The Versova–Bandra Sea Link (VBSL), officially Swatantrya Veer Savarkar Sea Link, is an under-construction bridge in
Mumbai Mumbai ( ; ), also known as Bombay ( ; its official name until 1995), is the capital city of the Indian state of Maharashtra. Mumbai is the financial capital and the most populous city proper of India with an estimated population of 12 ...
,
Maharashtra Maharashtra () is a state in the western peninsular region of India occupying a substantial portion of the Deccan Plateau. It is bordered by the Arabian Sea to the west, the Indian states of Karnataka and Goa to the south, Telangana to th ...
, India as a part of Coastal Road Phase-3 or Western Coastal Road. The bridge will connect Versova, a neighbourhood in the suburb of
Andheri Andheri (Help:IPA/Marathi, n̪d̪ʱeɾiː is a suburb situated in Western Mumbai, Maharashtra, India. Government and politics For administrative purposes, Andheri is bifurcated into Andheri (west) and Andheri (east). Andheri (west) comes ...
to the
Bandra–Worli Sea Link The Bandra–Worli Sea Link (officially known as Rajiv Gandhi Sea Link) is a 5.6 km long, 8-lane wide cable-stayed bridge that links Bandra in the Western Suburbs (Mumbai), Western Suburbs of Mumbai with Worli in South Mumbai. It is the second ...
in Bandra, as part of the Coastal Road. The 8-lane sea link is expected to reduce congestion on the Western Express Highway and the Western Line of the Mumbai Suburban Railway.


