Project management is the process of leading the work of a
team A team is a group of individuals (human or non-human) working together to achieve their goal. As defined by Professor Leigh Thompson of the Kellogg School of Management, " team is a group of people who are interdependent with respect to inf ...
to achieve all project goals within the given constraints. This information is usually described in project documentation, created at the beginning of the development process. The primary constraints are scope, time, and budget. The secondary challenge is to optimize the allocation of necessary inputs and apply them to meet pre-defined objectives. The objective of project management is to produce a complete project which complies with the client's objectives. In many cases, the objective of project management is also to shape or reform the client's brief to feasibly address the client's objectives. Once the client's objectives are clearly established, they should influence all decisions made by other people involved in the project – for example, project managers, designers, contractors, and subcontractors. Ill-defined or too tightly prescribed project management objectives are detrimental to decision-making. A project is a temporary and unique endeavor designed to produce a product, service, or result with a defined beginning and end (usually time-constrained, and often constrained by funding or staffing) undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. The temporary nature of projects stands in contrast with business as usual (or operations), which are repetitive, permanent, or semi-permanent functional activities to produce products or services. In practice, the
management Management (or managing) is the administration of an organization, whether it is a business, a nonprofit organization, or a Government agency, government body. It is the art and science of managing resources of the business. Management includ ...
of such distinct production approaches requires the development of distinct technical skills and management strategies.


