RACI matrix
   HOME

TheInfoList



OR:

A responsibility assignment matrix (RAM), also known as RACI matrix () or linear responsibility chart (LRC), describes the participation by various
role A role (also rôle or social role) is a set of connected behaviors, rights, moral obligation, obligations, beliefs, and social norm, norms as conceptualized by people in a social situation. It is an expected or free or continuously changing behavi ...
s in completing tasks or
deliverable A deliverable is a tangible or intangible good or service produced as a result of a project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a software product, a server upgr ...
s for a
project A project is any undertaking, carried out individually or collaboratively and possibly involving research or design, that is carefully planned to achieve a particular goal. An alternative view sees a project managerially as a sequence of even ...
or
business process A business process, business method or business function is a collection of related, structured activities or tasks by people or equipment in which a specific sequence produces a service or product (serves a particular business goal) for a parti ...
. RACI is an
acronym An acronym is a word or name formed from the initial components of a longer name or phrase. Acronyms are usually formed from the initial letters of words, as in ''NATO'' (''North Atlantic Treaty Organization''), but sometimes use syllables, as ...
derived from the four key responsibilities most typically used: ''responsible'', ''accountable'', ''consulted'', and ''informed''. It is used for clarifying and defining roles and responsibilities in cross-functional or departmental projects and processes. There are a number of alternatives to the RACI model.


Key responsibility roles in RACI model


Role distinction

There is a distinction between a role and individually identified people: a ''role'' is a descriptor of an associated set of tasks; may be performed by many people; and one person can perform many roles. For example, an organization may have ten people who can perform the role of ''project manager'', although traditionally each project only has one project manager at any one time; and a person who is able to perform the role of ''project manager'' may also be able to perform the role of ''business analyst'' and ''tester''. ;''R = Responsible'' (also ''recommender'') : Those who do the work to complete the task.Smith Michael, Erwin James:
Role & Responsibility Charting (RACI)
', Project Management Forum, 2005, p. 5
There is at least one role with a participation type of ''responsible'', although others can be delegated to assist in the work required (see also ''RASCI'' below for separately identifying those who participate in a supporting role) ;''A = Accountable'' (also ''approver'' or ''final approving authority'') : The one ultimately answerable for the correct and thorough completion of the deliverable or task, the one who ensures the prerequisites of the task are met and who delegates the work to those ''responsible''. In other words, an ''accountable'' must sign off (approve) work that ''responsible'' provides. There must be only one ''accountable'' specified for each task or deliverable.Margaria Tiziana: ''Leveraging Applications of Formal Methods, Verification, and Validation: 4th International Symposium on Leveraging Applications Proceedings]'', Part 1, Springer, 2010, p. 492 ;''C = Consulted'' (sometimes ''consultant'' or ''counsel'') : Those whose opinions are sought, typically
subject-matter expert A subject-matter expert (SME) is a person who has accumulated great knowledge in a particular field or topic and this level of knowledge is demonstrated by the person's degree, licensure, and/or through years of professional experience with the s ...
s; and with whom there is two-way communication. ;''I = Informed'' (also ''informee'') : Those who are kept up-to-date on progress, often only on completion of the task or deliverable; and with whom there is just one-way communication. Very often the role that is ''accountable'' for a task or deliverable may also be ''responsible'' for completing it (indicated on the matrix by the task or deliverable having a role ''accountable'' for it, but no role ''responsible'' for its completion, i.e. it is implied). Outside of this exception, it is generally recommended that each role in the project or process for each task receive, at most, just one of the participation types. Where more than one participation type is shown, this generally implies that participation has not yet been fully resolved, which can impede the value of this technique in clarifying the participation of each role on each task.


Assigning people to facilities

The matrix is typically created with a vertical axis (left-hand column) of tasks (from a
work breakdown structure A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into ...
) or deliverables (from a product breakdown structure), and a horizontal axis (top row) of roles (from an organizational chart). Another example from the maintenance and reliability community


Alternatives

There are a number of alternatives to the RACI participation types: RACI ROLES SHORTEN: Roles are the following ; Responsible : Does the work to complete the task   ; Accountable : Delegates work and is the last one to review the task or deliverable before it's deemed complete ; Consulted : Provides input based on either how it will impact their future project work or their domain of expertise on the deliverable itself ; Informed : Needs to be kept in the loop on project progress, rather than roped into details of every deliverable


PARIS

:This is an early version of a responsibility assignment matrix, with the roles defined as: :; ''Participant'' : :; ''Accountable'' : :; ''Review required'' : :; ''Input required'' : :; ''Sign-off required''


PACSI

: This is a version very useful to organizations where the output of activities under the accountability of a single person/function can be reviewed and vetoed by multiple stakeholders, due to the collaborative nature of the culture. :; ''Perform'' : :: The person/function carrying out the activity. :; ''Accountable'' : :: The person/function ultimately answerable for the correct and thorough completion of the deliverable or task, and often the one who delegates the work to the performer. :; ''Control'' :: The person/function reviewing the result of the activity. They have a right of veto; their advice is binding. :; ''Suggest'' : :: The person/function consulted to give advice based upon recognized expertise. The advice is non-binding. :; ''Informed'' : :: The person/function who must be informed of the result of the activity.


