The island of Ireland has 5,585
megawatt The watt (symbol: W) is the unit of power or radiant flux in the International System of Units (SI), equal to 1 joule per second or 1 kg⋅m2⋅s−3. It is used to quantify the rate of energy transfer. The watt is named after James ...
and the
Republic of Ireland Ireland ( ga, Éire ), also known as the Republic of Ireland (), is a country in north-western Europe consisting of 26 of the 32 Counties of Ireland, counties of the island of Ireland. The capital and largest city is Dublin, on the eastern ...
has 4,309 MW of installed
wind power Wind power or wind energy is mostly the use of wind turbines to generate electricity. Wind power is a popular, sustainable, renewable energy source that has a much smaller impact on the environment than burning fossil fuels. Historically ...
nameplate capacity Nameplate capacity, also known as the rated capacity, nominal capacity, installed capacity, or maximum effect, is the intended full-load sustained output of a facility such as a power station,
, the third highest per capita in the world. In 2020 wind turbines generated 36.3% of Ireland's electrical demand, one of the highest wind power penetrations in the world. Ireland has over 300
wind farm A wind farm or wind park, also called a wind power station or wind power plant, is a group of wind turbines in the same location used to produce electricity. Wind farms vary in size from a small number of turbines to several hundred wind turb ...
s (nearly 400 all-island); mostly onshore, with only the 25 MW
Arklow Bank Wind Park Arklow Bank Wind Park is a 25 megawatt offshore wind farm generating electrical power for the County Wicklow, Wicklow region in Republic of Ireland, Ireland. It is the first offshore wind farm in Ireland, and the world's first erection of ...
situated offshore as of 2020. This is unlike
Germany Germany,, officially the Federal Republic of Germany, is a country in Central Europe. It is the second most populous country in Europe after Russia, and the most populous member state of the European Union. Germany is situated betwe ...
and Great Britain two other European countries with high wind power penetration whose territorial waters (particularly the
German Bight The German Bight (german: Deutsche Bucht; da, tyske bugt; nl, Duitse bocht; fry, Dútske bocht; ; sometimes also the German Bay) is the southeastern bight of the North Sea bounded by the Netherlands and Germany to the south, and Denmark and ...
and waters off the coast of Scotland) are in extensive and growing use for offshore wind power. Ireland's instantaneous wind power generation fluctuates between near zero and nearly 4,500 MW due to weather, with an average
capacity factor The net capacity factor is the unitless ratio of actual electrical energy output over a given period of time to the theoretical maximum electrical energy output over that period. The theoretical maximum energy output of a given installation is def ...
of 32.3% in 2015. Irish wind power generation is higher during winter and lower in the summer. The overall capacity factor of Irish wind farms is high compared to the global average of onshore wind farms which usually ranges around 20% but significantly lower than that of offshore wind farms which often achieve capacity factors around 50%. Ireland uses an EU industry subsidy known as the Public Service Obligation to support development of wind and other domestic power generation, currently levied at €72 per year per household. In the 2016/17 period, €308 million raised through this levy was planned to be granted to supporting domestic renewable energy schemes. For comparison €120.90 million was planned to be granted to (non renewable)
peat Peat (), also known as turf (), is an accumulation of partially decayed vegetation or organic matter. It is unique to natural areas called peatlands, bogs, mires, moors, or muskegs. The peatland ecosystem covers and is the most efficient ...
generation. Concerns over energy security (Ireland lacks significant onshore fossil fuel resources other than peat, and has extensive wind resources), climate change mitigation policies, and compliance with EU Directives for market liberalisation, have all shaped wind power development in Ireland


Capacity Growth

Eddie O’Connor, then CEO of the semi-state owned peat harvesting company, Bord na Móna, commissioned the country's first "commercial wind farm" in a cutaway
peat bog A bog or bogland is a wetland that accumulates peat as a deposit of dead plant materials often mosses, typically sphagnum moss. It is one of the four main types of wetlands. Other names for bogs include mire, mosses, quagmire, and muskeg; a ...
in County Mayo in 1992. Following the first commercial wind farm, wind power deployment in the Republic of Ireland started slowly in the 1990s, but increased more rapidly from the 2000s onwards. Whilst annual wind capacity growth has been variable, it has shown an increasing trend (Figure 1). Wind power has provided a steadily increasing share of electricity, from 4% (1,874 GWh) in 2005, to 28% in 2018 (10,195 GWh) (Figure 2). In the first two months of 2020, wind provided 49% of electricity demand, and a peak recorded output from wind power of 4,471 MW was delivered on 12 February 2021. Wind is now the second largest source of electricity generation after natural gas, which accounted for 52% of electricity generated in 2018.