History

Until 1900,
civil engineering Civil engineering is a professional engineering discipline that deals with the design, construction, and maintenance of the physical and naturally built environment, including public works such as roads, bridges, canals, dams, airports, sewa ...
projects were generally managed by creative architects, engineers, and master builders themselves, for example,
Vitruvius Vitruvius (; c. 80–70 BC – after c. 15 BC) was a Roman architect and engineer during the 1st century BC, known for his multi-volume work entitled '' De architectura''. He originated the idea that all buildings should have three attribut ...
(first century BC), Christopher Wren (1632–1723),
Thomas Telford Thomas Telford FRS, FRSE, (9 August 1757 – 2 September 1834) was a Scottish civil engineer. After establishing himself as an engineer of road and canal projects in Shropshire, he designed numerous infrastructure projects in his native Scot ...
(1757–1834), and
Isambard Kingdom Brunel Isambard Kingdom Brunel (; 9 April 1806 – 15 September 1859) was a British civil engineer who is considered "one of the most ingenious and prolific figures in engineering history," "one of the 19th-century engineering giants," and "on ...
(1806–1859). In the 1950s, organizations started to systematically apply project-management tools and techniques to complex engineering projects. As a discipline, project management developed from several fields of application including civil construction, engineering, and heavy defense activity. Two forefathers of project management are
Henry Gantt Henry Laurence Gantt (; May 20, 1861 – November 23, 1919) was an American mechanical engineer and management consultant who is best known for his work in the development of scientific management. He created the Gantt chart in the 1910s. Gan ...
, called the father of planning and control techniques, who is famous for his use of the
Gantt chart A Gantt chart is a type of bar chart that illustrates a project schedule, named after its popularizer, Henry Gantt (1861–1919), who designed such a chart around the years 1910–1915. Modern Gantt charts also show the dependency relationshi ...
as a project management tool (alternatively ''Harmonogram'' first proposed by
Karol Adamiecki Karol Adamiecki ( Dąbrowa Górnicza, 18 March 1866 – 16 May 1933, Warsaw, Poland) was a Polish engineer, management researcher, economist, and professor. Life Karol Adamiecki was a prominent management researcher in Eastern and Central Eur ...
); and
Henri Fayol Henri Fayol (29 July 1841 – 19 November 1925) was a French mining engineer, mining executive, author and director of mines who developed a general theory of business administration that is often called Fayolism.Morgen Witzel (2003). ''Fifty key ...
for his creation of the five management functions that form the foundation of the body of knowledge associated with project and program management. Both Gantt and Fayol were students of
Frederick Winslow Taylor Frederick Winslow Taylor (March 20, 1856 – March 21, 1915) was an American mechanical engineer. He was widely known for his methods to improve industrial efficiency. He was one of the first management consultants. In 1909, Taylor summed up ...
's theories of scientific management. His work is the forerunner to modern project management tools including
work breakdown structure A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into ...
(WBS) and
resource allocation In economics, resource allocation is the assignment of available resources to various uses. In the context of an entire economy, resources can be allocated by various means, such as markets, or planning. In project management, resource allocati ...
. The 1950s marked the beginning of the modern project management era, where core
engineering Engineering is the use of scientific principles to design and build machines, structures, and other items, including bridges, tunnels, roads, vehicles, and buildings. The discipline of engineering encompasses a broad range of more speciali ...
fields came together to work as one. Project management became recognized as a distinct discipline arising from the management discipline with the engineering model. In the United States, prior to the 1950s, projects were managed on an ad-hoc basis, using mostly
Gantt chart A Gantt chart is a type of bar chart that illustrates a project schedule, named after its popularizer, Henry Gantt (1861–1919), who designed such a chart around the years 1910–1915. Modern Gantt charts also show the dependency relationshi ...
s and informal techniques and tools. At that time, two mathematical project-scheduling models were developed. The " critical path method" (CPM) was developed as a joint venture between DuPont Corporation and
Remington Rand Corporation Remington Rand was an early American business machine manufacturer, originally a typewriter manufacturer and in a later incarnation the manufacturer of the UNIVAC line of mainframe computers. Formed in 1927 following a merger, Remington Rand wa ...
for managing plant maintenance projects. The "
program evaluation and review technique The program evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. First developed by the United States Navy in ...
" (PERT), was developed by the U.S. Navy Special Projects Office in conjunction with the
Lockheed Corporation The Lockheed Corporation was an American aerospace manufacturer. Lockheed was founded in 1926 and later merged with Martin Marietta to form Lockheed Martin in 1995. Its founder, Allan Lockheed, had earlier founded the similarly named but ot ...
and
Booz Allen Hamilton Booz Allen Hamilton Holding Corporation (informally Booz Allen) is the parent of Booz Allen Hamilton Inc., an American management and information technology consulting firm, headquartered in McLean, Virginia, in Greater Washington, D.C., with 8 ...
as part of the
Polaris missile The UGM-27 Polaris missile was a two-stage solid-fueled nuclear-armed submarine-launched ballistic missile (SLBM). As the United States Navy's first SLBM, it served from 1961 to 1980. In the mid-1950s the Navy was involved in the Jupiter missi ...
submarine program.
PERT Pert or PERT may refer to: Ships * - see List of United States Navy ships: P * , a World War II corvette, originally HMS ''Nepeta'' * ''Pert'' (sidewheeler), a 19th-century steamboat that operated in British Columbia, Canada Statistics * PE ...
and CPM are very similar in their approach but still present some differences. CPM is used for projects that assume deterministic activity times; the times at which each activity will be carried out are known. PERT, on the other hand, allows for stochastic activity times; the times at which each activity will be carried out are uncertain or varied. Because of this core difference, CPM and
PERT Pert or PERT may refer to: Ships * - see List of United States Navy ships: P * , a World War II corvette, originally HMS ''Nepeta'' * ''Pert'' (sidewheeler), a 19th-century steamboat that operated in British Columbia, Canada Statistics * PE ...
are used in different contexts. These mathematical techniques quickly spread into many private enterprises. At the same time, as project-scheduling models were being developed, technology for project cost
estimating Estimation (or estimating) is the process of finding an estimate or approximation, which is a value that is usable for some purpose even if input data may be incomplete, uncertain, or unstable. The value is nonetheless usable because it is der ...
, cost management and engineering economics was evolving, with pioneering work by Hans Lang and others. In 1956, the American Association of Cost Engineers (now
AACE International AACE International (Association for the Advancement of Cost Engineering) was founded in 1956 by 59 cost estimators and cost engineers during the organizational meeting of the American Association of Cost Engineering at the University of New Hamps ...
; the Association for the Advancement of
Cost Engineering Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis". "Cost Engineers budget, plan and monitor inve ...
) was formed by early practitioners of project management and the associated specialties of planning and scheduling, cost estimating, and cost/ schedule control (project control). AACE continued its pioneering work and in 2006, released the first integrated process for portfolio, program, and project management ( total cost management framework). In 1969, the Project Management Institute (PMI) was formed in the USA. PMI publishes the original version of '' A Guide to the Project Management Body of Knowledge'' (PMBOK Guide) in 1996 with William Duncan as its primary author, which describes project management practices that are common to "most projects, most of the time."


Project management types

Project management methods can be applied to any project. It is often tailored to a specific type of project based on project size, nature, industry or sector. For example, the construction industry, which focuses on the delivery of things like buildings, roads, and bridges, has developed its own specialized form of project management that it refers to as ''construction project management'' and in which project managers can become trained and certified. The information technology industry has also evolved to develop its own form of project management that is referred to as ''IT project management'' and which specializes in the delivery of technical assets and services that are required to pass through various lifecycle phases such as planning, design, development, testing, and deployment. ''
Biotechnology Biotechnology is the integration of natural sciences and engineering sciences in order to achieve the application of organisms, cells, parts thereof and molecular analogues for products and services. The term ''biotechnology'' was first used ...
project management'' focuses on the intricacies of biotechnology research and development. ''Localization project management'' includes application of many standard project management practices to translation works even though many consider this type of management to be a very different discipline. There is public project management that covers all public works by the government, which can be carried out by the government agencies or contracted out to contractors. Another classification of project management is based on the hard (physical) or soft (non-physical) type. Common among all the project management types is that they focus on three important goals: time, quality, and cost. Successful projects are completed on schedule, within budget, and according to previously agreed quality standards i.e. meeting the Iron Triangle or Triple Constraint in order for projects to be considered a success or failure. For each type of project management, project managers develop and utilize repeatable templates that are specific to the industry they're dealing with. This allows project plans to become very thorough and highly repeatable, with the specific intent to increase quality, lower delivery costs, and lower time to deliver project results.


