Yadadri Thermal Power Plant
   HOME

TheInfoList



OR:

Yadadri Thermal Power Plant or Yadadri TPS is an upcoming 4000
megawatt The watt (symbol: W) is the unit of power or radiant flux in the International System of Units (SI), equal to 1 joule per second or 1 kg⋅m2⋅s−3. It is used to quantify the rate of energy transfer. The watt is named after James ...
, supercritical thermal power project coming up at Dameracherla,
Nalgonda district Nalgonda district is a district in the Telangana state of India. Nalgonda district has the highest number of mandals in the state with 31 mandals. The district shares boundaries with Suryapet, Rangareddy, Yadadri and Nagarkurnool districts an ...
in
Telangana Telangana (; , ) is a state in India situated on the south-central stretch of the Indian peninsula on the high Deccan Plateau. It is the eleventh-largest state and the twelfth-most populated state in India with a geographical area of and 3 ...
,
India India, officially the Republic of India (Hindi: ), is a country in South Asia. It is the seventh-largest country by area, the second-most populous country, and the most populous democracy in the world. Bounded by the Indian Ocean on the so ...
. The project is second largest in
South India South India, also known as Dakshina Bharata or Peninsular India, consists of the peninsular southern part of India. It encompasses the Indian states of Andhra Pradesh, Karnataka, Kerala, Tamil Nadu, and Telangana, as well as the union territ ...
, at a cost of ₹25,099 crores (US$3.8 billion) and is expected to complete by October 2021 in a phased manner. The state-owned Telangana State Power Generation Corporation Limited (
TSGENCO Telangana State Power Generation Corporation Limited is a division of Telangana State Electricity Board. It is responsible for power generation in thr state of Telangana. It has ceased to do power trading and has retained with powers of control ...
) is building the 5 x 800
mega Mega or MEGA may refer to: Science * mega-, a metric prefix denoting 106 * Mega (number), a certain very large integer in Steinhaus–Moser notation * "mega-" a prefix meaning "large" that is used in taxonomy * Gravity assist, for ''Moon-Eart ...
thermal power station, built on 2800 acres near Veerlapalem Village in Nalgonda District, the second mega project announced by the Telangana government after
Bhadradri Thermal Power Plant Bhadradri Thermal Power Station is a proposed power plant project located near Edulla Bayyaram at Manuguru in the Indian state of Telangana. History Chief Minister of Telangana Kalvakuntla Chandrashekar Rao laid down foundation stone for this ...
.


History

Chief Minister of Telangana,
K. Chandrashekar Rao Kalvakuntla Chandrashekar Rao (born 17 February 1954), often referred to by his initials KCR, is an Indian politician serving as the first and current Chief Minister of Telangana since 2 June 2014. He is the founder and leader of the Bharat Ra ...
laid the foundation stone for the project on 8 June 2015 at Veerlapalem village, Dhamacherla mandal. The name was rechristened from Damaracharla Thermal Power Plant as Yadadri.


The Project

The BHEL order, the largest ever in India for the company, includes design, supply, erection and commissioning of project on EPC basis. The project completion is executed on fast track basis within 36 months for first two units and balance three units in 48 months from October 2017. This is the biggest project executed by
BHEL Bharat Heavy Electricals Limited (BHEL) is an Indian central public sector undertaking. It is under the ownership of Ministry of Heavy Industries, Government of India. It is based in New Delhi, India. Established in 1956, BHEL is India ...
. Recently, joined Team Uppur including Best Engineers like: Anand Kumar, Sr Engineer; Naveen Kumar, Dy Manager; Rakesh Roushan, Manager; Ashok Kumar, Manager have speeded up the Project Progress. Already available Classy Engineers like Pranjal Jain, Sr Engineer & Deepak Kumar Mandal, Sr Engineer are contributing towards Site Progress. After successful completion of their previous Projects, the team is ready with new zeal to complete Yadadri TPP also. With joining of Team Uppur Engineers at Yadadri, already working manpower at Site is feeling highly motivated to complete this project also.


Clearances

The project has been accorded environmental clearance by the Ministry of Environment, Forest and Climate Change (MoEF&CC)in June 2017 and yet to get water allocation from Krishna river. MoEF granted Environment clearance to this thermal power plant on June 29, 2017. LOI issued to BHEL with zero date 17 October 2017. The revised environment norms at the center, the 4000 MW project will cost Telangana an additional ₹3100 crore. The new environment norms mandate setting-up of flue-gas desulfurization (FGD) devices.


Capacity

The planned capacity of the thermal power plant is 4000 MW (5 x 800 MW)


References

Nalgonda district Coal-fired power stations in Telangana Government of Telangana KCR Government initiatives Proposed infrastructure in Telangana Proposed power stations in India {{India-powerstation-stub