Drivers of wind power expansion

Concerns over energy security (Ireland has an estimated 15.4m tonnes of coal reserves, peat bogs, offshore oil and gas fields, and has extensive wind resources), climate change mitigation policies, and compliance with EU Directives for market liberalisation, have all shaped wind power development in Ireland. In the Directive 2001/77/EC, otherwise known as the RES-E Directive, the
European Union The European Union (EU) is a supranational political and economic union of member states that are located primarily in Europe. The union has a total area of and an estimated total population of about 447million. The EU has often been de ...
stated a goal to have 22% of the total energy consumed by member states to be produced from renewable energy resources by 2010. As a result, Ireland, in a report titled "Policy Consideration for Renewable Electricity to 2010", made the commitment to have 4% of its total energy consumption come from renewable energy resources by 2002 and 13.2% by 2010. The Department of Communications Marine and Natural Resources (DCMNR) founded the Renewable Energy Group (REG) which established the short term analysis group (STAG) to investigate a means of accomplishing this goal. To meet the 2010 target of 13.2%, 1,432 MW of electricity will need to be generated from renewable resources with 1,100 MW being generated from wind resources both onshore and offshore.


State financial support

State financial support for the national electricity sector, and particular technologies, has been influenced by a slow move towards liberalisation, and concerns for energy security and climate change mitigation. Ireland uses an industry subsidy known as the Public Service Obligation (PSO) to support the generation of electricity from sustainable, renewable and indigenous sources, including wind. The PSO levy is charged to all electricity customers. As of April 2020, for residential consumers, the current PSO levy is €38.68 per year inclusive of VAT, and is displayed on the typical two-monthly electricity bill as €5.68 (€2.84 x 2) + 13.5% VAT. The PSO levy funds the government's main mechanisms to support the generation of electricity from sustainable, renewable and indigenous sources. These mechanisms have shifted from the initial use of competitive auctions in the late 1990s, to a renewable energy
feed-in tariff A feed-in tariff (FIT, FiT, standard offer contract,Couture, T., Cory, K., Kreycik, C., Williams, E., (2010)Policymaker's Guide to Feed-in Tariff Policy Design National Renewable Energy Laboratory, U.S. Dept. of Energy advanced renewable tariff, ...
(REFiT) from 2006 to 2015, and back to a new renewable energy auction scheme as of 2020. Ireland's initial use of competitive auction from 1996 failed to support the intended growth in wind development. Between 2006 and 2015, the government supported a REFiT, secured for 15 years. The 2020 REFiT reference price for large wind (>5MW) is €70.98 /MWh and for small wind (<5MW) is €73.47/MWh. In June, 2020, Ireland will run its first competitive renewable energy auction under the government's new Renewable Energy Support Scheme (RESS-1). RESS-1 support is structured as a two-way floating feed-in premium (FIP), roughly the difference between the 'strike price' set in the successful auction bid and the 'market reference price'. When costs of electricity suppliers exceed market revenues a Support Payment will be due to the supplier, and when market revenues exceed costs a Difference Payment will be due from the supplier. An economic analysis of the financial cost of different RESS options, estimated that a least cost auction with floating FIP mechanism would cost a domestic consumer €0.79 per month by 2030 (at 2017 prices). This is significantly less than the current PSO levy rate to fund REFiT costs.