Approaches of project management

A 2017 study suggested that the success of any project depends on how well four key aspects are aligned with the contextual dynamics affecting the project, these are referred to as the ''four P's'': * Aim & Expectations: What are the aims & expectations of the project. *''Plan'': The planning and forecasting activities. * ''Process:'' The overall approach to all activities and project governance. * ''People:'' Including dynamics of how they collaborate and communicate. * ''Power:'' Lines of authority, decision-makers, organograms, policies for implementation and the like. There are a number of approaches to organizing and completing project activities, including phased, lean, iterative, and incremental. There are also several extensions to project planning, for example, based on outcomes (product-based) or activities (process-based). Regardless of the
methodology In its most common sense, methodology is the study of research methods. However, the term can also refer to the methods themselves or to the philosophical discussion of associated background assumptions. A method is a structured procedure for br ...
employed, careful consideration must be given to the overall project objectives, timeline, and cost, as well as the roles and responsibilities of all participants and stakeholders.


Benefits realization management

Benefits realization management (BRM) enhances normal project management techniques through a focus on outcomes (benefits) of a project rather than products or outputs and then measuring the degree to which that is happening to keep a project on track. This can help to reduce the risk of a completed project being a failure by delivering agreed upon requirements (outputs) i.e. project success but failing to deliver the ''benefits'' (outcomes) of those requirements i.e. product success. Note that good requirements management will ensure these benefits are captured as requirements of the project and their achievement monitored throughout the project. In addition, BRM practices aim to ensure the strategic alignment between project outcomes and business strategies. The effectiveness of these practices is supported by recent research evidencing BRM practices influencing project success from a strategic perspective across different countries and industries. These wider effects are called the strategic impact. An example of delivering a project to requirements might be agreeing to deliver a computer system that will process staff data and manage payroll, holiday, and staff personnel records in shorter times with reduced errors. Under BRM, the agreement might be to achieve a specified reduction in staff hours and errors required to process and maintain staff data after the system installation when compared without the system.


Critical path method

Critical path method (CPM) is an algorithm for determining the schedule for project activities. It is the traditional process used for predictive-based project planning. The CPM method evaluates the sequence of activities, the work effort required, the inter-dependencies, and the resulting float time per line sequence to determine the required project duration. Thus, by definition, the critical path is the pathway of tasks on the network diagram that has no extra time available (or very little extra time)."


Critical chain project management

Critical chain project management (CCPM) is an application of the theory of constraints (TOC) to planning and managing projects and is designed to deal with the uncertainties inherent in managing projects, while taking into consideration the limited availability of
resources Resource refers to all the materials available in our environment which are technologically accessible, economically feasible and culturally sustainable and help us to satisfy our needs and wants. Resources can broadly be classified upon their av ...
(physical, human skills, as well as management & support capacity) needed to execute projects. The goal is to increase the flow of projects in an organization (
throughput Network throughput (or just throughput, when in context) refers to the rate of message delivery over a communication channel, such as Ethernet or packet radio, in a communication network. The data that these messages contain may be delivered ove ...
). Applying the first three of the five focusing steps of TOC, the system constraint for all projects, as well as the resources, are identified. To exploit the constraint, tasks on the critical chain are given priority over all other activities.


Earned value management

Earned value management (EVM) extends project management with techniques to improve project monitoring. It illustrates project progress towards completion in terms of work and value (cost). Earned Schedule is an extension to the theory and practice of EVM.


Iterative and incremental project management

In critical studies of project management, it has been noted that phased approaches are not well suited for projects which are large-scale and multi-company, with undefined, ambiguous, or fast-changing requirements, or those with high degrees of risk, dependency, and fast-changing technologies. The cone of uncertainty explains some of this as the planning made on the initial phase of the project suffers from a high degree of uncertainty. This becomes especially true as software development is often the realization of a new or novel product. These complexities are better handled with a more exploratory or iterative and incremental approach. Several models of iterative and incremental project management have evolved, including agile project management,
dynamic systems development method Dynamic systems development method (DSDM) is an agile project delivery framework, initially used as a software development method. First released in 1994, DSDM originally sought to provide some discipline to the rapid application development (R ...
,
extreme project management Extreme project management (XPM) refers to a Method (software engineering), method of management, managing very complex and very uncertain projects. Extreme project management differs from traditional project management mainly in its open, elasti ...
, and Innovation Engineering®.


Lean project management

Lean project management uses the principles from lean manufacturing to focus on delivering value with less waste and reduced time.


