Frequency Support
   HOME

TheInfoList



OR:

Power system operations is a term used in
electricity generation Electricity generation is the process of generating electric power from sources of primary energy. For electric utility, utilities in the electric power industry, it is the stage prior to its Electricity delivery, delivery (Electric power transm ...
to describe the process of
decision-making In psychology, decision-making (also spelled decision making and decisionmaking) is regarded as the Cognition, cognitive process resulting in the selection of a belief or a course of action among several possible alternative options. It could be ...
on the timescale from one day (day-ahead operation) to minutes prior to the power delivery. The term power system control describes actions taken in response to unplanned ''disturbances'' (e.g., changes in demand or equipment failures) in order to provide reliable electric supply of acceptable quality. The corresponding engineering branch is called Power System Operations and Control. Electricity is hard to store, so at any moment the supply (generation) shall be balanced with demand ("
grid balancing Grid balancing ensures that electricity consumption matches electricity production of an electrical grid at any moment. Electricity is by its nature difficult to store and has to be available on demand, so the supply shall match the demand very cl ...
"). In an electrical grid the task of real-time balancing is performed by a regional-based control center, run by an electric utility in the traditional (
vertically integrated In microeconomics, management and international political economy, vertical integration, also referred to as vertical consolidation, is an arrangement in which the supply chain of a company is integrated and owned by that company. Usually each ...
) electricity market. In the restructured
North American power transmission grid The electrical power grid that powers Northern America is not a single grid, but is instead divided into multiple wide area synchronous grids. The Eastern Interconnection and the Western Interconnection are the largest. Three other regions in ...
, these centers belong to '' balancing authorities'' numbered 74 in 2016, the entities responsible for operations are also called
independent system operator A regional transmission organization (RTO) in the United States is an electric power transmission system operator (TSO) that coordinates, controls, and monitors a multi-state electric grid. The transfer of electricity between states is consider ...
s,
transmission system operator File:Electricity grid simple- North America.svg, 380px, Simplified diagram of AC electricity grid from generation stations to consumers in North America rect 2 243 235 438 Power station rect 276 317 412 556 Transformer rect 412 121 781 400 Elect ...
s. The other form of balancing resources of multiple power plants is a power pool. The balancing authorities are overseen by reliability coordinators.


Day-ahead operation

Day-ahead operation schedules the generation units that can be called upon to provide the electricity on the next day (unit commitment). The
dispatchable generation Dispatchable generation refers to sources of electricity that can be programmed ''on demand'' at the request of power grid operators, according to market needs. Dispatchable generators may adjust their power output according to a request. Conven ...
units can produce electricity on demand and thus can be scheduled with accuracy. The production of the weather-dependent
variable renewable energy Variable renewable energy (VRE) or intermittent renewable energy sources (IRES) are renewable energy sources that are not dispatchable due to their fluctuating nature, such as wind power and solar power, as opposed to controllable renewable ener ...
for the next day is not certain, its sources are thus non-dispatchable. This variability, coupled with uncertain future power demand and the need to accommodate possible generation and
transmission Transmission or transmit may refer to: Science and technology * Power transmission ** Electric power transmission ** Transmission (mechanical device), technology that allows controlled application of power *** Automatic transmission *** Manual tra ...
failures requires scheduling of
operating reserve In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply. Most power sy ...
s that are not expected to produce electricity, but can be dispatched on a very short notice. Some units have unique features that require their commitment much earlier: for example, the
nuclear power station A nuclear power plant (NPP), also known as a nuclear power station (NPS), nuclear generating station (NGS) or atomic power station (APS) is a thermal power station in which the heat source is a nuclear reactor. As is typical of thermal power st ...
s take a very long time to start, while hydroelectric plants require planning of water resources usage way in advance, therefore commitment decisions for these are made weeks or even months before prior to the delivery. For a "traditional"
vertically integrated electric utility In microeconomics, management and international political economy, vertical integration, also referred to as vertical consolidation, is an arrangement in which the supply chain of a company is integrated and owned by that company. Usually each ...
the main goal of the unit commitment is to minimize both the
marginal cost In economics, the marginal cost is the change in the total cost that arises when the quantity produced is increased, i.e. the cost of producing additional quantity. In some contexts, it refers to an increment of one unit of output, and in others it ...
of producing the unit electricity and the (quite significant for fossil fuel generation) start-up costs. In a "restructured"
electricity market An electricity market is a system that enables the exchange of electrical energy, through an electrical grid. Historically, electricity has been primarily sold by companies that operate electric generators, and purchased by consumers or electr ...
a
market clearing In economics, market clearing is the process by which, in an economic market, the supply of whatever is traded is equated to the demand so that there is no excess supply or demand, ensuring that there is neither a surplus nor a shortage. The new ...
algorithm is utilized, frequently in a form of an
auction An auction is usually a process of Trade, buying and selling Good (economics), goods or Service (economics), services by offering them up for Bidding, bids, taking bids, and then selling the item to the highest bidder or buying the item from th ...
; the
merit order The merit order is a way of ranking available sources of energy, especially electrical generation, based on ascending order of price (which may reflect the order of their short-run marginal costs of production) and sometimes pollution, together wi ...
is sometimes defined not just by the monetary costs, but also by the environmental concerns. Unit commitment is more complex than the shorter-time-frame operations, since unit availability is subject to multiple constraints: * demand-supply balance need to be maintained, including the sufficient
spinning reserve In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply. Most power sy ...
s for contingency. The balance need to reflect the transmission constraints; * thermal units might have limits on minimum uptime (once switched on, cannot be turned off quickly) and downtime (once stopped, cannot be quickly restarted again); * "must-run" units have to run due to technical constraints (for example,
combined heat and power Cogeneration or combined heat and power (CHP) is the use of a heat engine or power station to electricity generation, generate electricity and useful heat at the same time. Cogeneration is a more efficient use of fuel or heat, because otherwise ...
plants must run if their heat is needed); * there is usually a single crew at the plant that needs to be present during a thermal unit start-up, so only one unit can be started at a time.


