__NOTOC__ Santee Cooper, also known officially from the 1930s as the South Carolina Public Service Authority, is South Carolina's state-owned electric and water utility that came into being during the New Deal as both a
rural electrification Rural electrification is the process of bringing electrical power to rural and remote areas. Rural communities are suffering from colossal market failures as the national grids fall short of their demand for electricity. As of 2017, over 1 billion ...
and
public works Public works are a broad category of infrastructure projects, financed and constructed by the government, for recreational, employment, and health and safety uses in the greater community. They include public buildings ( municipal buildings, sc ...
project that created two lakes and cleared large tracts of land while building hydro-electric dams and power plants. Its headquarters are located in
Moncks Corner, South Carolina Moncks Corner is a town in and the county seat of Berkeley County, South Carolina, United States. The population was 7,885 at the 2010 census. As defined by the U.S. Census Bureau, Moncks Corner is included within the Charleston-North Charleston-S ...
. As one of the largest power providers in South Carolina, Santee Cooper directly serves more than 165,000 residential and commercial customers in Berkeley, Georgetown, and Horry counties. With a fuel and energy supply that includes coal, nuclear, oil, natural gas, hydroelectric, and other renewable sources, Santee Cooper supplies power to the cities of Bamberg and Georgetown, 30 large industrial customers, and
Charleston Air Force Base Charleston Air Force Base is a United States military facility located in the City of North Charleston, South Carolina. The facility is under the jurisdiction of the United States Air Force's 628th Air Base Wing (628 ABW), a subordinate elemen ...
. Santee Cooper generates the power distributed by some of
South Carolina )'' Animis opibusque parati'' ( for, , Latin, Prepared in mind and resources, links=no) , anthem = " Carolina";" South Carolina On My Mind" , Former = Province of South Carolina , seat = Columbia , LargestCity = Charleston , LargestMetro = ...
's electric cooperatives. Following the
Nukegate scandal The Nukegate scandal is a political and legal scandal that arose from the abandonment of the Virgil C. Summer nuclear expansion project in South Carolina by South Carolina Electric & Gas (SCE&G) and the South Carolina Public Service Authority (k ...
, the South Carolina General Assembly debated whether to privatize or reform Santee Cooper, ultimately passing a reform bill that overhauled the regulation and oversight of the state-owned utility.


Management

A board of directors appointed by the governor and approved by the state Senate governs Santee Cooper. A board member represents each congressional district and each of the three counties where Santee Cooper serves retail customers directly; two board member have previous electric cooperative experience; and the chairman is appointed at-large. In September 2017, Then-CEO Lonnie Carter announced his retirement following the decision to abandon construction of two new
AP1000 The AP1000 is a nuclear power plant designed and sold by Westinghouse Electric Company. The plant is a pressurized water reactor with improved use of passive nuclear safety and many design features intended to lower its capital cost and impr ...
nuclear reactors at the Virgil C. Summer Nuclear Generating Station, leaving Santee Cooper with debts of about $4.4 billion for the partial construction. For his leadership and vision, Carter is projected to receive over $800,000 a year in retirement. Following the failure, the predominant issue facing the South Carolina General Assembly from 2018 until the
COVID-19 pandemic The COVID-19 pandemic, also known as the coronavirus pandemic, is an ongoing global pandemic of coronavirus disease 2019 (COVID-19) caused by severe acute respiratory syndrome coronavirus 2 (SARS-CoV-2). The novel virus was first identi ...
in 2020 was whether to sell Santee Cooper or to reform the utility's management. The sale of the utility is favored by Governor McMaster. He called Santee Cooper a "rogue agency" due to its independence and financial problems.
NextEra Energy NextEra Energy, Inc. is an American energy company with about 58 GW of generating capacity (24 GW of which were from fossil fuel sources), revenues of over $18 billion in 2020, and about 14,900 employees throughout the US and Canada. It is the ...
, a Florida-based electric utility, bid to purchase Santee Cooper but withdrew in April 2021. In June 2021, the South Carolina General Assembly passed Act 90, overhauling the regulation of the utility but maintaining its state-owned status. The bill passed unanimously, making it veto-proof.