Offshore wind power

The
Arklow Bank Wind Park Arklow Bank Wind Park is a 25 megawatt offshore wind farm generating electrical power for the County Wicklow, Wicklow region in Republic of Ireland, Ireland. It is the first offshore wind farm in Ireland, and the world's first erection of ...
, located 10 km off the coast of
Arklow Arklow (; ; , ) is a town in County Wicklow on the southeast coast of Ireland. The town is overlooked by Ballymoyle Hill. It was founded by the Vikings in the ninth century. Arklow was the site of one of the bloodiest battles of the 1798 re ...
on the Arklow Bank in the
Irish Sea The Irish Sea or , gv, Y Keayn Yernagh, sco, Erse Sie, gd, Muir Èireann , Ulster-Scots: ''Airish Sea'', cy, Môr Iwerddon . is an extensive body of water that separates the islands of Ireland and Great Britain. It is linked to the Ce ...
, was Ireland's first offshore wind farm. The wind farm is owned and built by
GE Energy GE Power (formerly known as GE Energy) is an American energy technology company, owned by General Electric. Structure As of July 2019, GE Power is divided into the following divisions: * GE Gas Power (formerly Alstom Power Turbomachines), bas ...
and was co-developed by
Airtricity SSE Airtricity (previously Eirtricity) is an energy company founded in Ireland in 1997, and now a subsidiary SSE plc. SSE Airtricity supplies and distributes electricity and gas to Northern Ireland and the Republic of Ireland. History The com ...
and GE Energy. The site has 7 GE Energy 3.6 MW turbines that generate a total of 25 MW. The development of the site was originally divided into two phases with the first phase being the current installation of 7 turbines. The second phase was a partnership between Airtricity and
Acciona Energy Acciona, S.A. () is a Spanish multinational conglomerate dedicated to the development and management of infrastructure (construction, water, industrial and services) and renewable energy. The company, via subsidiary Acciona Energy, produces 21 te ...
. Acciona Energy had an option to buy the project after the facility is completed. The wind farm was planned to expand to 520 MW of power. However, in 2007, Phase 2 was cancelled. Although the waters off the Atlantic coastline of Ireland have higher winds, sites along the eastern coastline such as Arklow were chosen because of the shallower waters, which are 20 m deep or less. The National Offshore Wind Association of Ireland (NOW Ireland) announced in April 2010 that 60,000 potential jobs could be created in the Irish marine, construction, engineering and service industries through the development of offshore wind energy in Irish and European waters. NOW Ireland also announced in the same month that over €50bn was due to be invested in the Irish Sea and Celtic Sea in the next two decades. In Belfast, the harbour industry is being redeveloped as a hub for offshore windfarm construction, at a cost of about £50m. The work will create 150 jobs in construction, as well as requiring about 1m tonnes of stone from local quarries, which will create hundreds more jobs. "It is the first dedicated harbour upgrade for offshore wind".


Current trends

Grid connection is currently awarded on a 'first come, first connect' basis through Gate 3 procedures. On examination of the Gate 3 queue, there are a number of large onshore and offshore wind projects that are down the list and will, therefore, be offered grid connection towards the end of the anticipated 18-month processing period commencing in December 2009. While planning permission normally expires after 5 years, the Planning and Development Act 2000 section 41 allows for a longer period. At present it is common to apply and obtain a 10-year permission for a wind energy development. Section 42 of the above Act originally permitted a 5-year extension of the "appropriate period" provided that substantial works were carried out. This caused major problems as the term "substantial works" was not clearly defined which resulted in a large variety in interpretation of what constituted substantial works among the various planning authorities. This issue was rectified by the Planning and Development (Amendment) Act 2010 section 28 which inserted an additional paragraph allowing a once off extension not exceeding 5 years if "there were considerations of a commercial, economic or technical nature beyond the control of the applicant which substantially militated against either the commencement of development or the carrying out of substantial works pursuant to the planning permission" The fourth issue regarding the generation of wind power is the Renewable Energy
Feed-in Tariff A feed-in tariff (FIT, FiT, standard offer contract,Couture, T., Cory, K., Kreycik, C., Williams, E., (2010)Policymaker's Guide to Feed-in Tariff Policy Design National Renewable Energy Laboratory, U.S. Dept. of Energy advanced renewable tariff, ...
, or REFIT. The purpose of REFIT is to encourage development of renewable energy resources. For wind power production, the current limit to the tariff is 1,450 MW. However, applications currently being processed for grid connections exceed the limit by almost 1,500 MW for a total for nearly 3,000 MW. Since the limit is 1,450 MW, many of the applications for grid connections may not eligible for the tariff.