Hours-ahead operation

In the hours prior to the delivery, a system operator might need to deploy additional
supplemental reserve In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply. Most power sys ...
s or even commit more generation units, primarily to ensure the reliability of the supply while still trying to minimize the costs. At the same time, operator must ensure that enough
reactive power reserves Voltage control and reactive power management are two facets of an ancillary service that enables reliability of the transmission networks and facilitates the electricity market on these networks. Both aspects of this activity are intertwined (vo ...
are available to prevent the
voltage collapse Voltage, also known as (electrical) potential difference, electric pressure, or electric tension, is the difference in electric potential between two points. In a static electric field, it corresponds to the work needed per unit of charge to ...
.


Dispatch curve

The decisions ("
economic dispatch The merit order is a way of ranking available sources of energy, especially electrical generation, based on ascending order of price (which may reflect the order of their short-run marginal costs of production) and sometimes pollution, together wi ...
") are based on the dispatch curve, where the X-axis constitutes the system power, intervals for the generation units are placed on this axis in the ''
merit order The merit order is a way of ranking available sources of energy, especially electrical generation, based on ascending order of price (which may reflect the order of their short-run marginal costs of production) and sometimes pollution, together wi ...
'' with the interval length corresponding to the maximum power of the unit, Y-axis values represent the marginal cost (per-
MWh A kilowatt-hour ( unit symbol: kW⋅h or kW h; commonly written as kWh) is a non-SI unit of energy equal to 3.6 megajoules (MJ) in SI units, which is the energy delivered by one kilowatt of power for one hour. Kilowatt-hours are a commo ...
of electricity, ignoring the startup costs). For cost-based decisions, the units in the merit order are sorted by the increasing marginal cost. The graph on the right describes an extremely simplified system, with three committed generator units (fully dispatchable, with constant per-MWh cost): * unit A can deliver up to 120 MW at the cost of $30 per MWh (from 0 to 120 MW of system power); * unit B can deliver up to 80 MW at $60/MWh (from 120 to 200 MW of system power); * unit C is capable of 50 MW at $120/MWh (from 200 to 250 MW of system power). At the expected demand is 150 MW (a vertical line on the graph), unit A will be engaged at full 120 MW power, unit B will run at the dispatch level of 30 MW, unit C will be kept in reserve. The area under the dispatch curve to the left of this line represents the cost per hour of operation (ignoring the startup costs, $30 * 120 + $60 * 30 = $5,400 per hour), the incremental cost of the next MWh of electricity ($60 in the example, represented by a horizontal line on the graph) is called system lambda (thus another name for the curve, ''system lambda curve''). In real systems the cost per MWh usually is not constant, and the lines of the dispatch curve are therefore not horizontal (typically the marginal cost of power increases with the dispatch level, although for the
combined cycle power plant A combined cycle power plant is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy. On land, when used to make electricity the most common type is called a combined cycle gas turb ...
s there are multiple cost curves depending on the mode of operation, so the power-cost relationship is not necessarily
monotonic In mathematics, a monotonic function (or monotone function) is a function between ordered sets that preserves or reverses the given order. This concept first arose in calculus, and was later generalized to the more abstract setting of ord ...
). If the minimum level of demand in the example will stay above 120 MW, the unit A will constantly run at full power, providing
baseload power The base load (also baseload) is the minimum level of demand on an electrical grid over a span of time, for example, one week. This demand can be met by unvarying power plants or dispatchable generation, depending on which approach has the best mi ...
, unit B will operate at variable power, and unit C will need to be turned on and off, providing the "intermediate" or "cycling" capacity. If the demand goes above 200 MW only occasionally, the unit C will be idle most of the time and will be considered a
peaking power plant Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the powe ...
(a "peaker"). Since a peaker might run for just tens of hours per year, the cost of peaker-produced electricity can be very high in order to recover the capital investment and fixed costs (see the right side of a hypothetical full-scale dispatch curve).