Project lifecycle

There are five phases to a project lifecycle; known as process groups. Each process group represents a series of inter-related processes to manage the work through a series of distinct steps to be completed. This type of project approach is often referred to as "traditional" or "
waterfall A waterfall is a point in a river or stream where water flows over a vertical drop or a series of steep drops. Waterfalls also occur where meltwater drops over the edge of a tabular iceberg or ice shelf. Waterfalls can be formed in severa ...
". The five process groups are: # Initiating # Planning # Executing # Monitoring and Controlling # Closing Some industries may use variations of these project stages and rename them to better suit the organization. For example, when working on a
brick-and-mortar Brick and mortar (also bricks and mortar or B&M) refers to a physical presence of an organization or business in a building or other structure. The term ''brick-and-mortar business'' is often used to refer to a company that possesses or leases r ...
design and construction, projects will typically progress through stages like pre-planning, conceptual design, schematic design, design development, construction drawings (or contract documents), and construction administration. While the phased approach works well for small, well-defined projects, it often results in challenge or failure on larger projects, or those that are more complex or have more ambiguities, issues, and risks - see the parodying '
six phases of a big project The six phases of a big project is a cynical take on the outcome of large projects, with an unspoken assumption about their seemingly inherent tendency towards chaos. It can be seen as a parody of the traditional process groups in a project lifecyc ...
'.


Process-based management

The incorporation of process-based management has been driven by the use of maturity models such as the
OPM3 The Project Management Institute (PMI, legally Project Management Institute, Inc.) is a U.S.-based not-for-profit professional organization for project management. Overview PMI serves more than five million professionals including over 680,00 ...
and the
CMMI Capability Maturity Model Integration (CMMI) is a process level improvement training and appraisal program. Administered by the CMMI Institute, a subsidiary of ISACA, it was developed at Carnegie Mellon University (CMU). It is required by many ...
(capability maturity model integration; see :Image:Capability Maturity Model.jpg


Project production management

Project production management is the application of operations management to the delivery of capital projects. The Project production management framework is based on a project as a production system view, in which a project transforms inputs (raw materials, information, labor, plant & machinery) into outputs (goods and services).


Product-based planning

Product-based planning is a structured approach to project management, based on identifying all of the products (project
deliverable A deliverable is a tangible or intangible good or service produced as a result of a project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a software product, a server upgr ...
s) that contribute to achieving the project objectives. As such, it defines a successful project as output-oriented rather than activity- or task-oriented.Office for Government Commerce (1996) ''Managing Successful Projects with PRINCE2'', p14 The most common implementation of this approach is
PRINCE2 PRINCE2 (PRojects IN Controlled Environments) is a structured project management method and practitioner certification programme. PRINCE2 emphasises dividing projects into manageable and controllable stages. It is adopted in many countries wor ...
.


Process groups

Traditionally (depending on what project management methodology is being used), project management includes a number of elements: four to five project management process groups, and a control system. Regardless of the methodology or terminology used, the same basic project management processes or stages of development will be used. Major process groups generally include: PMI (2010). ''A Guide to the Project Management Body of Knowledge'' p.27-35 * Initiation * Planning * Production or execution * Monitoring and controlling * Closing In project environments with a significant exploratory element (e.g., research and development), these stages may be supplemented with decision points (go/no go decisions) at which the project's continuation is debated and decided. An example is the Phase–gate model.


Initiating

The initiating processes determine the nature and scope of the project. If this stage is not performed well, it is unlikely that the project will be successful in meeting the business’ needs. The key project controls needed here are an understanding of the business environment and making sure that all necessary controls are incorporated into the project. Any deficiencies should be reported and a recommendation should be made to fix them. The initiating stage should include a plan that encompasses the following areas. These areas can be recorded in a series of documents called Project Initiation documents. Project Initiation documents are a series of planned documents used to create an order for the duration of the project. These tend to include: * project proposal (idea behind project, overall goal, duration) * project scope (project direction and track) *
product breakdown structure {{more citations needed, date=January 2021 In project management under the PRINCE2 methodology, a product breakdown structure (PBS) is a tool for analysing, documenting and communicating the outcomes of a project, and forms part of the product b ...
(PBS) (a hierarchy of deliverables/outcomes and components thereof) *
work breakdown structure A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into ...
(WBS) (a hierarchy of the work to be done, down to daily tasks) *
responsibility assignment matrix A responsibility assignment matrix (RAM), also known as RACI matrix () or linear responsibility chart (LRC), describes the participation by various roles in completing tasks or deliverables for a project or business process. RACI is an acronym de ...
(RACI - Responsible, Accountable, Consulted, Informed) (roles and responsibilities aligned to deliverables / outcomes) * tentative project schedule (milestones, important dates, deadlines) * analysis of business needs and
requirement In product development and process optimization, a requirement is a singular documented physical or functional need that a particular design, product or process aims to satisfy. It is commonly used in a formal sense in engineering design, includ ...
s against measurable goals * review of the current operations * financial analysis of the costs and benefits, including a budget *
stakeholder analysis Stakeholder analysis (in conflict resolution, business administration, environmental health sciences decision making, Industrial ecology, and project management) is the process of assessing a system and potential changes to it as they relate to re ...
, including users and support personnel for the project *
project charter In project management, a project charter, project definition, or project statement is a statement of the scope, objectives, and participants in a project. It provides a preliminary delineation of roles and responsibilities, outlines the project's k ...
including costs, tasks, deliverables, and schedules *
SWOT analysis SWOT analysis (or SWOT matrix) is a strategic planning and strategic management technique used to help a person or organization identify Strengths, Weaknesses, Opportunities, and Threats related to business competition or project planning. It ...
: strengths, weaknesses, opportunities, and threats to the business


