The Roghun Dam (russian: Рогунская ГЭС; tg, Нерӯгоҳи барқи обии Роғун) is an
embankment dam An embankment dam is a large artificial dam. It is typically created by the placement and compaction of a complex semi-plastic mound of various compositions of soil or rock. It has a semi-pervious waterproof natural covering for its surface and ...
under construction on the
Vakhsh River The Vakhsh (Russian and Tajik: Вахш - ''Vaxsh'', fa, وخش), also known as the Surkhob (Сурхоб, سرخاب), in north-central Tajikistan, and the Kyzyl-Suu ( ky, Кызыл-Суу), in Kyrgyzstan, is a Central Asian river, and one of ...
in southern
Tajikistan Tajikistan (, ; tg, Тоҷикистон, Tojikiston; russian: Таджикистан, Tadzhikistan), officially the Republic of Tajikistan ( tg, Ҷумҳурии Тоҷикистон, Jumhurii Tojikiston), is a landlocked country in Centr ...
. The
dam A dam is a barrier that stops or restricts the flow of surface water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, human consumption, industrial use, a ...
is situated 110 km from
Dushanbe Dushanbe ( tg, Душанбе, ; ; russian: Душанбе) is the capital and largest city of Tajikistan. , Dushanbe had a population of 863,400 and that population was largely Tajik. Until 1929, the city was known in Russian as Dyushambe (r ...
. It is one of the planned
hydroelectric Hydroelectricity, or hydroelectric power, is electricity generated from hydropower (water power). Hydropower supplies one sixth of the world's electricity, almost 4500 TWh in 2020, which is more than all other renewable sources combined and ...
power plants of Vakhsh Cascade. Construction of the dam began in the Soviet era, in 1976, but was abandoned in 1993 after the collapse of the Soviet Union. Over three decades only preliminary construction has been carried out on the dam. Due to its controversial state, construction was suspended in August 2012 pending
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Interna ...
reports. The project was restarted by the Tajik government in 2016. The power plant's first unit was commissioned in November 2018 and second in September 2019, both on lower hydraulic head. The dam has drawn complaints from neighboring
Uzbekistan Uzbekistan (, ; uz, Ozbekiston, italic=yes / , ; russian: Узбекистан), officially the Republic of Uzbekistan ( uz, Ozbekiston Respublikasi, italic=yes / ; russian: Республика Узбекистан), is a doubly landlocked cou ...
, which fears it will negatively impact its lucrative
cotton Cotton is a soft, fluffy staple fiber that grows in a boll, or protective case, around the seeds of the cotton plants of the genus ''Gossypium'' in the mallow family Malvaceae. The fiber is almost pure cellulose, and can contain minor perce ...
crop A crop is a plant that can be grown and harvested extensively for profit or subsistence. When the plants of the same kind are cultivated at one place on a large scale, it is called a crop. Most crops are cultivated in agriculture or hydroponic ...
s. The dispute over the project has contributed significantly to bitter relations between the two former Soviet republics.


History

The Roghun Dam was first proposed in 1959 and a technical scheme was developed by 1965. Construction began in 1976, however the project stalled after the collapse of the
Soviet Union The Soviet Union,. officially the Union of Soviet Socialist Republics. (USSR),. was a transcontinental country that spanned much of Eurasia from 1922 to 1991. A flagship communist state, it was nominally a federal union of fifteen national ...
. An agreement on finishing the construction was signed between Tajikistan and
Russia Russia (, , ), or the Russian Federation, is a List of transcontinental countries, transcontinental country spanning Eastern Europe and North Asia, Northern Asia. It is the List of countries and dependencies by area, largest country in the ...
in 1994. Since the agreement was not implemented, it was denounced by Tajikistan parliament. In October 2004, an agreement was signed with
RUSAL United Company RUSAL, international public joint-stock company (russian: МКПАО «ОК РУСАЛ», MKPAO «ОК RUSAL») is the world's second largest aluminium company by primary production output (as of 2016). It was the largest until ov ...
in which RUSAL agreed to complete the Rogun facility, to build a new aluminum plant and to rebuild the
Tursunzade Aluminum Smelter The Tajik Aluminium Company ( tg, Ширкати Алюминийи Тоҷик; russian: Таджикская алюминиевая компания), abbreviated as TALCO ( Tajik/Russian: ТАЛКО) headquartered in Tursunzoda, Tajikistan, runs ...
. In February 2007, a new partnership between Russia and Tajikistan to complete the dam was announced, but later was refused by Russia because of disagreement concerning the controlling stake in the project. In May 2008, Tajikistan announced that construction of the dam had resumed. By December 2010, one of the river diversion tunnels was renovated and the second expected to commence in June or July 2011. Construction of the dam was suspended in August 2012 pending the
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Interna ...
assessment. In 2010, Tajikistan launched an
IPO An initial public offering (IPO) or stock launch is a public offering in which shares of a company are sold to institutional investors and usually also to retail (individual) investors. An IPO is typically underwritten by one or more investment ...
to raise US$1.4billion to finish construction of the dam. By April 26 of that year the Tajik government had raised just US$184 million, enough for two years of construction. On July 1, 2016 the state commission in charge of the project had chosen the Italian company
Salini Impregilo Webuild SpA (formerly Salini Impregilo SpA) () is an Italian industrial group specialised in the construction and civil engineering business headquartered in Milan. The company was formally founded in 2014 as the result of the merger by incorporat ...
to carry out the construction for $3.9 billion. The project is broken down into four components, with the most expensive one involving the building of a 335-meter-high
rockfill dam A dam is a barrier that stops or restricts the flow of surface water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, human consumption, industrial use, ...
which will entail costs of around $1.95 billion. On October 29, 2016 Tajik president
Emomali Rahmon Emomali Rahmon (; born Emomali Sharipovich Rahmonov, tg, Эмомалӣ Шарӣпович Раҳмонов, script=Latn, italic=no, Emomalī Sharīpovich Rahmonov; ; born 5 October 1952) has been the 3rd President of Tajikistan since 16 Novem ...
officially launched the construction of the dam. At the ceremony, the river's flow was ceremonially diverted through the reconstructed diversion tunnels. The power plant's first unit was commissioned in November 2018 and second in September 2019. In mid-July 2022 concrete pouring commenced on the main dam core.