Redispatch

Sometimes the grid constraints change unpredictably and a need arises to change the previously set unit commitments. This system redispatch change is controlled in real-time by the central operator issuing directives to market participants that submit in advance bids for the increase/decrease in the power levels. Due to the centralized nature of redispatch, there is no delay to negotiate terms of contracts; the cost incurred are allocated either to participants responsible for the disruption based on preestablished tariffs or in equal shares.


Minutes-ahead operation

In the minutes prior to the delivery, a system operator is using the
power-flow study In power engineering, a power-flow study (also known as power-flow analysis or load-flow study) is a numerical analysis of the flow of electric power in an interconnected system. A power-flow study usually uses simplified notations such as a one-li ...
algorithms in order to find the optimal power flow. At this stage the goal is reliability ("security") of the supply, applying contingency analysis. The practical electric networks are too complex to perform the calculations by hand, so from the 1920s the calculations were automated, at first in the form of specially-built
analog computer An analog computer or analogue computer is a type of computation machine (computer) that uses physical phenomena such as Electrical network, electrical, Mechanics, mechanical, or Hydraulics, hydraulic quantities behaving according to the math ...
s, so called ''
network analyzers Network, networking and networked may refer to: Science and technology * Network theory, the study of graphs as a representation of relations between discrete objects * Network science, an academic field that studies complex networks Mathematics ...
'', replaced by digital computers in the 1960s.


Control after disturbance

Small mismatches between the total demand and total load are typical and initially are taken care of by the
kinetic energy In physics, the kinetic energy of an object is the form of energy that it possesses due to its motion. In classical mechanics, the kinetic energy of a non-rotating object of mass ''m'' traveling at a speed ''v'' is \fracmv^2.Resnick, Rober ...
of the rotating machinery (mostly
synchronous generator An alternator (or synchronous generator) is an electrical generator that converts mechanical energy to electrical energy in the form of alternating current. For reasons of cost and simplicity, most alternators use a rotating magnetic field with ...
s): when there is too much supply, the devices absorb the excess, and frequency goes above the scheduled rate, conversely, too much demand causes the generator to deliver extra electricity through slowing down, with frequency slightly decreasing, not requiring an intervention from the operator. There are obvious limits to this "immediate control", so a ''control continuum'' is built into a typical power grid, spanning reaction intervals from seconds ("primary control") to hours ("time control").