5 largest onshore wind farms


Controversy


Economy

In 2011, the 120-member Irish Academy of Engineering described wind as "an extremely expensive way of reducing greenhouse gas emissions when compared to other alternatives" like conservation, nuclear energy or the
Corrib gas project The Corrib gas project ( ga, Tionscanamh Ghás Aiceanta na Coiribe) is a developed natural gas deposit located in the Atlantic Ocean, approximately off the northwest coast of County Mayo, Ireland. The project includes a natural gas pipeline and ...
and Liquified Gas tanker imports at Shannon, concluding that the suggestion of 40% grid penetration by wind, is "unrealistic". In 2020, grid penetration had hit 36.3% and was still increasing but far slowly. By contrast, the
Sustainable Energy Authority of Ireland The Sustainable Energy Authority of Ireland (SEAI) ( ga, Údarás Fuinnimh Inmharthana na hÉireann) is an Irish governmental body established to promote and aid in the development of sustainable energy in Ireland. History The SEAI was founded ...
said in 2014 that wind power cost the same as gas power. In 2020 the
Irish Times ''The Irish Times'' is an Irish daily broadsheet newspaper and online digital publication. It launched on 29 March 1859. The editor is Ruadhán Mac Cormaic. It is published every day except Sundays. ''The Irish Times'' is considered a newspaper ...
reported that the cost of onshore wind energy had dropped over the last 20 years but that regulation on noise and height of turbines made Irish wind energy more expensive than elsewhere.


Peatlands and bog landslides

Building wind turbines and access roads on top of
peatland A mire, peatland, or quagmire is a wetland area dominated by living peat-forming plants. Mires arise because of incomplete decomposition of organic matter, usually litter from vegetation, due to water-logging and subsequent anoxia. All types ...
results in the drainage and then eventual
oxidation Redox (reduction–oxidation, , ) is a type of chemical reaction in which the oxidation states of substrate change. Oxidation is the loss of electrons or an increase in the oxidation state, while reduction is the gain of electrons or a ...
of some of the peat. The turbines represent a minor impact,Richard Lindsay
Peat bogs and carbon
page 164. ''
University of East London , mottoeng = Knowledge and the fulfilment of vows , established = 1898 – West Ham Technical Institute1952 – West Ham College of Technology1970 – North East London Polytechnic1989 – Polytechnic of East London ...
'', 14 June 2010
provided that the entire wind farm area is not drained, potentially emitting more
carbon dioxide Carbon dioxide ( chemical formula ) is a chemical compound made up of molecules that each have one carbon atom covalently double bonded to two oxygen atoms. It is found in the gas state at room temperature. In the air, carbon dioxide is trans ...
(CO2) than the turbines would save.Richard Lindsay
Wind farms and blanket peat
page 70, 79-87, 111. ''
University of East London , mottoeng = Knowledge and the fulfilment of vows , established = 1898 – West Ham Technical Institute1952 – West Ham College of Technology1970 – North East London Polytechnic1989 – Polytechnic of East London ...
'', 2004
Biochemist Mike Hall said in 2009; "wind farms (built on peat bogs) may eventually emit more carbon than an equivalent coal-fired power station" if drained. A 2014 report for the
Northern Ireland Environment Agency The Northern Ireland Environment Agency (NIEA) is an executive agency within the Department of Agriculture, Environment and Rural Affairs (DAERA). It is responsible for conservation of Northern Ireland's environment and natural heritage. Origi ...
, which has similar peatland, notes that building wind turbines on peatland could release considerable carbon dioxide from the peat, weaken
flood control Flood control methods are used to reduce or prevent the detrimental effects of flood waters."Flood Control", MSN Encarta, 2008 (see below: Further reading). Flood relief methods are used to reduce the effects of flood waters or high water level ...
, and spoil water quality: "The potential knock-on effects of using the peatland resource for wind turbines are considerable and it is arguable that the impacts on this facet of
biodiversity Biodiversity or biological diversity is the variety and variability of life on Earth. Biodiversity is a measure of variation at the genetic (''genetic variability''), species (''species diversity''), and ecosystem (''ecosystem diversity'') l ...
will have the most noticeable and greatest financial implications for Northern Ireland." The
Irish Peatland Conservation Council The Irish Peatland Conservation Council (IPCC; ) is a national charitable organisation established in 1982 to conserve and protect a representative sample of Irish bogs, and to campaign on bog-related issues. History Having been for many years in D ...
maintains a database on incidences where building wind turbines (and wind farms) on or near peatland caused devastating
landslides Landslides, also known as landslips, are several forms of mass wasting that may include a wide range of ground movements, such as rockfalls, deep-seated slope failures, mudflows, and debris flows. Landslides occur in a variety of environments, ...
, called "bog bursts"/"peat flows". These accelerate the release of carbon dioxide into the atmosphere. In October 2003, the building of a wind farm in County Galway caused the Derrybrien landslide, an almost 2.5 km long, 450,000 m3 bog landslide, polluting a nearby lake and killing 50,000 fish. The lake was also the source of the town of
Gort Gort ( or ) is a town of around 3,000 inhabitants in County Galway in the west of Ireland. Located near the border with County Clare, the town lies between the Burren and the Slieve Aughty and is served by the R458 and R460 regional roads, wh ...
's drinking water. If all carbon in the slide is being released, it represents 7–15 months of production from the wind farm in avoided carbon dioxide from fossil power. In 2004, engineering companies were convicted of being responsible for the pollution, while the wind farm company was acquitted. The Irish government was convicted in 2008 of poor oversight. Following the Corrie Mountain bog burst of 2008, Ireland was fined by a European Court over its mishandling of wind farms on peatland. By 2010, there had been at least three major bog landslides related to wind farms in Ireland. In 2020, there was another large bog landslide at a wind farm construction site at Meenbog,
County Donegal County Donegal ( ; ga, Contae Dhún na nGall) is a county of Ireland in the province of Ulster and in the Northern and Western Region. It is named after the town of Donegal in the south of the county. It has also been known as County Tyrconn ...
. This polluted rivers that are protected Atlantic salmon habitats, and was predicted to have caused a "complete fish kill". Drinking water supplies linked to the rivers had to be suspended. The body representing industrial peat harvesting in Ireland, Bord na Móna, announced in 2015 the "biggest change of land use in modern Irish history": harvesting peat is being phased out by 2030, due to the long-expected depletion of profitable lowland peat, at which point the company would complete its transition to becoming a "sustainable biomass, wind and solar power" organization.