History

The prefeasibility study for the Versova–Bandra Sea Link (VBSL) was conducted by CES (I) Pvt. Ltd in 2007-2008. The
Government of Maharashtra The Government of Maharashtra is the executive branch of the Indian states of india, state of Maharashtra. The government is led by the List of chief ministers of Maharashtra, chief minister (currently Devendra Fadnavis since 5 December 2024) ...
appointed the Maharashtra State Road Development Corporation (MSRDC) as the nodal agency for the project on 19 December 2009. The Versova–Bandra Sea Link received environmental clearance, under certain conditions, from the Ministry of Environment and Forests in January 2013. A cabinet sub-committee on infrastructure chaired by then Maharashtra Chief Minister
Prithviraj Chavan Prithviraj Chavan (; born 17 March 1946) is an Indian politician who was the List of Chief Ministers of Maharashtra, 17th Chief Minister of Maharashtra from 2010 to 2014. Chavan is a graduate of BITS Pilani and University of California, Berkel ...
cleared the project on 15 January 2014. The project had been pending for approval from the State Government for the past four years. Some observers felt that the move was an attempt to keep the
Nationalist Congress Party The Nationalist Congress Party is one of the List of political parties in India#State parties, state parties in India and is one of the major political parties in Maharashtra Legislative Assembly, Maharashtra with a recognised state party statu ...
(NCP) happy prior to the 2014 general election, as this project and the Pune Ring Road project which was also approved the sub-committee, would be undertaken by the NCP-led MSRDC. The fate of the sea link had been uncertain after Chavan said that coastal roads were less expensive to build. Chavan had also stated that he favoured coastal roads because they had less environmental hurdles than a sea link.
Brihanmumbai Municipal Corporation The Brihanmumbai Municipal Corporation (BMC), or the Municipal Corporation of Greater Mumbai (MCGM) is the governing civic body of Mumbai, the capital city of Maharashtra. Salman Khan Is Now Brand Ambassador of BMC from 2016. The BMC is India ...
officials stated that the government had not clarified the future of the Coastal Road project, after approving the VBSL. The MSRDC invited
request for qualifications Request may refer to: * a question, a request for information * a petition, a formal document demanding something that is submitted to an authority. Request may also refer to: Computing and technology * in computer science, a message sent b ...
from companies interested in constructing the VBSL on 2 March 2014. The agency conducted a pre-bid conference for potential bidders on 28 March. The last date for the submission of technical bids was fixed as 30 May, and the MSRDC planned to open technical bids on 31 May 2014, as per the tender notice. The MSRDC estimated the project concession period to be 35 years in the absence of any viability gap funding (the state's financial contribution in a PPP project). However, after some members of the infrastructure sub-committee expressed reservations about the long concession period, the corporation decided to seek 20% from the Union Government, which the MSRDC estimated would reduce the concession period to about 28–30 years. However, the project was put on hold after the Maharashtra Government began promoting the Coastal Road project. On 29 April 2016, the State Government decided to resume implementation of the VBSL. The MSRDC received environmental clearance for the project from the State Environment Impact Assessment Authority (SEIAA) in February 2017. The
Louis Berger Group Louis Berger (formerly known as Berger Group Holdings) is a full-service engineering, architecture, planning, environmental, program and construction management and economic development firm based in Morristown, New Jersey. Founded in 1953 in H ...
was awarded a contract to provide project management services for the VBSL project in January 2018. The company conducted the feasibility study, prepared tenders and reviewed construction on the project. A joint venture between
Reliance Infrastructure Reliance Infrastructure Limited (R-Infra), formerly Reliance Energy Limited (REL) and Bombay Suburban Electric Supply (BSES), is an Indian private sector enterprise involved in power generation, infrastructure, construction and defence. It is p ...
and Italian construction company
Astaldi Astaldi S.p.A. is an Italian multinational major construction company based in Rome. The group is active in the fields of civil engineering, hydraulic engineering, electromechanical engineering and transportation. Significant subsidiaries incl ...
was awarded the engineering, procurement and construction contract worth to build the VBSL in May 2018.
Larsen & Toubro Larsen & Toubro Limited, abbreviated as L&T, is an Indian multinational conglomerate, with interests in industrial technology, heavy industry, engineering, construction, manufacturing, power, information technology, defence and financial se ...
and ITD Cementation also participated in the bidding for the VBSL placing higher bids of and respectively. The agreement was signed between the winning consortium and the MSRDC on 4 September 2018, and a deadline of 24 June 2023 was set for completing the project. The MSRDC also announced that it had appointed the Louis Berger Group to design three connecting roads to link the Versova–Bandra Sea Link with key roads near its entry and exit points. Construction on the project must be halted for three months every year during the monsoon season. The Maharashtra Maritime Board prohibits work in the sea during monsoon due to the potential safety risk for workers. On 26 February 2019, the Maharashtra Coastal Zone Management Authority (MCZMA) approved the setting up of a casting yard at Juhu Beach for the project. Activist Zoru Bhathena filed a petition challenging the decision in the
Bombay High Court The High Court of Bombay is the High courts of India, high court of the States and union territories of India, states of Maharashtra and Goa in India, and the union territory of Dadra and Nagar Haveli and Daman and Diu. It is seated primarily ...
. The Court cancelled the permission granted by the MCZMA citing a violation of coastal regulation zone (CRZ) guidelines on 26 April. The MSRDC filed a special leave petition appealing the order in the Supreme Court. On 9 May, the two-judge bench of the
Supreme Court In most legal jurisdictions, a supreme court, also known as a court of last resort, apex court, high (or final) court of appeal, and court of final appeal, is the highest court within the hierarchy of courts. Broadly speaking, the decisions of ...
upheld the High Court's verdict. The MSRDC withdrew its special leave petition, and stated that it would it file a writ petition seeking permission from the High Court to set up the casting yard. If the petition is denied the agency will have to find alternate land for the casting yard, which would delay the start of construction. The agency filed a review petition with the High Court on 30 August. MSRDC officials stated that they were also exploring the possibility of renting land temporarily for use as a casting yard in case the review petition failed. The agency also requested the National Environmental Engineering Research Institute to conduct an environment assessment report on the proposed casting yard. The issue concerning the casting yard was finally resolved in July 2020 when the MSRDC allocated an alternate plot in Malad. The 10 acre plot of land was leased from a private landowner at an annual rent of , which is borne equally by the MSRDC and the contractors. Construction work on the project was impacted by the
COVID-19 pandemic The COVID-19 pandemic (also known as the coronavirus pandemic and COVID pandemic), caused by severe acute respiratory syndrome coronavirus 2 (SARS-CoV-2), began with an disease outbreak, outbreak of COVID-19 in Wuhan, China, in December ...
which caused delays due to labour shortages and other factors. Progress on the project was very slow, with the consortium only completing about 2.07% of the total project work as of 15 August 2021, as opposed to Reliance's claims of completing the project within 60 months from June 2019. Due to the slow progress, the MSRDC began imposing a penalty of per day on Reliance Infrastructure from 1 September 2021. In January 2022, Reliance exited the project by selling its shares to Astaldi's
subsidiary A subsidiary, subsidiary company, or daughter company is a company (law), company completely or partially owned or controlled by another company, called the parent company or holding company, which has legal and financial control over the subsidia ...
,
Webuild Webuild S.p.A. (previously Salini Impregilo S.p.A.; ) is an Italian industrial group specialising in construction and civil engineering. The company was formally founded in 2014 as the result of the merger by incorporation of Salini into Impregi ...
. After Reliance's exit, Webuild appointed
Gurugram Gurgaon (), officially named Gurugram (), is a satellite city of Delhi and administrative headquarters of Gurgaon district, located in the northern Indian state of Haryana. It is situated near the Delhi–Haryana border, about southwest o ...
-based APCO Infratech as its new partner. Aiming to speed up progress on the project, MSRDC provided the contractors with a second casting yard in August 2022. The yard, which is owned by the MSRDC, is located on an 82,000 square metre plot near its headquarters in Bandra. The agency charged contractors a nominal annual rent of 1 to use the yard. The final legal challenge against the environmental clearance granted to the VBSL project was dismissed by the
National Green Tribunal The National Green Tribunal (NGT) is a statutory body in India that deals with expeditious disposal of cases related to environmental protection and other natural resources. It was set up under the National Green Tribunal Act in 2010. India ...
(NGT) on 22 August 2022. However, a petition filed by Dileep V. Nevatia in 2017 challenging the environmental clearance was still pending before the NGT. On 25 January 2023, the NGT ruled that despite its previous rulings, the petitioner had the right to be heard as he was not a party to the previous appeals. However, on 17 March 2023, the Supreme Court stayed the legal proceedings at the NGT. The Court cited the legal doctrine of ''
res judicata ''Res judicata'' or ''res iudicata'', also known as claim preclusion, is the Latin term for ''judged matter'', and refers to either of two concepts in common law civil procedure: a case in which there has been a final judgment and that is no lon ...
'' and ruled that "the same issue cannot be agitated again and again". The project's CRZ clearance expired in January 2023. The MCZMA recommended its renewal in March 2023, and the renewal was approved by the
Ministry of Environment, Forest and Climate Change The Ministry of Environment, Forest and Climate Change (MoEFCC) is an Government of India, Indian government Ministry (government department), ministry. The ministry Portfolio (government), portfolio is currently held by Bhupender Yadav, Union ...
in May 2023. The Ministry appointed the
Zoological Survey of India The Zoological Survey of India (ZSI), founded on 1 July 1916 by the Ministry of Environment, Forest and Climate Change of the Government of India as a premier Indian organisation in zoological research and studies to promote the survey, explora ...
to monitor the impact on marine life and the
Indian Institute of Science Education and Research, Pune Indian Institute of Science Education and Research, Pune (IISER Pune) is an autonomous public university established in 2006. It is one of the seven Indian Institutes of Science Education and Research, and was one of the first IISERs to be ...
to conserve mangroves during the construction period. About 8% of the total project work had been completed as of May 2023.