Seconds-after control

The is engaged automatically within seconds after the frequency disturbance. Primary control stabilizes the situation, but does not return the conditions to the normal and is applied both to the generation side (where the
governor A governor is an politician, administrative leader and head of a polity or Region#Political regions, political region, in some cases, such as governor-general, governors-general, as the head of a state's official representative. Depending on the ...
adjusts the power of the
prime mover Prime mover may refer to: Philosophy *Unmoved mover, a concept in Aristotle's writings Engineering * Prime mover (engine or motor), a machine that converts various other forms of energy (chemical, electrical, fluid pressure/flow, etc.) into ener ...
) and to the load, where: * induction motors self-adjust (lower frequency reduces the energy use); * under-frequency relays disconnect interruptible loads; *
ancillary services Ancillary services are the services necessary to support the transmission of electric power from power plant, generators to consumers given the obligations of control areas and transmission utilities within those control areas to maintain reliable ...
are engaged (load is reduced as procured via reliability services contracts). Another term commonly used for the primary control is frequency response (or "beta"). Frequency response also includes the
inertial response Inertial response is a property of large synchronous generators, which contain large synchronous rotating masses, and which acts to overcome any immediate imbalance between power supply and demand for electric power systems, typically the electric ...
of the generators. This is the parameter that is approximated by the frequency bias coefficient of the
area control error The utility frequency, (power) line frequency (American English) or mains frequency (British English) is the nominal frequency of the oscillations of alternating current (AC) in a wide area synchronous grid transmitted from a power station to t ...
(ACE) calculation used for
automatic generation control In an electric power system, automatic generation control (AGC) is a system for adjusting the power output of multiple generators at different power plants, in response to changes in the load. Since a power grid requires that generation and load ...
.


Minutes-after control

The is used to restore the system frequency after a disturbance, with adjustments made by the balancing authority control computer (this is typically referred to as load-frequency control or
automatic generation control In an electric power system, automatic generation control (AGC) is a system for adjusting the power output of multiple generators at different power plants, in response to changes in the load. Since a power grid requires that generation and load ...
) and manual actions taken by the balancing authority staff. Secondary control uses both the
spinning Spin or spinning most often refers to: * Spin (physics) or particle spin, a fundamental property of elementary particles * Spin quantum number, a number which defines the value of a particle's spin * Spinning (textiles), the creation of yarn or thr ...
and non-spinning reserves, with balancing services deployed within minutes after disturbance (hydropower plants are capable of an even faster reaction).


Tertiary control

The ''tertiary control'' involves reserve deployment and restoration to handle the current and future contingencies.


Emergency control

In the event of a significant
grid contingency In an electrical grid, contingency is an unexpected failure of a single principal component (e.g., an electrical generator or a power transmission line) that causes the change of the system state large enough to endanger the grid security. Some p ...
, like a major loss of generation capacity, emergency measures might be necessary to avoid a
cascading failure A cascading failure is a failure in a system of interconnection, interconnected parts in which the failure of one or few parts leads to the failure of other parts, growing progressively as a result of positive feedback. This can occur when a singl ...
.
Load shedding Load shedding (LS) is a protective method of emergency power control where, during a large disbalance between supply and demand, the demand (load) is intentionally disconnected ("shed") so that the available electricity supply within a safe timefr ...
(LS) is a standard emergency control action that reduces demand by disconnecting certain loads within an acceptable timeframe (0.2 - 3 seconds), thereby preventing the collapse of the grid. Another emergecy control action is
islanding Islanding is the intentional or unintentional division of an Wide area synchronous grid, interconnected power grid into individual disconnected regions with their own power generation. Intentional islanding is often performed as a Defence in depth ...
.


Time control

The goal of the time control is to maintain the long-term frequency at the specified value within a wide area synchronous grid. Due to the disturbances, the average frequency drifts, and a ''time error'' accumulates between the official time and the time measured in the AC cycles. In the US, the average 60 Hz frequency is maintained within each
interconnection In telecommunications, interconnection is the physical linking of a carrier's network with equipment or facilities not belonging to that network. The term may refer to a connection between a carrier's facilities and the equipment belonging to its ...
by a designated entity, time monitor, that periodically changes the frequency target of the grid (''scheduled frequency'') to bring the overall time offset within the predefined limits. For example, in the
Eastern Interconnection The Eastern Interconnection is one of the two major alternating current, alternating-current (AC) electrical grids in the North American power transmission grid. The other major wide area synchronous grid, interconnection is the Western Inter ...
the action (temporarily setting the frequency to 60.02 Hz or 59.98 Hz) is initiated when the time offset reaches 10 seconds and ceases once the offset reaches 6 seconds. Time control is performed either by a computer (''Automatic Time Error Correction''), or by the monitor requesting balancing authorities to adjust their settings.


References


Sources

* * * * * * * * * {{cite book , last=Kundur , first=P. , last2=Balu , first2=N.J. , last3=Lauby , first3=M.G. , title=Power System Stability and Control , publisher=McGraw-Hill Education , series=EPRI power system engineering series , year=1994 , isbn=978-0-07-035958-1 , url=https://books.google.com/books?id=wOlSAAAAMAAJ , access-date=2023-06-12 Electric power generation Power engineering Electric power infrastructure Power station technology