Planning

After the initiation stage, the project is planned to an appropriate level of detail (see an example of a flowchart). The main purpose is to plan time, cost, and resources adequately to estimate the work needed and to effectively manage risk during project execution. As with the Initiation process group, a failure to adequately plan greatly reduces the project's chances of successfully accomplishing its goals.
Project planning Project planning is part of project management, which relates to the use of schedules such as Gantt charts to plan and subsequently report progress within the project environment. Project planning can be done manually or by the use of project m ...
generally consists of * determining the project management methodology to follow (e.g. whether the plan will be defined wholly upfront, iteratively, or in rolling waves); * developing the
scope statement In project management, scope statements can take many forms depending on the type of project being implemented and the nature of the organization. The scope statement details the project deliverables and describes the major objectives. The objectiv ...
; * selecting the planning team; * identifying deliverables and creating the product and work breakdown structures; * identifying the activities needed to complete those deliverables and networking the activities in their logical sequence; * estimating the resource requirements for the activities; * estimating time and cost for activities; * developing the schedule; * developing the budget; * risk planning; * developing quality assurance measures; * gaining formal approval to begin work. Additional processes, such as planning for communications and for scope management, identifying roles and responsibilities, determining what to purchase for the project, and holding a kick-off meeting are also generally advisable. For
new product development In business and engineering, new product development (NPD) covers the complete process of bringing a new product to market, renewing an existing product or introducing a product in a new market. A central aspect of NPD is product design, along ...
projects, conceptual design of the operation of the final product may be performed concurrent with the project planning activities and may help to inform the planning team when identifying deliverables and planning activities.


Executing

While executing we must know what are the planned terms that need to be executed. The execution/implementation phase ensures that the project management plan's deliverables are executed accordingly. This phase involves proper allocation, coordination, and management of human resources and any other resources such as materials and budgets. The output of this phase is the project deliverables.


Project documentation

Documenting everything within a project is key to being successful. To maintain budget, scope, effectiveness and pace a project must have physical documents pertaining to each specific task. With correct documentation, it is easy to see whether or not a project's requirement has been met. To go along with that, documentation provides information regarding what has already been completed for that project. Documentation throughout a project provides a paper trail for anyone who needs to go back and reference the work in the past. In most cases, documentation is the most successful way to monitor and control the specific phases of a project. With the correct documentation, a project's success can be tracked and observed as the project goes on. If performed correctly documentation can be the backbone of a project's success


Monitoring and controlling

Monitoring and controlling consist of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken, when necessary, to control the execution of the project. The key benefit is that project performance is observed and measured regularly to identify variances from the project management plan. Monitoring and controlling include:James P. Lewis (2000). ''The project manager's desk reference: : a comprehensive guide to project planning, scheduling, evaluation, and systems.'' p.185 * Measuring the ongoing project activities ('where we are'); * Monitoring the project variables (cost, effort, scope, etc.) against the project management plan and the project performance baseline (''where we should be''); * Identifying corrective actions to address issues and risks properly (''How can we get on track again''); * Influencing the factors that could circumvent integrated change control so only approved changes are implemented. Two main mechanisms support monitoring and controlling in projects. On the one hand,
contract A contract is a legally enforceable agreement between two or more parties that creates, defines, and governs mutual rights and obligations between them. A contract typically involves the transfer of goods, services, money, or a promise to tr ...
s offer a set of rules and incentives often supported by potential penalties and sanctions. On the other hand, scholars in business and management have paid attention to the role of integrators (also called project barons) to achieve a project's objectives. In turn, recent research in project management has questioned the type of interplay between contracts and integrators. Some have argued that these two monitoring mechanisms operate as substitutes as one type of organization would decrease the advantages of using the other one. In multi-phase projects, the monitoring and control process also provides feedback between project phases, to implement corrective or preventive actions to bring the project into compliance with the project management plan. Project maintenance is an ongoing process, and it includes: * Continuing support of end-users * Correction of errors * Updates to the product over time In this stage,
auditor An auditor is a person or a firm appointed by a company to execute an audit.Practical Auditing, Kul Narsingh Shrestha, 2012, Nabin Prakashan, Nepal To act as an auditor, a person should be certified by the regulatory authority of accounting and a ...
s should pay attention to how effectively and quickly user problems are resolved. Over the course of any construction project, the work scope may change. Change is a normal and expected part of the construction process. Changes can be the result of necessary design modifications, differing site conditions, material availability, contractor-requested changes, value engineering, and impacts from third parties, to name a few. Beyond executing the change in the field, the change normally needs to be documented to show what was actually constructed. This is referred to as change management. Hence, the owner usually requires a final record to show all changes or, more specifically, any change that modifies the tangible portions of the finished work. The record is made on the contract documents – usually, but not necessarily limited to, the design drawings. The end product of this effort is what the industry terms as-built drawings, or more simply, "as built." The requirement for providing them is a norm in construction contracts. Construction document management is a highly important task undertaken with the aid of an online or desktop software system or maintained through physical documentation. The increasing legality pertaining to the construction industry's maintenance of correct documentation has caused an increase in the need for document management systems. When changes are introduced to the project, the viability of the project has to be re-assessed. It is important not to lose sight of the initial goals and targets of the projects. When the changes accumulate, the forecasted result may not justify the original proposed investment in the project. Successful project management identifies these components, and tracks and monitors progress, so as to stay within time and budget frames already outlined at the commencement of the project. Exact methods were suggested to identify the most informative monitoring points along the project life-cycle regarding its progress and expected duration.


