Unit Commitment
   HOME

TheInfoList



OR:

Power system operations is a term used in electricity generation to describe the process of
decision-making In psychology, decision-making (also spelled decision making and decisionmaking) is regarded as the Cognition, cognitive process resulting in the selection of a belief or a course of action among several possible alternative options. It could be ...
on the timescale from one day (day-ahead operation) to minutes prior to the
power delivery Electricity delivery is the process that starts after generation of electricity in the power station, up to the use by the consumer. The main processes in electricity delivery are, by order: * Transmission * Distribution * Retailing See also *Ele ...
. The term power system control describes actions taken in response to unplanned ''disturbances'' (e.g., changes in demand or equipment failures) in order to provide reliable electric supply of acceptable quality. The corresponding engineering branch is called Power System Operations and Control. Electricity is hard to store, so at any moment the supply (generation) shall be balanced with demand ("
grid balancing Grid balancing ensures that electricity consumption matches electricity production of an electrical grid at any moment. Electricity is by its nature difficult to store and has to be available on demand, so the supply shall match the demand very cl ...
"). In an electrical grid the task of real-time balancing is performed by a regional-based control center, run by an electric utility in the traditional (
vertically integrated In microeconomics, management and international political economy, vertical integration is a term that describes the arrangement in which the supply chain of a company is integrated and owned by that company. Usually each member of the supply ...
) electricity market. In the restructured North American power transmission grid, these centers belong to '' balancing authorities'' numbered 74 in 2016, the entities responsible for operations are also called independent system operators, transmission system operators. The other form of balancing resources of multiple power plants is a
power pool Power pooling is used to balance electrical load over a larger network (electrical grid) than a single utility. It is a mechanism for interchange of power between two and more utilities which provide or generate electricity For exchange of power be ...
. The balancing authorities are overseen by
reliability coordinator Reliability, reliable, or unreliable may refer to: Science, technology, and mathematics Computing * Data reliability (disambiguation), a property of some disk arrays in computer storage * High availability * Reliability (computer networking), ...
s.


Day-ahead operation

Day-ahead operation schedules the generation units that can be called upon to provide the electricity on the next day (unit commitment). The dispatchable generation units can produce electricity on demand and thus can be scheduled with accuracy. The production of the weather-dependent variable renewable energy for the next day is not certain, its sources are thus non-dispatchable. This variability, coupled with uncertain future power demand and the need to accommodate possible generation and
transmission Transmission may refer to: Medicine, science and technology * Power transmission ** Electric power transmission ** Propulsion transmission, technology allowing controlled application of power *** Automatic transmission *** Manual transmission *** ...
failures requires scheduling of
operating reserve In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply. Most power sys ...
s that are not expected to produce electricity, but can be dispatched on a very short notice. Some units have unique features that require their commitment much earlier: for example, the nuclear power stations take a very long time to start, while hydroelectric plants require planning of water resources usage way in advance, therefore commitment decisions for these are made weeks or even months before prior to the delivery. For a "traditional"
vertically integrated electric utility In microeconomics, management and international political economy, vertical integration is a term that describes the arrangement in which the supply chain of a company is integrated and owned by that company. Usually each member of the supply c ...
the main goal of the unit commitment is to minimize both the
marginal cost In economics, the marginal cost is the change in the total cost that arises when the quantity produced is incremented, the cost of producing additional quantity. In some contexts, it refers to an increment of one unit of output, and in others it r ...
of producing the unit electricity and the (quite significant for fossil fuel generation) start-up costs. In a "restructured" electricity market a market clearing algorithm is utilized, frequently in a form of an auction; the merit order is sometimes defined not just by the monetary costs, but also by the environmental concerns. Unit commitment is more complex than the shorter-time-frame operations, since unit availability is subject to multiple constraints: * demand-supply balance need to be maintained, including the sufficient spinning reserves for contingency. The balance need to reflect the transmission constraints; * thermal units might have limits on minimum uptime (once switched on, cannot be turned off quickly) and downtime (once stopped, cannot be quickly restarted again); * "must-run" units have to run due to technical constraints (for example,
combined heat and power Cogeneration or combined heat and power (CHP) is the use of a heat engine or power station to generate electricity and useful heat at the same time. Cogeneration is a more efficient use of fuel or heat, because otherwise- wasted heat from elect ...
plants must run if their heat is needed); * there is usually a single crew at the plant that needs to be present during a thermal unit start-up, so only one unit can be started at a time.