Local opposition

Some on-land wind farms in Ireland have been opposed by local residents, county councils, the
Heritage Council The Heritage Council ( ga, An Comhairle Oidhreachta) is an organisation created by the Irish government to "engage, educate and advocate to develop a wider understanding of the vital contribution that our heritage makes to our social, environmenta ...
and An Taisce (The National Trust) for their potential to blight the landscape, and having a harmful impact on protected scenic areas, archaeological landscapes, tourism and cultural heritage. In 2014, more than 100 protest groups united against government plans to build thousands of wind turbines in the Midlands to export energy to Britain. Among other things, they argued the wind farms would ruin the landscape and mainly benefit "multinational corporations who are sucking subsidies from the UK taxpayers". The Irish government shelved the plans. In 2021 a proposed wind farm at Kilranelagh in the
Wicklow Mountains The Wicklow Mountains (, archaic: ''Cualu'') form the largest continuous upland area in the Republic of Ireland. They occupy the whole centre of County Wicklow and stretch outside its borders into the counties of Dublin, Wexford and Carlow. ...
was refused as it would have harmed the area's archaeological landscape, which includes the Baltinglass
hillfort A hillfort is a type of earthwork used as a fortified refuge or defended settlement, located to exploit a rise in elevation for defensive advantage. They are typically European and of the Bronze Age or Iron Age. Some were used in the post-Roma ...
complex. An application to build a wind farm overlooking the scenic valley of
Gougane Barra Gougane Barra () is a scenic valley and heritage site in the Shehy Mountains of County Cork, Ireland. It is near Ballingeary in the Muskerry ''Gaeltacht''. Gougane Barra is at the source of the River Lee and includes a lake with an oratory built ...
was refused by
Cork County Council Cork County Council ( ga, Comhairle Contae Chorcaí) is the authority responsible for local government in County Cork, Ireland. As a county council, it is governed by the Local Government Act 2001. The council is responsible for housing and ...
, who voted unanimously against it. The company appealed to
An Bord Pleanála (; meaning "The Planning Board"; ABP) is an independent, statutory, quasi-judicial body that decides on appeals from planning decisions made by local authorities in the Republic of Ireland. As of 2007, An Bord Pleanála directly decided major ...
, whose inspector also rejected it, stating it "would have significant adverse environmental and visual impacts and is not sustainable at this highly sensitive location". Despite this, An Bord Pleanála granted permission, on the grounds that the wind farm would contribute "to the implementation of Ireland's national strategic policy on renewable energy". The spokesman of the campaigners against the wind farm said the decision was undemocratic, as the local people and council opposed it.