Closing

Closing includes the formal acceptance of the project and the ending thereof. Administrative activities include the archiving of the files and documenting lessons learned. This phase consists of: * Contract closure: Complete and settle each contract (including the resolution of any open items) and close each contract applicable to the project or project phase. * Project close: Finalize all activities across all of the process groups to formally close the project or a project phase Also included in this phase is the Post Implementation Review. This is a vital phase of the project for the project team to learn from experiences and apply to future projects. Normally a Post Implementation Review consists of looking at things that went well and analyzing things that went badly on the project to come up with lessons learned.


Project control and project control systems

Project control (also known as
Cost Engineering Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis". "Cost Engineers budget, plan and monitor inve ...
) should be established as an independent function in project management. It implements verification and controlling functions during the processing of a project to reinforce the defined performance and formal goals. The tasks of project control are also: * the creation of infrastructure for the supply of the right information and its update * the establishment of a way to communicate disparities in project parameters * the development of project information technology based on an intranet or the determination of a project
key performance indicator A performance indicator or key performance indicator (KPI) is a type of performance measurement. KPIs evaluate the success of an organization or of a particular activity (such as projects, programs, products and other initiatives) in which it eng ...
system (KPI) * divergence analyses and generation of proposals for potential project regulations * the establishment of methods to accomplish an appropriate project structure, project workflow organization, project control, and governance * creation of transparency among the project parameters Fulfillment and implementation of these tasks can be achieved by applying specific methods and instruments of project control. The following methods of project control can be applied: * investment analysis * cost–benefit analysis * value benefit analysis * expert surveys * simulation calculations * risk-profile analysis * surcharge calculations *
milestone A milestone is a numbered marker placed on a route such as a road, railway line, canal or boundary. They can indicate the distance to towns, cities, and other places or landmarks; or they can give their position on the route relative to so ...
trend analysis * cost trend analysis * target/actual comparison Project control is that element of a project that keeps it on track, on time, and within budget. Project control begins early in the project with planning and ends late in the project with post-implementation review, having a thorough involvement of each step in the process. Projects may be audited or reviewed while the project is in progress. Formal audits are generally risk or compliance-based and management will direct the objectives of the audit. An examination may include a comparison of approved project management processes with how the project is actually being managed. Each project should be assessed for the appropriate level of control needed: too much control is too time-consuming, too little control is very risky. If project control is not implemented correctly, the cost to the business should be clarified in terms of errors and fixes. Control systems are needed for cost,
risk In simple terms, risk is the possibility of something bad happening. Risk involves uncertainty about the effects/implications of an activity with respect to something that humans value (such as health, well-being, wealth, property or the environm ...
, quality, communication, time, change, procurement, and human resources. In addition, auditors should consider how important the projects are to the
financial statement Financial statements (or financial reports) are formal records of the financial activities and position of a business, person, or other entity. Relevant financial information is presented in a structured manner and in a form which is easy to un ...
s, how reliant the stakeholders are on controls, and how many controls exist. Auditors should review the development process and procedures for how they are implemented. The process of development and the quality of the final product may also be assessed if needed or requested. A business may want the auditing firm to be involved throughout the process to catch problems earlier on so that they can be fixed more easily. An auditor can serve as a controls consultant as part of the development team or as an independent auditor as part of an audit. Businesses sometimes use formal systems development processes. This help assure systems are developed successfully. A formal process is more effective in creating strong controls, and auditors should review this process to confirm that it is well designed and is followed in practice. A good formal systems development plan outlines: * A strategy to align development with the organization's broader objectives * Standards for new systems * Project management policies for timing and budgeting * Procedures describing the process * Evaluation of quality of change


Characteristics of projects

There are five important characteristics of a project: (i) It should always have specific start and end dates. (ii) They are performed and completed by a group of people. (iii) The output is the delivery of a unique product or service. (iv) They are temporary in nature. (v) It is progressively elaborated. Examples are: designing a new car or writing a book.


