The was Japan's first commercial nuclear power plant.
The first unit was built in the early 1960s to the British
Magnox
Magnox is a type of nuclear power / production reactor that was designed to run on natural uranium with graphite as the moderator and carbon dioxide gas as the heat exchange coolant. It belongs to the wider class of gas-cooled reactors. The ...
design, and generated power from 1966 until it was decommissioned in 1998.
A second unit, nominally a separate power station called , was built at the site in the 1970s, the first in Japan to produce over 1000 MW of electricity.
The site is located in
Tokai in the
Naka District in
Ibaraki Prefecture
is a Prefectures of Japan, prefecture of Japan located in the Kantō region of Honshu. Ibaraki Prefecture has a population of 2,828,086 (1 July 2023) and has a geographic area of . Ibaraki Prefecture borders Fukushima Prefecture to the north, ...
,
Japan
Japan is an island country in East Asia. Located in the Pacific Ocean off the northeast coast of the Asia, Asian mainland, it is bordered on the west by the Sea of Japan and extends from the Sea of Okhotsk in the north to the East China Sea ...
and is operated by the
Japan Atomic Power Company. The total site area amounts to 0.76 km
2 (188 acres) with 0.33 km
2, or 43% of it, being green area that the company is working to preserve.
The plant has been not operational since the reactor
shut down automatically due to the
2011 Tōhoku earthquake and tsunami
On 11 March 2011, at 14:46:24 Japan Standard Time, JST (05:46:24 UTC), a 9.0–9.1 Submarine earthquake, undersea megathrust earthquake occurred in the Pacific Ocean, east of the Oshika Peninsula of the Tōhoku region. It lasted approx ...
.
Reactors on site
Unit 1

This reactor was built based on the British-developed
Magnox
Magnox is a type of nuclear power / production reactor that was designed to run on natural uranium with graphite as the moderator and carbon dioxide gas as the heat exchange coolant. It belongs to the wider class of gas-cooled reactors. The ...
technology for dual-use.
Unit 1 is the first full-size nuclear reactor to be decommissioned in Japan.
The experience in decommissioning this plant is expected to be of use in the future when more Japanese plants are decommissioned.
Below is a brief time-line of the process:
* March 31, 1998: Operations cease
* March 2001: Last of the nuclear fuel moved off-site
* October 4, 2001: Decommissioning plan announced
* December 2001: Decommissioning begins, spent fuel pool is cleaned
* 2003: Turbine room and electric generator taken down
* Late 2004: Fuel moving crane dismantled
* 2011: Reactor itself is dismantled
Unit 2

Unit 2 is a
Boiling Water Reactor
A boiling water reactor (BWR) is a type of nuclear reactor used for the generation of electrical power. It is the second most common type of electricity-generating nuclear reactor after the pressurized water reactor (PWR).
BWR are thermal neutro ...
and was the first nuclear reactor built in Japan to produce over 1,000 MW of electricity.
By some formalities in the paperwork, the unit is technically separate from the rest of the nuclear facilities in Tokai, but it is managed with the rest of them and even shares the same front gate.
History
Tokaimura Accidents
Two separate nuclear accidents occurred in the 90s at the Tokai plant and nearby reprocessing facility, both in . In March 1997 a fire broke out in the bituminisation facility where spent fuel is encased in molten asphalt (bitumen) for storage. The event exposed more than 20 people to radiation but there were no direct fatalities.
The second more serious accident occurred on 30 September 1999 when workers, who were not properly trained, brought too much highly enriched uranium together causing a
criticality accident
A criticality accident is an accidental uncontrolled nuclear fission chain reaction. It is sometimes referred to as a critical excursion, critical power excursion, divergent chain reaction, or simply critical. Any such event involves the uninten ...
. A total of 119 people were exposed to radiation of which 2 were fatal cases.
In 2002, an evaluation technology adopted by the Japan Society of Civil Engineers had determined that the site of the plant could experience tsunami waves as high as 4.86 metres.
The government of Ibaraki prefecture published their own calculations in October 2007, where they estimated that such waves could be as high as 6 to 7 metres.
Japan Atomic Power changed its wave level assumption to 5.7 meters. Reconstruction works to raise the height of the 4.9-metre protection around the plant to 6.1 meters were started in July 2009, in order to protect the seawater pumps intended to cool an emergency diesel generator. Although most of the work was completed by September 2010, cable holes in the levee were still not fully covered. This work was scheduled to be completed around May 2011.
Additions to the
seawall
A seawall (or sea wall) is a form of coastal defense constructed where the sea, and associated coastal processes, impact directly upon the landforms of the coast. The purpose of a seawall is to protect areas of human habitation, conservation, ...
that raised it to a height of 6.1 meters were completed on 9 March, just two days before the
2011 Tōhoku earthquake and tsunami
On 11 March 2011, at 14:46:24 Japan Standard Time, JST (05:46:24 UTC), a 9.0–9.1 Submarine earthquake, undersea megathrust earthquake occurred in the Pacific Ocean, east of the Oshika Peninsula of the Tōhoku region. It lasted approx ...
.
In November 2018, the
NRA
NRA may refer to:
Organizations Asia and Oceania
* National Railway Administration, the national railway regulator of China
* National Recruitment Agency, Central Recruiting Agency of the Indian Government
* New Revolutionary Alternative, an anar ...
approved a 20-year extension. Following that, the operator will need the consent of the Ibaraki prefectural government, as well as six local municipalities, including the village of Tokai.
2011 earthquake and tsunami
When the tsunami did hit the Tokai plant in March 2011, the waves were 5.3 to 5.4 metres in height, higher than earlier estimations but still 30 to 40 centimetres lower than the most recent estimation.
The Tokai plant suffered a loss of external power-supply.