Environmental Impact & Greenhouse gases

In a typical study of a wind farms
Life cycle assessment Life cycle assessment or LCA (also known as life cycle analysis) is a methodology for assessing environmental impacts associated with all the stages of the life cycle of a commercial product, process, or service. For instance, in the case o ...
(LCA), in isolation, it usually results in similar findings as the following 2006 analysis of 3 installations in the US Midwest, were the carbon dioxide ( CO2) emissions of wind power ranged from 14 to 33
metric ton The tonne ( or ; symbol: t) is a unit of mass equal to 1000  kilograms. It is a non-SI unit accepted for use with SI. It is also referred to as a metric ton to distinguish it from the non-metric units of the short ton ( United State ...
per GWh (14 - 33 g CO2/ kWh) of energy produced, with most of the CO2 emissions coming from the production of concrete for wind-turbine foundations. However, when approached from the effects on the grid as a whole, that assess wind turbines' ability to reduce a country's total electric grid
emission intensity An emission intensity (also carbon intensity or C.I.) is the emission rate of a given pollutant relative to the intensity of a specific activity, or an industrial production process; for example grams of carbon dioxide released per megajoule o ...
, a study by the Irish national grid, a grid that is predominately (~70%) powered by fossil gas, (and if it was 100% gas, would result in emissions of 410 - 650 g CO2/ kWh.) found that "Producing electricity from wind reduces the consumption of fossil fuels and therefore leads to lectric gridemissions savings", with findings in reductions of the grid-wide CO2 emissions to 0.33-0.59
metric ton The tonne ( or ; symbol: t) is a unit of mass equal to 1000  kilograms. It is a non-SI unit accepted for use with SI. It is also referred to as a metric ton to distinguish it from the non-metric units of the short ton ( United State ...
of CO2 per MWh (330 - 590 g CO2/ kWh). These findings were of relatively "low
mission Mission (from Latin ''missio'' "the act of sending out") may refer to: Organised activities Religion *Christian mission, an organized effort to spread Christianity *Mission (LDS Church), an administrative area of The Church of Jesus Christ of ...
savings", as presented in the Journal of '' Energy Policy'', and were largely due to an over-reliance on the results from the analysis of wind farms LCAs in isolation. As high
electric grid An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids vary in size and can cover whole countries or continents. It consists of:Kaplan, S. M. (2009). Smart Grid. Electrical Power ...
penetration by intermittent power sources e.g. wind power, sources which have low
capacity factor The net capacity factor is the unitless ratio of actual electrical energy output over a given period of time to the theoretical maximum electrical energy output over that period. The theoretical maximum energy output of a given installation is def ...
s due to the weather, either requires the construction of transmission to neighbouring areas, energy storage projects like the 292 MW Turlough Hill Power Station, that have their own additional
emission intensity An emission intensity (also carbon intensity or C.I.) is the emission rate of a given pollutant relative to the intensity of a specific activity, or an industrial production process; for example grams of carbon dioxide released per megajoule o ...
which must be accounted for, or the more common practice of requiring a higher reliance on fossil fuels than the
spinning reserve In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply. Most power sys ...
requirements necessary to back-up the more dependable/
baseload power The base load (also baseload) is the minimum level of demand on an electrical grid over a span of time, for example, one week. This demand can be met by unvarying power plants, dispatchable generation, or by a collection of smaller intermittent en ...
sources, such as hydropower and nuclear energy. This higher dependence on back-up/
Load following power plant A load-following power plant, regarded as producing mid-merit or mid-priced electricity, is a power plant that adjusts its power output as demand for electricity fluctuates throughout the day. Load-following plants are typically in between base lo ...
s to ensure a steady
power grid An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids vary in size and can cover whole countries or continents. It consists of:Kaplan, S. M. (2009). Smart Grid. Electrical Power ...
output has the knock-on-effect of more frequent inefficient (in e g/kW·h)
throttling A throttle is any mechanism by which the power or speed of an engine is controlled. Throttle or throttling may also refer to: Fiction * ''Throttle'' (film), a 2005 thriller * ''Throttle'' (novella), a 2009 novella by Stephen King and his son Jo ...
up and down of these other power sources in the grid to accommodate the intermittent power source's variable output. When one includes the intermittent sources total effect it has on other power sources in the grid system, that is, including these inefficient start up emissions of backup power sources to cater for wind energy, into wind energy's total system wide life cycle, this results in a higher real-world emission intensity related to wind energy than the in-isolation ''g/kW·h'' value, a statistic that is determined by looking at the power source in isolation and thus ignores all down-stream detrimental/inefficiency effects it has on the grid. In a 2012 paper that appeared in the ''Journal of Industrial Ecology'' it states. According to the
IPCC The Intergovernmental Panel on Climate Change (IPCC) is an intergovernmental body of the United Nations. Its job is to advance scientific knowledge about climate change caused by human activities. The World Meteorological Organization (WMO) ...
, wind turbines when assessed in isolation, have a median life cycle emission value of between 12 and 11 ( g eq/ kWh). While the more dependable alpine Hydropower and nuclear stations have median total life cycle emission values of 24 and 12 g CO2-eq/kWh respectively. Regarding interconnections, Ireland is connected to adjacent UK National Grid at an electricity interconnection level (transmission capacity relative to production capacity) of 9%.COM/2015/082 final: "Achieving the 10% electricity interconnection target
TextPDF
page 2-5. ''
European Commission The European Commission (EC) is the executive of the European Union (EU). It operates as a cabinet government, with 27 members of the Commission (informally known as "Commissioners") headed by a President. It includes an administrative body ...
'', 25 February 2015
ArchiveMirror
/ref> The two grids have a high wind correlation of 0.61, whereas the wind correlation between the Irish grid and the Danish grid is low at 0.09.


