What constitutes a breach of contract
There exists two elementary forms of breach of contract. The first is actual failure to perform the contract as and when specified constitutes the first and most obvious type of breach. A contract lays down what must be done, what cannot be done, and when it must be done. If what was prescribed has not been done within the stipulated or reasonable period, there has been a breach of contract. A further form of breach of contract is conduct indicating an unwillingness or inability to perform an obligation arising from that contract. As noted by Seddon et al, these forms of breach of contract overlap, and an actual failure to perform may manifest an unwillingness or inability to perform. This is not always the case: an individual may fail to perform a contractual obligation even when willing or able. These classifications describe only ''how'' a contract can be breached, not how serious the breach is. A judge will make a decision on whether a contract was breached based on the claims of both parties. The first type above is an ''actual'' breach of contract. The two other types are breaches as to the future performance of the contract and are technically known as ''renunciatory'' breaches. The defaulting party renunciates the contract in advance of when it is required to performs its obligations. Renunciatory breach is more commonly known as "anticipatory breach."Classifications of breaches of contract
The general law has three categories of breaches of contract, which measure of the seriousness of the breach. In the absence of a contractual or statutory provision, any breach of contract is categorized: * breach of warranty; * breach of condition; or * breach of an innominate term, otherwise known as an ''intermediate'' term. There is no "internal rating system" within each of these categories (such as "a serious breach of warranty"). Any breach of contract is of a breach of warranty, condition or innominate term. In terms of priority of classification of these terms, a term of a contract is an innominate term unless it is clear that it is intended to be a condition or aRights to damages for breach
Any breach of contract (warranty, condition or innominate term) gives rise to a right in the hands of the innocent party to recover their damage suffered which caused by the breach of contract by the defaulting party. Damages in the UK are the only remedy available for breach of a warranty. Those damages can come in different forms such as an award of monetary damages, liquidation damages, specific performances, rescission, andDamages for disappointment
Damages for distress or disappointment are not generally allowed by the courts, but cases where the award of such damages has been considered and agreed includeRight to terminate for breach
A right to terminate a contract arises for: # ''breach of a condition'' of the contract, no matter how trivial the breach of the condition may be; # ''repudiatory breach'', that is an actual breach of an innominate term, where the consequence of the breach is sufficiently serious to give rise to a right to terminate; or # ''renunciatory breach'' (aka anticipatory breach), where the other party makes clear to the innocent party that it: ## is not going to perform the contract at all, or ## is going to commit a breach of a condition, or ## is going to commit a breach of an innominate term, :: and the consequences will be such as to entitle the innocent party to treat the contract as at an end. An innocent party is therefore entitled to elect to terminate a contract only for breach of a condition of the contract, repudiatory breach or renunciatory breach. To terminate a contract for repudiatory breach, the innocent party must tell the defaulting party. Many commercial contracts include clauses that set out a process whereby notice must be given and in what form. Consequently, if there is a written contract, care should be taken to check the contract terms and to ensure compliance notwithstanding that the other party may, on the face of it, have committed a clear and repudiatory breach. It is only when the defaulting party is told that a repudiatory breach has been "accepted" that the contract is terminated. If the defaulting party is not told the repudiatory breach has been accepted, the contract continues in force. An innocent party is not compelled to exercise its right to terminate, and accept a repudiatory breach. Otherwise, the contract continues in force.Repudiatory breaches
Conduct is repudiatory if it deprives the innocent party of ''substantially the whole of the benefit'' intended received as consideration for performance of its future obligations under the contract. Different forms of words are used by courts to express this central concept. The most prominent is whether the breach goes to ''the root of the contract''. Those forms of words are simply different ways of expressing the "substantially the whole benefit" test. Sometimes the innocent party may be deprived of its entitlement to damages for repudiatory breach of contract: *if the innocent party is ''irremediably disabled from performance'', provided that that inability to perform on the part of the innocent party is not itself attributable to the repudiatory breach; *if the innocent party has ''a settled intention not to perform''.Renunciatory breaches