Hours-ahead operation

In the hours prior to the delivery, a system operator might need to deploy additional supplemental reserves or even commit more generation units, primarily to ensure the reliability of the supply while still trying to minimize the costs. At the same time, operator must ensure that enough reactive power reserves are available to prevent the
voltage collapse Voltage, also known as electric pressure, electric tension, or (electric) potential difference, is the difference in electric potential between two points. In a static electric field, it corresponds to the work needed per unit of charge to ...
.


Dispatch curve

The decisions (" economic dispatch") are based on the dispatch curve, where the X-axis constitutes the system power, intervals for the generation units are placed on this axis in the '' merit order'' with the interval length corresponding to the maximum power of the unit, Y-axis values represent the marginal cost (per-
MWh A kilowatt-hour (unit symbol: kW⋅h or kW h; commonly written as kWh) is a unit of energy: one kilowatt of power for one hour. In terms of SI derived units with special names, it equals 3.6 megajoules (MJ). Kilowatt-hours are a common bil ...
of electricity, ignoring the startup costs). For cost-based decisions, the units in the merit order are sorted by the increasing marginal cost. The graph on the right describes an extremely simplified system, with three committed generator units (fully dispatchable, with constant per-MWh cost): * unit A can deliver up to 120 MW at the cost of $30 per MWh (from 0 to 120 MW of system power); * unit B can deliver up to 80 MW at $60/MWh (from 120 to 200 MW of system power); * unit C is capable of 50 MW at $120/MWh (from 200 to 250 MW of system power). At the expected demand is 150 MW (a vertical line on the graph), unit A will be engaged at full 120 MW power, unit B will run at the dispatch level of 30 MW, unit C will be kept in reserve. The area under the dispatch curve to the left of this line represents the cost per hour of operation (ignoring the startup costs, $30 * 120 + $60 * 30 = $5,400 per hour), the incremental cost of the next MWh of electricity ($60 in the example, represented by a horizontal line on the graph) is called system lambda (thus another name for the curve, ''system lambda curve''). In real systems the cost per MWh usually is not constant, and the lines of the dispatch curve are therefore not horizontal (typically the marginal cost of power increases with the dispatch level, although for the combined cycle power plants there are multiple cost curves depending on the mode of operation, so the power-cost relationship is not necessarily monotonic). If the minimum level of demand in the example will stay above 120 MW, the unit A will constantly run at full power, providing baseload power, unit B will operate at variable power, and unit C will need to be turned on and off, providing the "intermediate" or "cycling" capacity. If the demand goes above 200 MW only occasionally, the unit C will be idle most of the time and will be considered a
peaking power plant Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the power ...
(a "peaker"). Since a peaker might run for just tens of hours per year, the cost of peaker-produced electricity can be very high in order to recover the capital investment and fixed costs (see the right side of a hypothetical full-scale dispatch curve).


Redispatch

Sometimes the grid constraints change unpredictably and a need arises to change the previously set unit commitments. This system redispatch change is controlled in real-time by the central operator issuing directives to market participants that submit in advance bids for the increase/decrease in the power levels. Due to the centralized nature of redispatch, there is no delay to negotiate terms of contracts; the cost incurred are allocated either to participants responsible for the disruption based on preestablished tariffs or in equal shares.


Minutes-ahead operation

In the minutes prior to the delivery, a system operator is using the power-flow study algorithms in order to find the
optimal power flow Electrical power system simulation involves power system modeling and network simulation in order to analyze electrical power systems using design/offline or real-time data. Power system simulation software's are a class of computer simulation pro ...
. At this stage the goal is reliability ("security") of the supply. The practical electric networks are too complex to perform the calculations by hand, so from the 1920s the calculations were automated, at first in the form of specially-built analog computers, so called '' network analyzers'', replaced by digital computers in the 1960s.