Tourism

One major aspect of wind farms in Ireland is tourist attraction and also local attraction. The Bord na Mona wind farm in Mount Lucas, Daingean, Co.Offaly has provided a local walk way through the newly established wind farm that attracts people of all ages. The walk way provides a safe environment off-road for walking, running and cycling. The walk way is approximately nine kilometres in distance with numerous stop off points for breaks. Maps can also be located in a variety of locations on the walk for guidance around the wind farm and back to allocated car parks. The walk way also provides aesthetic scenery on a relatively flat landscape. Such a walk attracts many people year round and circulates money back into the local community as tourists stop off in local shops.


Grid study in Ireland

An Irish study of the grid indicates that it would be feasible to accommodate 42% (of demand) renewables in the electricity mix. This acceptable level of renewable penetration was found in what the study called Scenario 5, provided 47% of electrical capacity (different from demand) with the following mix of renewable energies: * 6,000 MW wind * 360 MW base load renewables * 285 MW additional variable renewables (other intermittent sources) The study cautions that various assumptions were made that "may have understated dispatch restrictions, resulting in an underestimation of operational costs, required wind curtailment, and CO2 emissions" and that "The limitations of the study may overstate the technical feasibility of the portfolios analyzed..." Scenario 6, which proposed renewables providing 59% of electrical capacity and 54% of demand had problems. Scenario 6 proposed the following mix of renewable energies: * 8,000 MW wind * 392 MW base load renewables * 1,685 MW additional variable renewables (other intermittent sources) The study found that for Scenario 6, "a significant number of hours characterized by extreme system situations occurred where load and reserve requirements could not be met. The results of the network study indicated that for such extreme renewable penetration scenarios, a system re-design is required, rather than a reinforcement exercise." The study declined to analyze the cost effectiveness of the required changes because "determination of costs and benefits had become extremely dependent on the assumptions made" and this uncertainty would have impacted the robustness of the results.


See also

*
List of wind farms Lists of wind farms include: *List of onshore wind farms *List of offshore wind farms Wind farms by country * List of wind farms in Australia * List of wind farms in Canada * List of wind farms in China * List of wind farms in Denmark * List ...
*
List of offshore wind farms in the Irish Sea This is a complete list of operational, offshore wind farms in the Irish Sea and connected areas such as the Celtic Sea and North Channel. This information is gathered from multiple Internet sources,< at the top in each column. {{DEFAULTSORT:Wind Power In The Republic Of Ireland