Project complexity

Complexity and its nature play an important role in the area of project management. Despite having a number of debates on this subject matter, studies suggest a lack of definition and reasonable understanding of complexity in relation to the management of complex projects. Project complexity is the property of a project which makes it difficult to understand, foresee, and keep under control its overall behavior, even when given reasonably complete information about the project system. The identification of complex projects is specifically important to multi-project engineering environments. As it is considered that project complexity and project performance are closely related, it is important to define and measure the complexity of the project for project management to be effective. Complexity can be: * Structural complexity (also known as detail complexity, or complicatedness), i.e. consisting of many varied interrelated parts. It is typically expressed in terms of size, variety, and interdependence of project components, and described by technological and organizational factors. * Dynamic complexity refers to phenomena, characteristics, and manifestations such as ambiguity, uncertainty, propagation, emergence, and chaos. Based on the
Cynefin framework The Cynefin framework ( ) is a conceptual framework used to aid decision-making. Created in 1999 by Dave Snowden when he worked for IBM Global Services, it has been described as a "sense-making device". ''Cynefin'' is a Welsh word for ''habitat' ...
, complex projects can be classified as: * Simple (or clear, obvious, known) projects, systems, or contexts. These are characterized by known knowns, stability, and clear cause-and-effect relationships. They can be solved with standard operating procedures and best practices. * Complicated: characterized by known unknowns. A complicated system is the sum of its parts. In principle, it can be deconstructed into smaller simpler components. While difficult, complicated problems are theoretically solvable with additional resources, specialized expertise, analytical, reductionist, simplification, decomposition techniques, scenario planning, and following good practices. * Complex are characterized by unknown unknowns, and emergence. Patterns could be uncovered, but they are not obvious. A complex system can be described by
Euclid Euclid (; grc-gre, Εὐκλείδης; BC) was an ancient Greek mathematician active as a geometer and logician. Considered the "father of geometry", he is chiefly known for the '' Elements'' treatise, which established the foundations of ...
’s statement that the whole is more than the sum of its parts. * Really complex projects, a.k.a. very complex, or chaotic: characterized by unknowables. No patterns are discernible in really complex projects. Causes and effects are unclear even in retrospect. Paraphrasing
Aristotle Aristotle (; grc-gre, Ἀριστοτέλης ''Aristotélēs'', ; 384–322 BC) was a Greek philosopher and polymath during the Classical period in Ancient Greece. Taught by Plato, he was the founder of the Peripatetic school of ph ...
, a really complex system is different from the sum of its parts. By applying the discovery in measuring work complexity described in
Requisite Organization Requisite organization (RO) is a term and methodology developed by Elliott Jaques and Kathryn Cason as a result of the research in stratified systems theory, general theory of bureaucracy, work complexity and human capability over 60 years. Requ ...
and Stratified Systems Theory, Dr. Elliott Jaques classifies projects and project work (stages, tasks) into basic 7 levels of project complexity based on such criteria as time-span of discretion and complexity of a project's output: * Level 1 Project – improve the direct output of an activity (quantity, quality, time) within a business process with a targeted completion time up to 3 months. * Level 2 Project – develop and improve compliance to a
business process A business process, business method or business function is a collection of related, structured activities or tasks by people or equipment in which a specific sequence produces a service or product (serves a particular business goal) for a parti ...
with a targeted completion time of 3 months to 1 year. * Level 3 Project – develop, change, and improve a business process with a targeted completion time of 1 to 2 years. * Level 4 Project – develop, change, and improve a functional system with a targeted completion time of 2 to 5 years. * Level 5 Project – develop, change, and improve a group of functional systems/business functions with a targeted completion time of 5 to 10 years. * Level 6 Project – develop, change, and improve a whole single value chain of a company with targeted completion time from 10 to 20 years. * Level 7 Project – develop, change, and improve multiple value chains of a company with target completion time from 20 to 50 years. Benefits from measuring Project Complexity is to improve project people feasibility by * Match the level of a project's complexity with effective targeted completion time of a project * Match the level of a project's complexity with the respective capability level of the project manager * Match the level of a project task's complexity with the respective capability of the project members


Positive, appropriate (requisite), and negative complexity

Similarly with the Law of requisite variety and The law of requisite complexity, project complexity is sometimes required in order for the project to reach its objectives, and sometimes it has beneficial outcomes. Based on the effects of complexity, Stefan Morcov proposed its classification as Positive, Appropriate, or Negative. * Positive complexity is the complexity that adds value to the project, and whose contribution to project success outweighs the associated negative consequences. * Appropriate (or requisite) complexity is the complexity that is needed for the project to reach its objectives, or whose contribution to project success balances the negative effects, or the cost of mitigation outweighs negative manifestations. * Negative complexity is the complexity that hinders project success.


