DART Underground
   HOME

TheInfoList



OR:

DART Underground ( ga, DART Faoi Thalamh), also known as the Interconnector or DART+ Tunnel, is a proposed mainline-rail tunnel in
Dublin Dublin (; , or ) is the capital and largest city of Republic of Ireland, Ireland. On a bay at the mouth of the River Liffey, it is in the Provinces of Ireland, province of Leinster, bordered on the south by the Dublin Mountains, a part of th ...
, Ireland. First proposed in 1972, it was not funded or scheduled. While the Greater Dublin Transport Strategy 2016-2035 (published in 2016) included the DART Underground as a proposed National Transport Authority project, the tunnel was not included in the
National Development Plan National Development Plan (NDP, ga, Plean Forbartha Náisiúnta) was the title given by the Irish Government to a scheme of organised large-scale expenditure on (mainly) national infrastructure. The first five-year plan ran from 1988 to 1993, ...
published in 2018 or DART+ expansion plans published in August 2020. The original plans, which proposed an expansion of the electrified Dublin Area Rapid Transit (DART) network, projected the development of a tunnel between
Heuston Station Heuston Station ( ; ga, Stáisiún Heuston; formerly Kingsbridge Station) also known as Dublin Heuston, is one of Dublin's largest railway stations and links the capital with the south, southwest and west of Ireland. It is operated by Iar ...
and
Pearse Station Pearse railway station ( ga, Stáisiún na bPiarsach) or Dublin Pearse is a railway station on Westland Row on the Southside of Dublin, Ireland. It is Ireland's busiest commuter station and second busiest station overall (behind Dublin Conno ...
. It had been planned to leave an existing line, via the
Phoenix Park Tunnel The Phoenix Park Tunnel is a railway tunnel in Dublin, Ireland. The tunnel was built in 1877 and begins at the Liffey Railway Bridge near Heuston Station, running underneath the Phoenix Park for 690 metres before re-emerging close to the juncti ...
, idle in the event of the scheme being built. This line however was subsequently reopened, connecting Heuston station with Dublin's Docklands - a cross-city connection which the DART Underground scheme was supposed to achieve. Accordingly, when the Irish Government published a new national spatial strategy in 2018, the revised plans dropped the DART Underground scheme in favour of these existing lines. Having previously secured planning consent, the project was initially deferred until after 2016, and by 2015, it had been announced that the project would be redrafted to a lower cost design. In October 2016, a "scaled down" plan was published with a potential commencement date "in 2020". As of September 2017 however, it was suggested that the developments would be deferred until after 2030, with the National Transport Authority undertaking a review of the project and its route; this review projected to complete sometime between 2018 and 2027. While the planned alignment was to be preserved, it was announced in November 2021 that DART Underground would not proceed in the period 2022–2042.