RASIC or RASCI

:This is an expanded version of the standard RACI, less frequently known as ''RASCI'', breaking the ''responsible'' participation into: :; ''Responsible'' : ::Those responsible for the task, who ensure that it is done as per the ''approver'' :; ''Support'' :: Resources allocated to ''responsible''. Unlike ''consulted'', who may provide input to the task, ''support'' helps complete the task.


RASI

:This is an alternative version of the standard RACI, foregoing the ''consulted'' participation and replacing it with: :; ''Support'' :: Resources which play a supporting role in implementation.


RACI + F

:This is an expanded version of the standard RACI, with an additional participation type: Facilitate. This variation was introduced by Christophe Le Coent in 2012. Coent argued that the facilitator or coach role is important in agile software development environments and should therefore be explicitly included in the RAM. The use of RAM in Agile environments is considered contentious because some practitioners believe that everyone working in an agile team should be jointly responsible and accountable. :; ''Facilitates'' :: Facilitate activities during a Scrum project.


RACIQ

:This is an expanded version of the standard RACI, with an additional participation type: :; ''Quality review'' :: Those who check whether the product meets the quality requirements.


RACI-VS

:This is an expanded version of the standard RACI, with two additional participation types: :; ''Verifier'' :: Those who check whether the
product Product may refer to: Business * Product (business), an item that serves as a solution to a specific consumer problem. * Product (project management), a deliverable or set of deliverables that contribute to a business solution Mathematics * Produ ...
meets the
acceptance criteria In engineering and its various subdisciplines, acceptance testing is a test conducted to determine if the requirements of a specification or contract are met. It may involve chemical tests, physical tests, or performance tests. In systems ...
set forth in the
product description In the PRINCE2 project management method, a product description (PDD) is a structured format that presents information about a project product. It is a management product (document), usually created by the project manager during the process of i ...
. :; ''Signatory'' : ::Those who approve the ''verify'' decision and authorize the product hand-off. It seems to make sense that the ''signatory'' should be the party being ''accountable'' for its
success Success is the state or condition of meeting a defined range of expectations. It may be viewed as the opposite of failure. The criteria for success depend on context, and may be relative to a particular observer or belief system. One person migh ...
.


CAIRO

:This is an expanded version of the standard RACI, also known as ''RACIO'' with one additional participation type. :; ''Out of the loop'' (or ''omitted'') :: Designating individuals or groups who are specifically not part of the task. Specifying that a resource does not participate can be as beneficial to a task's completion as specifying those who do participate.


DACI

:Another version that has been used to centralize decision making, and clarify who can re-open discussions. :; ''Driver'' :: A single ''driver'' of overall project like the person steering a car. :; ''Approver'' :: One or more ''approver''s who make most project decisions, and are responsible if it fails. :; ''Contributors'' :: Are the worker-bees who are responsible for deliverables; and with whom there is two-way communication. :; ''Informed'' :: Those who are impacted by the project and are provided status and informed of decisions; and with whom there is one-way communication.


RAPID

:Another tool used to clarify decision roles and thereby improve decision making, is RAPID, which was created by and is a registered trademark of
Bain & Company Bain & Company is an American management consulting company headquartered in Boston, Massachusetts. The firm provides advice to public, private, and non-profit organizations. One of the Big Three management consultancies, Bain & Company was fo ...
. :; ''Recommend'' :: The ''recommend'' role typically involves 80 percent of the work in a decision. The recommender gathers relevant input and proposes a course of action—sometimes alternative courses, complete with pros and cons so that the decision maker's choices are as clear, simple and timely as possible. :; ''Agree'' :: The ''agree'' role represents a formal approval of a recommendation. The 'A' and the 'R' should work together to come to a mutually satisfactory proposal to bring forward to the decider. But not all decisions will need an agree role, as this is typically reserved for those situations where some form of regulatory or compliance sign-off is required. :; ''Perform'' :: The ''perform'' role defines who is accountable for executing or implementing the decision once it is made. Best-practice companies typically define P's and gather input from them early in the process. :; ''Input'' :: The ''input'' role provides relevant information and facts so that the recommender and decider can assess all the relevant facts to make the right decision. However, the 'I' role is strictly advisory. Recommenders should consider all input, but they don't have to reflect every point of view in the final recommendation. :; ''Decide'' :: The ''decide'' role is for the single person who ultimately is accountable for making the final decision, committing the group to action and ensuring the decision gets implemented.