Alignment

The Versova–Bandra Sea Link has a total length of and forms part of the Coastal Road that links Marine Lines with Kandivali. It connects the Bandra-end of the Bandra–Worli Sea Link with Nana Nani Park in Versova. It also provides interchanges with Carter Road and Juhu providing a total of 4 entry/exit points. The main sea link bridge is in length with 4 lanes in each direction. It also houses a 24-lane toll plaza. Connectors on either end of the main bridge link it with Bandra and Versova. The Bandra connector is 1.17 km in length with 2 lanes in each direction, while the Versova connector is 1.80 km in length with 3 lanes in each direction. The Versova connector also houses an 18-lane toll plaza. The main sea link bridge also has two interchanges connecting it with Carter Road and Juhu Koliwada. The Carter Road connector is 1.80 km in length, has 3 lanes in each direction and houses an 18-lane toll plaza. The Juhu Koliwada connector is 2.80 km in length, has 2 lanes in each direction and houses a 12-lane toll plaza.


Cost

The cost of the project was originally estimated as in 2012. This escalated to in 2013, in 2014, and when construction began in 2019. The cost was estimated to be in 2023. MSRDC Vice Chairman Radheshyam Mopalwar stated that tolls would be collected on the sea link until 2052. The toll rates are expected to thrice the rates on the Bandra-Worli Sea Link as the Versova Bandra Sea Link is thrice as long.