The levee was overrun, but only one of three seawater pumps failed, and the reactors could be kept stable and safe in cold shutdown with the emergency diesel generator cooled by the two remaining seawater pumps.
Following the
2011 Tōhoku earthquake and tsunami
On 11 March 2011, at 14:46:24 Japan Standard Time, JST (05:46:24 UTC), a 9.0–9.1 Submarine earthquake, undersea megathrust earthquake occurred in the Pacific Ocean, east of the Oshika Peninsula of the Tōhoku region. It lasted approx ...
, the Number 2 reactor was one of eleven nuclear reactors nationwide
to be shut down automatically.
It was reported on 14 March that a cooling system pump for the Number 2 reactor had stopped working.
Japan Atomic Power Company stated that there was a second operational pump and that cooling was working, but that two of three diesel generators used to power the cooling system were out of order.
Construction work on additional safety measures, including a 1.7 km sea wall to protect from possible tsunamis, was originally scheduled to be completed in March 2021.
In 2020 it was announced this was delayed until December 2022.
Stress tests
After the disaster in Fukushima, a stress-test was ordered by the Japanese government, since an investigation of the electrical installations of the Tokai 2 reactor revealed that they did not meet the earthquake-resistance standards set by the government.
Seismic research in 2011 showed that the March 11th quake was caused by the simultaneous movement by multiple
active fault
An active fault is a fault that is likely to become the source of another earthquake sometime in the future. Geologists commonly consider faults to be active if there has been movement observed or evidence of seismic activity during the last 10,0 ...
s off the coast of northern Japan in the Pacific Ocean, and in this way a much bigger earthquakes could be triggered, than the plants were designed to withstand at the time they were built. In March 2012, the Tokai 2 Plant in Ibaraki Prefecture and the Tomari power facility in Hokkaido, said that they could not rule out the possibility that the plants were vulnerable. Other nuclear power stations declared that the active faults near their nuclear plants would not move at the same time, and even when this would happen, the impact would be limited. NISA would look into the evaluation of active faults done by the plants.
In 2017 the
Nuclear Regulation Authority discovered that the wrong fuel rod position data had been used in safety evaluations since the plant had been built, consequent to a change to fuel rod specifications during the design and construction process.
Mito District Court injunction
In March 2021, the Mito District Court ordered the Tokai 2 reactor suspend operations, following the request of 224 plaintiffs. The plaintiffs, residents of Ibaraki Prefecture and the Tokyo metropolitan area, filed a lawsuit in 2012 against the operator. One of the key contentions was the appropriateness of the Japan Atomic Power's seismic
ground motion
Ground motion is the movement of the Earth’s surface from earthquakes or explosions. Ground motion is produced by seismic waves that are generated by sudden slip on a fault or sudden pressure at the explosive source and travel through the Eart ...
figure. The operator defended its basis seismic ground motion figure as 50 percent higher than the average. The plaintiffs contended that the figure should be four times as high as the current figure.
Public opinion
On 11 October 2011 Tatsuya Murakami, the mayor of the village
Tokai, said in a meeting with minister
Goshi Hosono, that the Tokai 2 reactor situated 110 kilometers from Tokyo should be decommissioned, because the reactor was more than 30 years old, and the people had lost confidence in the nuclear safety commission of the government.
In 2011 and 2012, about 100,000 signatures against the resumption of the plant's operation which shutdown due to the 2011 earthquake, were submitted to Ibaraki Governor Masaru Hashimoto. The petition urged the prefectural government not to allow the Tokai power station to resume operation, saying, "We should not allow a recurrence of the irretrievable sacrifice and loss as experienced in the Fukushima Daiichi nuclear power plant accident".
Reprocessing plant
The Tokai nuclear complex also contained a reprocessing plant built in 1971 that operated from 1981 until 2006. In 2014 it was decided to permanently cease operations because upgrades to match the post-Fukushima safety requirements were uneconomical.
See also
*
Fukushima Daiichi nuclear disaster
The Fukushima nuclear accident was a major nuclear accident at the Fukushima Daiichi Nuclear Power Plant in Ōkuma, Fukushima, Japan, which began on 11 March 2011. The cause of the accident was the 2011 Tōhoku earthquake and tsunami, which r ...
*
List of boiling water reactors
*
Lists of nuclear disasters and radioactive incidents
These are lists of nuclear disasters and radioactive incidents.
Main lists
* List of nuclear and radiation accidents and incidents
* List of nuclear and radiation accidents by death toll
* List of civilian nuclear accidents
* List o ...
*
List of nuclear power plants in Japan
The following is a list of Japanese nuclear power plants.
After the Fukushima Daiichi nuclear disaster, all 17 major plants were shut down. As of 2022, only 6 out of 17 major nuclear power plants operate in the country, operated by the Kyushu Elec ...
*
Tokaimura nuclear accident
The Tokaimura nuclear accidents refer to two nuclear related incidents near the village of Tōkai, Ibaraki, Tōkai, Ibaraki Prefecture, Japan. The first accident occurred on 11 March 1997, producing an explosion after an experimental batch of s ...
*
*
Rokkasho Reprocessing Plant
The is a nuclear reprocessing plant with an annual capacity of 800 tons of uranium or 8 tons of plutonium. It is owned by Japan Nuclear Fuel Limited (JNFL) and is part of the Rokkasho complex located in the village of Rokkasho, Aomori, Rokkasho ...
, meant to be the successor of the Tokai reprocessing Plant
References
External links
{{DEFAULTSORT:Tokai Nuclear Power Plant
1960s establishments in Japan
Buildings and structures in Ibaraki Prefecture
Nuclear power stations in Japan
Nuclear power stations using boiling water reactors
Tōkai, Ibaraki