Conduct is renunciatory if shows an intention to commit a repudiatory breach. The conduct would lead a reasonable person to conclude that the party does not intend to perform its future obligations when they fell due. Showing an intention to perform a contract in a manner which is ''inconsistent'' with the terms of the contract also shows an intention not to perform the contract. Whether such conduct is so severe so as to amount to a renunciatory breached depends upon whether the threatened difference in performance is repudiatory. An intention to perform connotes a willingness to perform, but willingness in this context does not mean a desire to perform despite an inability to do so. To say "I would like to but I cannot" negatives intent just as much as "I will not". Contracting parties must perform contracts in strict accordance with their terms: what was agreed in the first instance when the contract was formed. To do otherwise is therefore a breach of contract. In the event of a renunciatory breach, the innocent party may: * choose to accept the breach at once and to terminate the contract, without waiting for the due date of performance, or * wait for the time for performance of the contract. If the defaulting party does not perform when the time for performance arrives, the contract may be terminated. However, if the defaulting party performs, the right to terminate is lost forever. Conduct comprising a breach for performance of contractual obligations that have fallen due may be insufficient to be a repudiation. However: * Nevertheless, conduct may be a renunciation because it would lead the reasonable observer to conclude that there was an intention not to perform in the future, and * the past and threatened future breaches taken together would be repudiatory. The reason for a defaulting party committing an actual breach is generally irrelevant to whether it constitutes a breach, or whether the breach is a repudiation (this is an incident of ''strict liability'' for the performance of contractual obligations). However, the reason may be highly relevant to what such breach would lead the reasonable observer to conclude about the defaulting party's intentions in relation to future performance and therefore to the issue of renunciation. Often, the question whether conduct is a renunciation falls to be judged by reference to the defaulting party's intention, which is objectively evinced by past breaches and other words and conduct.Breach of warranty
A breach of a warranty of a contract creates a right to damages for the loss suffered, which was caused by the breach. These "minor" breaches do not entitle the innocent party to terminate the contract. The innocent party cannot sue the party in default forBreach of a condition
Breach of a ''condition'' of a contract is known as a ''repudiatory breach''. Again, a repudiatory breach entitles the innocent party at common law to (1) terminate the contract, and (2) claim damages. No other type of breach except a repudiatory breach is sufficiently serious to permit the innocent party to terminate the contract for breach.Types of breach
Contracts often use wording other than ''repudiatory breach'' to describe a type of breach of contract. These contractual terms include ''material breach'', ''fundamental breach'', ''substantial breach'', ''serious breach''. These alternative wordings have no fixed meaning in law but are interpreted within the context of the contract that they are used. For that reason, the meaning of the different terms varies from case to case. Possible interpretations of their meaning include "repudiatory breach", and "serious breach, but not as serious as a repudiatory breach".Trivial breach
A ''trivial breach'' is one that does not meet the standard for designation as a material, serious or substantial breach. An Arizona Supreme Court decision in a 1990 commercial retail lease case noted that "the overwhelming majority of Sjurisdictions... hold the landlord's right to terminate is not unlimited. We believe a court's decision to permit termination must be tempered by notions of equity and common sense. We thus hold a forfeiture for a trivial or immaterial breach of a commercial lease should not be enforced." In Rice (t/a The Garden Guardian) v Great Yarmouth Borough Council (2000), the UK Court of Appeal decided that a clause which provided that the contract could be terminated "if the contractor commits a breach of any of its obligations under the contract" should not be given its literal meaning: it was considered "contrary to business common sense" to allow any breach at all, however trivial, to create grounds for termination.Winser, C., ''Terminating a Commercial Contract for Material Breach'', Crown Office Chambers, June 2007Material breach