RATSI

:Another tool used in organization design or roles analysis. :; ''Responsibility'' :: Identify who is in charge of making sure the work is done. :; ''Authority'' :: Identify who has final decision power on the work. :; ''Task'' :: Identify who actually does the work. :; ''Support'' :: Identify who is involved to provide support to the work. :; ''Informed'' :: Identify who is informed that the work has been done (or will be started)


DRASCI

:A variant of RASCI developed by three Whitehall theorists (Kane, Jackson, Gilbert). This scheme is adapted for use in matrix management environments, and differs only from RASCI in having an additional role of ''Driver'' and a narrower definition of ''Support'': :; ''Driver'' :: An individual or party that assists those who are ''responsible'' for delivering a task by both producing supporting collateral and setting timescales for delivery in line with the overarching aim of the individual or party who is ''accountable'' for the overall accomplishment of the objective. The distinction between ''driver'' and ''support'' lies in that the former reinforces and clarifies the parameters of the task on behalf of those who are ''accountable'', while the latter refers to those who help those who are ''responsible'' in reaching a given goal.


PDQA

: A version developed at U Tokyo and MIT for model-based project management. The PDQA set of roles corresponds to demand for capabilities of teams. Roles include those for work on scope, handling of dependencies as coordination, and exception handling through error detection and decisions across a project organization. PDQA is used in agent-based modeling to simulate the supply of these capabilities by teams in projects. :; ''Primary'' :: Provides skill-based effort within capacity to complete scope and also manages dependencies through coordination. :; ''Decision'' :: Handles any decision, including scope acceptable and exception handling decisions leading to rework. (Does not generation nominal scope). :; ''Quality'' :: Reviews scope as it progresses to detect poor quality and escalates to decision-maker as so. (Does not general nominal scope). :; ''Assist'' :: Provides skill-based effort with the capacity to complete scope, in assistance to the primary. (Does not manage dependencies through coordination).


DCI

: A minimal set of decision-making categories used in organisation design or roles analysis. :; ''Decision maker'' :: Individuals who make the decision and is accountable for its impact on the business. :; ''Consulted'' :: Individuals accountable for providing guidance based on functional expertise and experience, highlighting issues and raising alternatives to support the Decision Maker. :; ''Informed'' :: Impacted stakeholders are notified after the decision has been made and who will need to support the execution of the decision.


RASCEIO

To be used when working on governance, risk, compliance (GRC) and outsourcing matters: :; ''Responsible'' : :; ''Accountable'' : :; ''Support'' : :; ''Consult'' : :; ''Execute'' :: Third parties contracted to execute activities in accordance with a service level agreement :; ''Inform'' : :; ''Overview'' :: Key GRC roles, such as risk owner, policy owner - where accountability is devolved, but a role is needed to oversee whether accountabilities all fit together


Variations

There are also a number of variations to the meaning of RACI participation types:


RACI (alternative scheme)

:There is an alternative ''coding'', less widely published but used by some practitioners and process mapping software, which modifies the application of the ''R'' and ''A'' codes of the original scheme. The overall methodology remains the same but this alternative avoids potential confusion of the terms ''accountable'' and ''responsible'', which may be understood by management professionals but not always so clearly differentiated by others: :; ''Responsible'' :: Those responsible for the performance of the task. There should be exactly one person with this assignment for each task. :; ''Assists'' ::Those who assist in the completion of the task :; ''Consulted'' :: Those whose opinions are sought; and with whom there is two-way communication. :; ''Informed'' :: Those who are kept up-to-date on progress; and with whom there is one-way communication.


ARCI (decisions)

:This alternative is focused only on documenting who has the authority to make which decisions. This can work across all sized workgroups. :; ''Accountable'' :: Authorized to ''approve'' an answer to the decision. :; ''Responsible'' :: Responsible to ''recommend'' an answer to the decision. :; ''Consulted'' :: Those whose opinions are sought, and with whom there is two-way communication. :; ''Informed'' :: Those who are informed after the decision is made, and with whom there is one-way communication.


References

{{reflist


External links


Comprehensive Series on RACI
Project management techniques Business terms