History

DART Underground was first proposed in 1972 in the "Transportation in Dublin" study conducted by An Foras Forbartha, an anteceding body to
Forfás Forfás () was the national policy advisory board for enterprise, trade, science, technology and innovation in Ireland. The agency was established in January 1994 under thIndustrial Development Act, 1993and was run by a board appointed by the Mi ...
as an underground rail link to connect Dublin's three main railway stations. In 1975,
CIÉ Córas Iompair Éireann (''Irish Transport Company''), or CIÉ, is a statutory corporation of Ireland, answerable to the Irish Government and responsible for most public transport within the republic and jointly with its Northern Ireland counte ...
commissioned the "Dublin Rapid Rail Transportation Study" (DRRTS),Environmental Impact Study Dart Underground 2010 History of
which recommended a four-phase plan including a prototypical Dart Underground: * Phase 1 - Upgrade and electrify Howth – Bray (completed 1984 as the DART). * Phase 2 - An underground line from Connolly to Heuston. Rapid Transit tracks Heuston to Clondalkin overground. Spur to Tallaght from Clondalkin (partially completed in 2010 when Rapid Transit tracks were installed either side of Clondalkin). * Phase 3 - A short northerly spur off the Maynooth line to Blanchardstown and a short southerly spur to Broadstone (never completed). * Phase 4 - A tunnel from Broadstone to Sandymount (later redesigned as Metro North before being shelved indefinitely in 2011). The DRRTS, if completed as envisaged in 1975, would have resulted in a cross shaped pair of tunnels in the city centre meeting at a central station in Temple Bar. The next plan, proposed in 2001 as an "Interconnector", was included in the Platform For Change strategy report issued by the now defunct Dublin Transportation Office (DTO). A Railway Order permitting the construction of the project was granted in December 2011 by
An Bord Pleanála (; meaning "The Planning Board"; ABP) is an independent, statutory, quasi-judicial body that decides on appeals from planning decisions made by local authorities in the Republic of Ireland. As of 2007, An Bord Pleanála directly decided major ...
. In August 2014, then
Minister for Transport A ministry of transport or transportation is a ministry responsible for transportation within a country. It usually is administered by the ''minister for transport''. The term is also sometimes applied to the departments or other government ag ...
Paschal Donohoe Paschal Donohoe (born 19 September 1974) is an Irish Fine Gael politician who has served as Minister for Public Expenditure and Reform since December 2022 and President of the Eurogroup since July 2020. He has been a Teachta Dála (TD) for the ...
TD was told that both the Dart Underground and Metro North projects would have had to rely on private funding if they were to be built. In 2010, the estimated projected cost for DART Underground was €4 billion, more than half of which was expected to be provided by a
public private partnership In public relations and communication science, publics are groups of individual people, and the public (a.k.a. the general public) is the totality of such groupings. This is a different concept to the sociological concept of the ''Öffentlichkei ...
arrangement. Donohoe was told he had to decide on whether to proceed with DART Underground by 24 September 2015, by which time the Railway Order and planning approval would expire. A High Court ruling reduced the period for which compulsory purchase order notices could be issued from seven years to 18 months. The National Transport Authority's Greater Dublin Area draft Transport Strategy 2016–2035, published in October 2015, expressed the desire to see the tunnel completed as part of the overall DART extension programme.


Delays and status

In May 2010,
Iarnród Éireann Iarnród Éireann () or Irish Rail, is the operator of the national railway network of Ireland. Established on 2 February 1987, it is a subsidiary of Córas Iompair Éireann (CIÉ). It operates all internal InterCity, Commuter, DART and fr ...
anticipated that, if construction had begun in 2012, the tunnel would have been operational by 2018. In June 2010, Iarnród Éireann submitted an application to
An Bord Pleanála (; meaning "The Planning Board"; ABP) is an independent, statutory, quasi-judicial body that decides on appeals from planning decisions made by local authorities in the Republic of Ireland. As of 2007, An Bord Pleanála directly decided major ...
for a Railway Order for the scheme under the ''Transport (Railway Infrastructure) Act 2001''. In November 2011, the government deferred funding the project due to the decrease in capital spending until 2016 at the earliest. A month later, in December 2011, a Railway Order was granted for the development. The granting of the Railway Order covered the construction of the scheme and any necessary compulsory acquisition of property, but did not commit funding to the project. In September 2015, it was announced that the project had been cancelled in favour of a simpler alternative. However, it was planned to return as part of a future DART Expansion Programme, to potentially start no earlier than 2020 or 2021. As of 2016, the National Transport Authority (NTA) was reviewing the project. By September 2017, it was suggested that this review would complete during 2018, and that -depending on the outcome of the review- works on the project would not commence until at least 2020. Revised projections suggested that it would be at least "2030 before passengers could use the new line". By April 2018, the
Irish Independent The ''Irish Independent'' is an Irish daily newspaper and online publication which is owned by Independent News & Media (INM), a subsidiary of Mediahuis. The newspaper version often includes glossy magazines. Traditionally a broadsheet new ...
reported that the DART underground plans had been "dropped .completely in favour of four new stations at ground level". Later in 2018, the then
Minister for Transport A ministry of transport or transportation is a ministry responsible for transportation within a country. It usually is administered by the ''minister for transport''. The term is also sometimes applied to the departments or other government ag ...
stated that the review of the project's plans and route (by the NTA) would complete during the period of the 2018-2027 National Development Plan. The project was not included in the DART+ expansion plans published in August 2020. In April 2021, the project was reportedly "being resurrected" but in November 2021 the NTA stated that the DART Underground / Interconnector would not proceed until after 2042, although they would "preserve and protect an alignment to allow its future delivery". Other Luas projects and Metrolink also had new timings assigned.