Post V.C. Summer Reform

Act 90 of 2021, effective after January 1, 2022, brings Santee Cooper under the purview of the
South Carolina Public Service Commission The South Carolina Public Service Commission (PSC) is a regulatory agency that regulates public utilities in the state of South Carolina, including electric power, telecommunications, natural gas, and water & wastewater. In addition, the PSC ...
, the regulatory agency that oversees
public utilities A public utility company (usually just utility) is an organization that maintains the infrastructure for a public service (often also providing a service using that infrastructure). Public utilities are subject to forms of public control and ...
in the state. This oversight includes integrated resource planning, service territory changes, facility siting and acquisition, purchase power agreements, and competitive procurement of renewable resources. Rates will continue to be set by the Santee Cooper Board of Directors but are subject to increased scrutiny. The reform will oust all but one of the ten members of the Board of Directors by 2025. It reduces the elected term of a Board Member to four years and places a three-term limit, as well as restrictions on severance packages for exiting members. The board selection process remains the same.


Santee Cooper Lakes

The Santee Cooper Power and Navigation Project, constructed in 1939, improved navigation on and provided
hydroelectric power Hydroelectricity, or hydroelectric power, is electricity generated from hydropower (water power). Hydropower supplies one sixth of the world's electricity, almost 4500 TWh in 2020, which is more than all other renewable sources combined an ...
from the Santee and Cooper rivers in
South Carolina )'' Animis opibusque parati'' ( for, , Latin, Prepared in mind and resources, links=no) , anthem = " Carolina";" South Carolina On My Mind" , Former = Province of South Carolina , seat = Columbia , LargestCity = Charleston , LargestMetro = ...
. With the creation of Lake Marion and
Lake Moultrie Lake Moultrie is the third largest lake in South Carolina. Created in the 1940s by a state utility project to dam the Cooper River, it covers more than . It provides a wide variety of recreational opportunities, including fishing. Location Lak ...
, the project was intended to improve the health, recreation, and economy of the area. At the time, the Santee Cooper Project was the largest land-clearing project in U.S. history, with over 12,500 workers clearing over of swamp and forestland. of dams and dikes were constructed, including a , tall earthen dike. The Pinopolis Dam included the hydroelectric station and
navigation lock A lock is a device used for raising and lowering boats, ships and other watercraft between stretches of water of different levels on river and canal waterways. The distinguishing feature of a lock is a fixed chamber in which the water lev ...
, the highest single-lift lock in the world. A
spillway A spillway is a structure used to provide the controlled release of water downstream from a dam or levee, typically into the riverbed of the dammed river itself. In the United Kingdom, they may be known as overflow channels. Spillways ensure th ...
was built to control floodwaters, with 62 gates allowing overflow of excess water. In completing the largest earth-moving project in the nation's history, of earth were moved and 3.1 million cubic yards of concrete were poured. The $48.2 million project (55 percent federal loan, 45 percent federal grant) first generated electricity on February 17, 1942. As transmission lines were built, power flowed to customers in Berkeley, Georgetown and Horry counties, and ultimately to electric cooperatives serving customers in 46 counties.


Projects and power plants


Power plants

In addition to the plants listed above, Santee Cooper has 28 MW of
Landfill gas Landfill gas is a mix of different gases created by the action of microorganisms within a landfill as they decompose organic waste, including for example, food waste and paper waste. Landfill gas is approximately forty to sixty percent methane ...
generation and 74 MW of wood biomass generation. Santee Cooper has 800 MW of renewable energy generation online or under contract. Santee Cooper owns one-third of the V.C. Summer Nuclear Station operated by Dominion Energy South Carolina, which owns the remaining two-thirds.


Johns Island Transmission Project

Since 2017, Santee Cooper has partnered with Dominion Energy to construct the Johns Island-Queensboro 115kV Transmission project on Johns Island, South Carolina. The 5.1 mile-long transmission line will be the island's second line and has received the requisite approvals from the relevant state agencies as well as the
United States Army Corps of Engineers , colors = , anniversaries = 16 June (Organization Day) , battles = , battles_label = Wars , website = , commander1 = ...
. It will traverse 2.2 miles of preexisting
right of way Right of way is the legal right, established by grant from a landowner or long usage (i.e. by prescription), to pass along a specific route through property belonging to another. A similar ''right of access'' also exists on land held by a gov ...
. The utilities will need to acquire approximately 2.9 miles of new right of way. Parts of the line will run through a number of wetlands, including Simmons Creek and Murray Creek. Residents of surrounding neighborhoods have raised concerns about the line's environmental impacts. It is estimated that it would have cost approximately $30 million to bury the line.