History
The technique is generally considered to have originated in the Heavy Organic Chemicals Division of Imperial Chemical Industries (ICI), which was then a major British and international chemical company. Its origins have been described by Trevor Kletz, Kletz, Trevor (2000). ''By Accident... A Life Preventing Them in Industry''. PFV Publications. who was the company's safety advisor from 1968 to 1982. In 1963 a team of three people met for three days a week for four months to study the design of a newMethod
The method is applied to complex processes, for which sufficient design information is available and not likely to change significantly. This range of data should be explicitly identified and taken as the "design intent" basis for the HAZOP study. For example, a prudent designer will have allowed for foreseeable variations within the process, creating a larger design envelope than just the basic requirements, and the HAZOP will be looking at ways in which this might not be sufficient. A common use of the HAZOP is relatively early through the detailed design of a plant or process. However, it can also be applied at other stages, including later operational life of existing plants, in which case it is usefully applied as a revalidation tool to ensure that unduly managed changes have not crept in since first plant start-up. Where design information is not fully available, such as during front-end loading, a ''coarse'' HAZOP can be conducted; however, where a design is required to have a HAZOP performed to meet legislative or regulatory requirements, such an early exercise cannot be considered sufficient and a later, detailed design HAZOP also becomes necessary. For process plants, identifiable sections (''nodes'') are chosen so that for each a meaningful ''design intent'' can be specified . They are commonly indicated on piping and instrumentation diagrams (P&IDs) and process flow diagrams (PFDs). P&IDs in particular are the foremost reference document for conducting a HAZOP. The extent of each node should be appropriate to the complexity of the system and the magnitude of the hazards it might pose. However, it will also need to balance between "too large and complex" (fewer nodes, but the team members may not be able to consider issues within the whole node at once) and "too small and simple" (many trivial and repetitive nodes, each of which has to be reviewed independently and documented). For each node, in turn, the HAZOP team uses a list of standardized ''guidewords'' and process ''parameters'' to identify potential ''deviations'' from the design intent. For each deviation, the team identifies feasible ''causes'' and likely ''consequences'' then decides (with confirmation by risk analysis where necessary, e.g., by way of an agreed upon risk matrix) whether the existing safeguards are sufficient, or whether an ''action'' or ''recommendation'' to install additional safeguards or put in place administrative controls is necessary to reduce the risks to an acceptable level. The degree of preparation for the HAZOP is critical to the overall success of the review. "Frozen" design information provided to the team members with time for them to familiarize themselves with the process, an adequate schedule allowed for the performance of the HAZOP, provision of the best team members for their role. Those scheduling a HAZOP should take into account the review scope, the number of nodes to be reviewed, the provision of completed design drawings and documentation and the need to maintain team performance over an extended time-frame. The team members may also need to perform some of their normal tasks during this period and the HAZOP team members can tend to lose focus unless adequate time is allowed for them to refresh their mental capabilities. The team meetings should be managed by an independent, trained HAZOP ''facilitator'' (also referred to as HAZOP leader or chairperson), who is responsible for the overall quality of the review, partnered with a dedicated ''scribe'' to minute the meetings. As the IEC standard puts it:The success of the study strongly depends on the alertness and concentration of the team members and it is therefore important that the sessions are not too long and that there are appropriate intervals between sessions. How these requirements are achieved is ultimately the responsibility of the study leader.For a medium-sized chemical plant, where the total number of items to be considered is around 1200 pieces of equipment and piping, about 40 such meetings would be needed.Swann, C. D.; Preston, M. L. (1995). "Twenty-five Years of HAZOPs". ''Journal of Loss Prevention in the Process Industries.'' 8(6): 349-353 Various software programs are now available to assist in the management and scribing of the workshop.
Guidewords and parameters
Source: In order to identify deviations, the team applies (systematically i.e. in a given order) a set of guidewords to each node in the process. To prompt discussion, or to ensure completeness, appropriate process parameters are considered in turn, which apply to the design intent. Typical parameters are flow (or flowrate), temperature, pressure, level, composition, etc. The IEC standard notes guidewords should be chosen that are appropriate to the study, neither too specific (limiting ideas and discussion) nor too general (allowing loss of focus). A fairly standard set of guidewords (given as an example the standard) is as follows: Where a guide word is meaningfully applicable to a parameter (e.g., "no flow", "more temperature"), their combination should be recorded as a credible potential ''deviation'' from the design intent that requires review. The following table gives an overview of commonly used guideword-parameter pairs (deviations) and common interpretations of them. Once the causes and effects of any potential hazards have been established, the system being studied can then be modified to improve its safety. The modified design should then be subject to a formal HAZOP close-out, to ensure that no new problems have been added.HAZOP team
A HAZOP study is a team effort. The team should be as small as practicable and having relevant skills and experience. Where a system has been designed by a contractor, the HAZOP team should contain personnel from both the contractor and the client company. A minimum team size of fiveNolan, Dennis P. (1994) ''Application of HAZOP and What-If Safety Reviews to the Petroleum, Petrochemical and Chemical Industries''. Park Ridge, N.J.: Noyes Publications. . is recommended. In a large process there will be many HAZOP meetings and the individuals within the team may change, as different specialists and deputies will be required for the various roles. As many as 20 individuals may be involved. Each team member should have a definite role as follows: In earlier publications it was suggested that the study leader could also be the recorder Kletz, Trevor A. (1983). ''HAZOP & HAZAN. Notes on the Identification and Assessment of Hazards'' (2nd ed.). Rugby: IChemE. but separate roles are now generally recommended. The use of computers and projector screens enhances the recording of meeting minutes (the team can see what is minuted and ensure that it is accurate), the display of P&IDs for the team to review, the provision of supplemental documented information to the team and the logging of non-HAZOP issues that may arise during the review, e.g., drawing/document corrections and clarifications. Specialist software is now available from several suppliers to support the recording of meeting minutes and tracking the completion of recommended actions.See also
*Notes
References
Further reading
* * *Explanation by a software supplier: ** ** * * * * {{Risk management Process safety