Salamonde Dam ( pt, Barragem de Salamonde, links=no; ) is a
concrete Concrete is a composite material composed of fine and coarse aggregate bonded together with a fluid cement (cement paste) that hardens (cures) over time. Concrete is the second-most-used substance in the world after water, and is the most wid ...
arch dam An arch dam is a concrete dam that is curved upstream in plan. The arch dam is designed so that the force of the water against it, known as hydrostatic pressure, presses against the arch, causing the arch to straighten slightly and strengthe ...
on the
Cávado River The Cávado River ( pt, rio Cávado; ) is a river located in northern Portugal. It has its source in Serra do Larouco at an elevation of above sea level. It runs from Fonte da Pipa, near the triangulation station Larouco, to its mouth into t ...
, where the river forms the border line between the districts of
Braga Braga ( , ; cel-x-proto, Bracara) is a city and a municipality, capital of the northwestern Portuguese district of Braga and of the historical and cultural Minho Province. Braga Municipality has a resident population of 193,333 inhabitants (in ...
and
Vila Real Vila Real () is the capital and largest city of the Vila Real District, in the North region. It is also the seat of the Douro intermunicipal community and of the Trás-os-Montes e Alto Douro historical province. The Vila Real municipality cover ...
. It is located in the municipality
Vieira do Minho Vieira do Minho (, ) is a municipality in the district of Braga, in the north of Portugal. The population in 2011 was 12,997, in an area of 216.44 km². The present mayor is António Cardoso, elected by a coalition between PSD and the CDS– ...
, in Braga District, Portugal. The dam was completed in 1953. It is owned by ''Companhia Portuguesa de Produção de Electricidade'' (CPPE). The dam was designed by
Coyne et Bellier Coyne et Bellier is a global consulting and engineering firm based out of Gennevilliers, France. They specialize in infrastructure projects such as dams, nuclear and hydroelectric power plants, roads, tunnels and other below-surface facilities. The ...
.


Dam

Salamonde Dam is a 75 m tall (height above foundation) and 284 m long arch dam with a crest altitude of 281 m. The volume of the dam is 93,000 m³. The dam features a
spillway A spillway is a structure used to provide the controlled release of water downstream from a dam or levee, typically into the riverbed of the dammed river itself. In the United Kingdom, they may be known as overflow channels. Spillways ensure th ...
with 4 gates over the dam (maximum discharge 1,700 m³/s) and one bottom outlet (maximum discharge 130 m³/s).


Reservoir

At full reservoir level of 280 m (maximum flood level of 280.5 m) the reservoir of the dam has a surface area of 2.42 (2.36) km² and a total capacity of 65 mio. m³; its active capacity is 56.3 (55 or 57) mio. m³. With the 55 mio. m³ water 26.9 GWh can be produced.


Power plant


Salamonde I

The hydroelectric power plant went operational in 1953. It is operated by EDP. The plant has a
nameplate capacity Nameplate capacity, also known as the rated capacity, nominal capacity, installed capacity, or maximum effect, is the intended full-load sustained output of a facility such as a power station,
of 42 MW. Its average annual generation is 231.2 (175, 232 or 244) GWh. The power station contains 2 Francis turbine-generators with 21.8 MW (25 MVA) each in an underground powerhouse. The turbine rotation is 428 rpm. The minimum hydraulic head is 78 m, the maximum 125 m. Maximum flow per turbine is 22 m³/s. The turbines and generators were provided by
Voith The Voith Group is a German manufacturer of machines for the pulp and paper industry, technical equipment for hydropower plants and drive and braking systems. The family-owned company, which operates worldwide and has its headquarters in Heid ...
.


Salamonde 2

In 2011 Alstom has been awarded a contract by EDP to install a 207 MW Francis reversible pump turbine and a 244 MVA motor-generator in a new
pumped-storage Pumped-storage hydroelectricity (PSH), or pumped hydroelectric energy storage (PHES), is a type of hydroelectric energy storage used by electric power systems for load balancing. The method stores energy in the form of gravitational potential ...
power plant. The new power plant is expected to go operational in August 2015. Its average annual generation is estimated to be 386 GWh.


See also

* List of power stations in Portugal *
List of dams and reservoirs in Portugal This page is a list of dams and reservoirs in Portugal, arranged by NUTS Regions and Subregions: Norte Alto Tâmega * Alto Tâmega Dam * Daivões Dam * Gouvães Dam Cávado * Caniçada Dam, Parada do Bouro, Vieira do Minho * Salamonde Da ...


External links

* *


References

{{DEFAULTSORT:Salamonde Dam Dams in Portugal Hydroelectric power stations in Portugal Arch dams Dams completed in 1953 Energy infrastructure completed in 1953 1953 establishments in Portugal Buildings and structures in Braga District Underground power stations Vieira do Minho Cávado River