Control after disturbance

Small mismatches between the total demand and total load are typical and initially are taken care of by the kinetic energy of the rotating machinery (mostly
synchronous generator In an alternating current electric power system, synchronization is the process of matching the frequency of a generator or other source to a running network. An AC generator cannot deliver power to an electrical grid unless it is running at the sam ...
s): when there is too much supply, the devices absorb the excess, and frequency goes above the scheduled rate, conversely, too much demand causes the generator to deliver extra electricity through slowing down, with frequency slightly decreasing, not requiring an intervention form the operator. There are obvious limits to this "immediate control", so a ''control continuum'' is built into a typical power grid, spanning reaction intervals from seconds ("primary control") to hours ("time control").


Seconds-after control

The is engaged automatically within seconds after the frequency disturbance. Primary control stabilizes the situation, but does not return the conditions to the normal and is applied both to the generation side (where the governor adjusts the power of the prime mover) and to the load, where: * induction motors self-adjust (lower frequency reduces the energy use); * under-frequency relays disconnect
interruptible load Firm services, also called uninterruptible services, are services, such as electricity (firm power) and natural gas supplies, that are intended to be available at all times during a period covered by an agreement. Also, the service is not subject to ...
s; * ancillary services are engaged (load is reduced as procured via reliability services contracts). Another term commonly used for the primary control is frequency response (or "beta"). Frequency response also includes the
inertial response Inertial response is a property of large synchronous generators, which contain large synchronous rotating masses, and which acts to overcome any immediate imbalance between power supply and demand for electric power systems, typically the electrica ...
of the generators. This is the parameter that is approximated by the frequency bias coefficient of the area control error (ACE) calculation used for
automatic generation control In an electric power system, automatic generation control (AGC) is a system for adjusting the power output of multiple generators at different power plants, in response to changes in the load. Since a power grid requires that generation and load ...
.


Minutes-after control

The is used to restore the system frequency after a disturbance, with adjustments made by the balancing authority control computer (this is typically referred to as
load-frequency control The utility frequency, (power) line frequency (American English) or mains frequency (British English) is the nominal frequency of the oscillations of alternating current (AC) in a wide area synchronous grid transmitted from a power station to th ...
or
automatic generation control In an electric power system, automatic generation control (AGC) is a system for adjusting the power output of multiple generators at different power plants, in response to changes in the load. Since a power grid requires that generation and load ...
) and manual actions taken by the balancing authority staff. Secondary control uses both the
spinning Spin or spinning most often refers to: * Spinning (textiles), the creation of yarn or thread by twisting fibers together, traditionally by hand spinning * Spin, the rotation of an object around a central axis * Spin (propaganda), an intentionally b ...
and non-spinning reserves, with balancing services deployed within minutes after disturbance (hydropower plants are capable of an even faster reaction).


Tertiary control

The ''tertiary control'' involves reserve deployment and restoration to handle the current and future contingencies.


Time control

The goal of the time control is to maintain the long-term frequency at the specified value within a
wide area synchronous grid A wide area synchronous grid (also called an "interconnection" in North America) is a three-phase electric power grid that has regional scale or greater that operates at a synchronized utility frequency and is electrically tied together during no ...
. Due to the disturbances, the average frequency drifts, and a ''time error'' accumulates between the official time and the time measured in the AC cycles. In the US, the average 60 Hz frequency is maintained within each interconnection by a designated entity, time monitor, that periodically forces a grid frequency change to bring the overall time offset within the predefined limits. For example, in the Eastern Interconnection the action (temporarily setting the frequency to 60.02 Hz or 59.98 Hz) is initiated when the time offset reaches 10 seconds and ceases once the offset reaches 6 seconds. Time control is performed either by a computer (''Automatic Time Error Correction''), or by the monitor requesting balancing authorities to adjust their settings.


References


Sources

* * * * * * * * {{cite book , last1=NERC , title=Balancing and Frequency Control , date=May 11, 2021 , publisher= North American Electric Reliability Corporation , url=https://www.nerc.com/comm/OC/ReferenceDocumentsDL/Reference_Document_NERC_Balancing_and_Frequency_Control.pdf Electric power generation Power engineering Electric power infrastructure Power station technology