A ''material breach'' has been held to mean "a breach of contract which is more than trivial, but need not be repudiatory" and confirmed as meaning "a breach which is substantial. The breach must be a serious matter, rather than a matter of little consequence." A breach of contract will likely constitute a material breach if the term of the contract which has been breached is a condition of the contract. A variety of tests may be applied to terms of contracts to decide whether a term is a warranty or a condition of the contract. In respect to the EPC Agreements, material breach is defined as "shall mean a breach by either Party of any of its obligations under this Agreement which has or is likely to have a Material Adverse Effect on the Project and which such Party shall have failed to cure". Other UK cases which relate to the concept of a material breach include: * National Power plc v United Gas Company Ltd. (1998), where Colman J considered wording relating to "a material breach of any of he guilty party'sobligations", allowing termination of the contract if remedy of such breach had not been commenced within seven days. The judge ruled that recognition that a material breach might be remedied distinguished the concept from a repudiatory breach, and there was no commercial sense in a clause restricting the common law rights of the innocent party, in relation to a repudiatory breach, and therefore "material breach" must refer to a form of breach which is not repudiatory. *Glolite Ltd. v Jasper Conran Ltd. (1998), where Neuberger J stated that and that *Phoenix Media Limited v Cobweb Information (2000) * Dalkia Utilities Services plc v Celtech International (2006) noted that assessing "materiality" involved looking at the actual breaches, their consequences, he guilty party'sexplanation for the breaches, their context within the agreement, the consequences of holding the agreement determined and the consequences of allowing the agreement to continue. Financial difficulties experienced by Celtech meant that they missed three payments out of 174 due over the 15 year life of the contract. These represented 8.5% of the total contract sum and were therefore not trivial or minimal, but Celtech were making attempts to pay and therefore not in repudiatory breach. Celtech were, however, in material breach of the contract and the contractual right to terminate could therefore be exercised by Dalkia. * Gallaher International Ltd v Tlias Enterprises (2008) *Crosstown Music Company v Rive Droite Music Ltd (2009), also making the point that a "material" breach was more significant than a "trivial" breach.England and Wales High Court (Chancery Division)Right to remedy a breach
A party in breach of contract may have the right to remedy their breach, for example if the breach itself is remediable and a provision for remedy or a time period for exercising such as right is included within the contract. In the case of Vinergy International (PVT) Ltd v Richmond Mercantile Limited FZC (2016), a clause within the contract between the disputing parties stated that "failure ... to observe any of the terms herein and to remedy the same where it is capable of being remedied within the period specified in the notice given by the aggrieved party to the party in default, calling for remedy, being a period not less than twenty (20) days" would constitute grounds for termination of the contract. The period allowed for such a remedy may be referred to as a "cure period".Upadhyaya, N.Fundamental breach
'' Fundamental breach'' of contract is no longer the test for a serious breach of contract to justify termination. The test is that set out for repudiatory breach, above. The concept of fundamental breach as a free standing legal concept no longer has any legal force but is now simply another possible term of a contract that needs to be construed like any other term of a contract. A ''fundamental breach'' is usually read as a reference to a repudiatory breach. A term may be a condition inAnticipatory breach
Renunciatory breach (usually referred to as ''anticipatory breach'' or ''breach by anticipatory repudiation'') is an unequivocal indication that the party will not perform when performance falls due or a situation in which future non-performance is inevitable. An anticipatory breach gives the innocent party the option to terminate the contract immediately and sue for damages or to wait for the time of performance. If the party required to perform does not do so when it is required by the contract, the innocent party can terminate then. For example, A contracts with B on January 1 to sell 500 quintals of wheat and to deliver it on May 1. Subsequently, on April 15, A writes to B and says that he will not deliver the wheat. B may immediately consider the breach to have occurred and file a suit for damages for the scheduled performance even though A has until May 1 to perform. However, a unique feature of anticipatory breach is that if an aggrieved party chooses not to accept a repudiation occurring before the time set for performance, the contract continues on foot, but also there will be no right to damages unless an actual breach occurs.See also
* Anticipatory repudiation *References