrecke Wendlingen–Ulm die Tunnelbauwerke des Albaufstieges''
(PDF; 139 kB). Presseinformation der Deutschen Bahn vom 17. Oktober 2012.
Originally, the award was not expected to be made until the end of 2010 (Status: December 2011).Kommunikationsbüro Bahnprojekt Stuttgart–Ulm (Hrsg.)
''Steckbrief: Zum weiteren Projektfortschritt im Nachgang zur Volksabstimmung''
. Presseinformation vom 2. Dezember 2011.
The award was officially published at the end of November 2012. 6The total cost for both the tunnel Albaufstiegs specified end of October 2013, about 1.05 billion euros. For the full planning approval section 2.4, the price was estimated at EUR 1,074.3 million. When the financing agreement for the new line was concluded in April 2009, the Boßler Tunnel was estimated to have shell costs of around EUR 19.5 million per kilometer and tube. When applying for the financial construction permit in 2010, the planned cost was EUR 32.0 million per kilometer and tube.Deutscher Bundestag (Hrsg.)
''Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Winfried Hermann, Dr. Anton Hofreiter, Dr. Valerie Wilms, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN – Drucksache 17/4001 – Aktuelle Entwicklungen bei der geplanten Neubaustrecke Wendlingen–Ulm''
(PDF; 107 kB). Drucksache 17/4293 vom 17. Dezember 2010.


Construction

The clearing work for the construction side began in early December 2012. In 2013, an embankment was added between the existing bridge over the L1214 road and the future tunnel portal.Arnd Woletz: ''Vorboten der Mammut-Baustelle''. In: Neue Württembergische Zeitung, 8. Dezember 2012
online
.
The bridge was completed the first building of the new line in 2011 In early 2012, following the Site survey the advance was scheduled for mid-2013 Andreas Pflüger: ''Mitte 2013 beginnt das große Bohren und Buddeln''. In: Stuttgarter Zeitung, Nr. 24, 30. Januar 2012. The excavation at 'intermediate attack Umpfental' 'began in July 2013. 66 months are provided for the shell. The two tubes should be first built using the
NATM The New Austrian tunneling method (NATM), also known as the sequential excavation method (SEM) or sprayed concrete lining method (SCL), is a method of modern tunnel design and construction employing sophisticated monitoring to optimize various w ...
. To accelerate the construction, three intermediate points were provided. As part of a plan amendment process in 2008 an intermediate advance was rejected.''Beim Lärmschutz bleibt die Bahn unbeweglich''.
In: ''Göppinger Kreisnachrichten'', 14. November 2008.
The planning of 2009 envisaged another intermediate advance in the form of a preliminary window tunnel, to be filled in after completion of the tunneling. The machine advance from the western portal was over a length of 2830 m. An advance from the eastern portal was not undertaken, due to the very steep flanks and environmental considerations. By mid-November 2014, 600 meters of intermediate advance had been completed. Of the 8,772 m long west tube, 8,745 m are being advanced in traditional drill & blast methods; portal structures are planned for the remaining 27 m. Of the 8,788 m long east tunnel, 8,761 m are being advanced using traditional drill & blast methods and 27. m using cut and cover for the portals. Together with the Steinbühltunnel, a total of 4.3 million cubic meters of material will be excavated. The machine advance should, according to the planning status of the end of 2013, begin not later than 21 September 2014. ell, did it?ref name="gz-2013-11-23"> Approximately 8,000 people attended a Construction Site Open Day on 8 November 2014. Machine advance began symbolically. The actual machine advance was scheduled to begin in January 2015. After the overburden proved more solid than initially planned, in 2014, an extended machine advance was considered. Could machine advance be used? Spätestens am 8. Dezember 2014 wurde der konventionelle Vortrieb ohne Angabe von Gründen gestoppt. Dabei waren bergabwärts 731 m und bergaufwärts bei 47 m. It was downhill 731 m and uphill at 47 m The according to other sources for before Christmas in 2014 announced propelling start was delayed, according to web information indefinitely due to necessary fine adjustments to the machine At the end of February 2015, the Federal Railway announced its intention to extend the machine advance In early March 2015, talks were held between German railway and contractors on the extension of mechanical tunneling Due in part to lack of permits, the start of driving was delayed four months in total The machine advance finally began on 14 April 2015. The 120 meter long, 11.38. m high machine, worth 29 million euros, is called '' S 833 '' and was given the name '' Kätchen''. It was planned advance by 15 to 20 meters per day. The machine advance would take eight to nine months in the first tunnel tube. After one kilometer of machines advance, very dry rock dust was unexpectedly encountered. Instead of the planned 20 meters per day, the machine advanced achieved as much as 30 meters. In July and August 2015, the advance was paused for five weeks in order to convert the logistics for a higher driving speed. On 5 August 2015 the advance was resumed early September 2015 were with the machine 1.6 propelled km The segments for the outer skin of the tunnel were made in a segment plant in Weilheim, seven days a week, in two shifts per day with 100 workers each. They are transported the 1.6 km to the tunnel portal with a Feldbahn. On 6 November 2016 the machine finished the first tunnel. The structural work was done from 2013–2018.Deutscher Bundestag (Hrsg.)
''Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Ute Kumpf, Michael Groß, Christian Lange (Backnang), weiterer Abgeordneter und der Fraktion der SPD – Drucksache 17/13198 – Sachstand wichtiger Verkehrsprojekte für Baden-Württemberg''
(PDF; 177 kB). Drucksache 17/13846 vom 6. Juni 2013.
The tunnel is scheduled for completion in November 2019.


Geology

For about six kilometres, the tunnel passes beneath
Middle Jurassic The Middle Jurassic is the second epoch of the Jurassic Period. It lasted from about 174.1 to 163.5 million years ago. Fossils of land-dwelling animals, such as dinosaurs, from the Middle Jurassic are relatively rare, but geological formations co ...
layers. Preliminary investigations had shown very low strength in some sections, thus unstable rock is expected in connection with an overburden of up to 280 m. Furthermore,
Karst Karst is a topography formed from the dissolution of soluble rocks such as limestone, dolomite, and gypsum. It is characterized by underground drainage systems with sinkholes and caves. It has also been documented for more weathering-resistant ro ...
formations are expected in the White Jurassic layers. The Middle Jurassic layers consist of claystone and argillaceous marl with sandstone inclusions. From top to bottom, the layers α, β (unstable rock), and γ - ξ are traversed, followed by White Jurassic α, β, and γ. The water pressure in the Middle Jurassic layers is expected to reach , in the White Jurassic up to .Joachim Nied, Peter Marquart: ''Planung, Realisierung und Geologie der Großprojekte Stuttgart 21 und NBS Wendlingen–Ulm''. In: ''Geotechnik'', 30 (2007), Nr. 4, , S. 225–231.


References


External links


"The Stuttgart-Ulm Rail Project"
DB Projekt Stuttgart–Ulm GmbH. Retrieved 29 September 2016. {{DEFAULTSORT:Bossler Tunnel High-speed railway lines in Germany Railway tunnels in Germany