Technical description

Rogun was listed as the highest dam in the world — high — but this is a projected height. In reality the dam was only circa high until 1993 when it was destroyed in a flood. three projects are under consideration: the original, , and two alternatives, and , all having their advantages and drawbacks. The hydroelectric power plant is expected to have six turbines with combined capacity of 3600 MW. When complete, it is expected to produce 17.1 TWh of electrical work per year.


Impact assessment

In response to the request of the bordering countries and especially
Uzbekistan Uzbekistan (, ; uz, Ozbekiston, italic=yes / , ; russian: Узбекистан), officially the Republic of Uzbekistan ( uz, Ozbekiston Respublikasi, italic=yes / ; russian: Республика Узбекистан), is a doubly landlocked cou ...
, the
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Interna ...
has financed the Techno-Economic Assessment Study (TEAS) conducted by consortium of
Coyne et Bellier Coyne et Bellier is a global consulting and engineering firm based out of Gennevilliers, France. They specialize in infrastructure projects such as dams, nuclear and hydroelectric power plants, roads, tunnels and other below-surface facilities. The ...
, Electroconsult and IPA Energy + Water Economics, and Environmental and Social Impact Assessment (ESIA) conducted by
Pöyry Pöyry PLC ( fi, Pöyry Oyj), which merged in 2019 with Swedish company ÅF into AFRY, was an international consulting and engineering firm that served clients globally across the energy and industrial sectors and provided local engineering serv ...
. The reports, originally slated to be released in February 2012, were delayed until mid-2014. The ESIA was published on 16 June 2014 and the TEAS in July 2014. Overall, the ESIA stated that "Most impacts are rather small and easily mitigated, if mitigation is required at all." and that "There is no impact of the category "strong negative, mitigation not possible", which would have to be considered as a no-go for the project." All parties, including Central Asian states met in
Almaty Almaty (; kk, Алматы; ), formerly known as Alma-Ata ( kk, Алма-Ата), is the List of most populous cities in Kazakhstan, largest city in Kazakhstan, with a population of about 2 million. It was the capital of Kazakhstan from 1929 to ...
in July 2014 for the 5th Riparian Meeting to discuss findings within the TEAS and ESIA.


International tensions

The project has raised tensions with Uzbekistan over the impact of the dam on its cotton irrigation systems. In February 2010, Uzbek Prime Minister
Shavkat Mirziyoyev Shavkat Miromonovich Mirziyoyev (Uzbek Latin: ''Shavkat Miromonovich (Miromon o‘g‘li) Mirziyoyev'', Uzbek Cyrillic: Шавкат Миромонович (Миромон ўғли) Мирзиёев ; born 24 July 1957) is an Uzbek politician ...
sent a letter to his Tajik counterpart demanding an independent examination of the possible consequences of the dam. During October 2010, Uzbek President
Islam Karimov Islam Abduganiyevich Karimov ( uz, Islom Abdugʻaniyevich Karimov / Ислом Абдуғаниевич Каримов, italics=no; russian: link=no, Ислам Абдуганиевич Каримов; 30 January 1938 – 2 September 2016) was t ...
called the Rogun hydropower plants a "stupid project." However, in 2018 Uzbekistan dropped its opposition to the Rogun Dam. "Go ahead and build it, but we hold to certain guarantees in accordance with these conventions that have been signed by you," Uzbek Foreign Minister
Abdulaziz Komilov Abdulaziz Khafizovich Kamilov ( uz, Abdulaziz Xafizovich Kamilov; russian: Абдулазиз Хафизович Камилов, Abdulaziz Khafizovich Kamilov; born November 16, 1947) is an Uzbek politician who was Uzbekistan's Minister of Forei ...
said in a televised appearance on July 5, 2018.Uzbekistan and Tajikistan: No more dam problems?
/ref>