Opposition

During 2010 there was opposition to the project in Dublin's
East Wall East Wall () is an inner city area of the Northside of Dublin, Ireland. Built on reclaimed ground in the 1820s, the area is also 30 minutes walk from Dublin's main thoroughfare, O'Connell Street. Location East Wall is bounded by West Road to t ...
area, where the tunnel would have begun and where tunnelling operations were planned to be located. Complaints were exacerbated by the suggestion that, while they would have had to endure the disturbance created by the tunneling works, East Wall residents would not gain anything from the project as they would not have easy access to a DART station - since they were roughly halfway (20 minutes walk) between the Clontarf Road and Docklands stations. Complaints were also raised by residents at a Western entrance to the tunnel, at Inchicore. In late 2017, developers expressed concern that planned developments near Pearse Street Station were declined permission on the basis of their potential impact on the proposed DART Underground project.


Possible routes and stations

If routed as originally proposed, the existing (single) DART line would be replaced by two DART lines forming a rough "X" shape - with an intersection at Pearse Station. The first of these lines would begin to the north-east of the city in Howth/Malahide, follow the existing DART line to Clontarf Road station, before diverging into a tunnel which would ultimately emerge close to the
Inchicore railway works Inchicore railway works, also known locally as 'Inchicore' or 'The Works', was founded by the Great Southern and Western Railway in 1846 and emerged to become the major engineering centre for railways in Ireland. Located west of Dublin city ...
grounds. A second line would follow the existing southern DART line from Bray/Greystones to Connolly Station, from which it would diverge on a line to Maynooth station in Kildare. If following this plan, underground platforms would be added to the existing over-ground platforms at Spencer Dock station,
Pearse station Pearse railway station ( ga, Stáisiún na bPiarsach) or Dublin Pearse is a railway station on Westland Row on the Southside of Dublin, Ireland. It is Ireland's busiest commuter station and second busiest station overall (behind Dublin Conno ...
, and Stephen's Green station. New stations would also be built close to Christ Church (underground) and
Inchicore Inchicore () is a suburb of Dublin, Ireland. Located approximately west of the city centre, Inchicore was originally a small village separate from Dublin. The village developed around Richmond Barracks (built 1810) and Inchicore railway works (b ...
(overground). , no route was confirmed and no station developments were planned or funded. Additional assessment (of both routes and stations) was proposed to be undertaken between 2018 and 2027. , Jacobs Engineering were reportedly charged with devising route options for the line, with no direction to "adhere to the previously alignment" or "location of new stations required
f any F, or f, is the sixth letter in the Latin alphabet, used in the modern English alphabet, the alphabets of other western European languages and others worldwide. Its name in English is ''ef'' (pronounced ), and the plural is ''efs''. Hist ...
.


See also

*
Rail transport in Ireland Rail transport in Ireland (InterCity, commuter and freight) is provided by Iarnród Éireann in the Republic of Ireland and by Northern Ireland Railways in Northern Ireland. Most routes in the Republic radiate from Dublin. Northern Ireland has ...


References


External links


Irish Rail DART Expansion/Underground Project website
{{coord missing, County Dublin Transport in County Dublin Railway tunnels in the Republic of Ireland Dublin Suburban Rail Proposed railway tunnels in Europe Proposed rail infrastructure in the Republic of Ireland Proposed railway lines in the Republic of Ireland Underground commuter rail