Project managers

A project manager is a professional in the field of project management. Project managers are in charge of the people in a project. People are the key to any successful project. Without the correct people in the right place and at the right time a project cannot be successful. Project managers can have the responsibility of the planning, execution, controlling, and closing of any project typically relating to the construction industry, engineering, architecture,
computing Computing is any goal-oriented activity requiring, benefiting from, or creating computing machinery. It includes the study and experimentation of algorithmic processes, and development of both hardware and software. Computing has scientific, ...
, and telecommunications. Many other fields of production engineering, design engineering, and heavy industrial have project managers. A project manager needs to understand the order of execution of a project to schedule the project correctly as well as the time necessary to accomplish each individual task within the project. A project manager is the person accountable for accomplishing the stated project objectives on behalf of the client. Project Managers tend to have multiple years’ experience in their field. A project manager is required to know the project in and out while supervising the workers along with the project. Typically in most construction, engineering, architecture, and industrial projects, a project manager has another manager working alongside of them who is typically responsible for the execution of task on a daily basis. This position in some cases is known as a superintendent. A superintendent and project manager work hand in hand in completing daily project task. Key project management responsibilities include creating clear and attainable project objectives, building the project requirements, and managing the triple constraint (now including more constraints and calling it competing constraints) for projects, which is cost, time, quality and scope for the first three but about three additional ones in current project management. A typical project is composed of a team of workers who work under the project manager to complete the assignment within the time and budget targets. A project manager normally reports directly to someone of higher stature on the completion and success of the project. A project manager is often a client representative and has to determine and implement the exact needs of the client, based on knowledge of the firm they are representing. The ability to adapt to the various internal procedures of the contracting party, and to form close links with the nominated representatives, is essential in ensuring that the key issues of cost, time, quality and above all, client satisfaction, can be realized. A complete project manager, a term first coined by Dr. Robert J. Graham in his simulation, has been expanded upon by Randall L. Englund and Alfonso Bucero. They describe a complete project manager as a person who embraces multiple disciplines, such as
leadership Leadership, both as a research area and as a practical skill, encompasses the ability of an individual, group or organization to "lead", influence or guide other individuals, teams, or entire organizations. The word "leadership" often gets vi ...
, influence, negotiations, politics, change and conflict management, and humor. These are all "soft" people skills that enable project leaders to be more effective and achieve optimized, consistent results.


Multilevel success framework and criteria - project success vs. project performance

There is a tendency to confuse the project success with project management success. They are two different things. "Project success" has 2 perspectives: * the perspective of the process, i.e. delivering efficient outputs; typically called project management performance or project efficiency. * the perspective of the result, i.e. delivering beneficial outcomes; typically called project performance (sometimes just project success). Project management success criteria are different from project success criteria. The project management is said to be successful if the given project is completed within the agreed upon time, met the agreed upon scope and within the agreed upon budget. Subsequent to the triple constraints, multiple constraints have been considered to ensure project success. However, the triple or multiple constraints indicate only the efficiency measures of the project, which are indeed the project management success criteria during the project lifecycle. The priori criteria leave out the more important after-completion results of the project which comprise four levels i.e. the output (product) success, outcome (benefits) success and impact (strategic) success during the product lifecycle. These posterior success criteria indicate the effectiveness measures of the project product, service or result, after the project completion and handover. This overarching multilevel success framework of projects, programs and portfolios has been developed by Paul Bannerman in 2008. In other words, a project is said to be successful, when it succeeds in achieving the expected business case which needs to be clearly identified and defined during the project inception and selection before starting the development phase. This multilevel success framework conforms to the theory of project as a transformation depicted as the input-process / activity-output-outcome-impact in order to generate whatever value intended. Emanuel Camilleri in 2011 classifies all the critical success and failure factors into groups and matches each of them with the multilevel success criteria in order to deliver business value. An example of a performance indicator used in relation to project management is the "backlog of commissioned projects" or "project backlog".


Risk management

The United States
Department of Defense Department of Defence or Department of Defense may refer to: Current departments of defence * Department of Defence (Australia) * Department of National Defence (Canada) * Department of Defence (Ireland) * Department of National Defense (Philipp ...
states that "Cost, Schedule, Performance, and Risk" are the four elements through which Department of Defense acquisition professionals make trade-offs and track program status. There are also
international standards international standard is a technical standard developed by one or more international standards organizations. International standards are available for consideration and use worldwide. The most prominent such organization is the International Org ...
. Risk management applies proactive identification (see tools) of future problems and understanding of their consequences allowing predictive decisions about projects. ERM system plays a role in overall risk management.


Work breakdown structure and other breakdown structures

The
work breakdown structure A work-breakdown structure (WBS) in project management and systems engineering is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into ...
(WBS) is a
tree structure A tree structure, tree diagram, or tree model is a way of representing the hierarchical nature of a structure in a graphical form. It is named a "tree structure" because the classic representation resembles a tree, although the chart is genera ...
that shows a subdivision of the activities required to achieve an objective – for example a portfolio, program, project, and contract. The WBS may be hardware-, product-, service-, or
process A process is a series or set of activities that interact to produce a result; it may occur once-only or be recurrent or periodic. Things called a process include: Business and management *Business process, activities that produce a specific se ...
-oriented (see an example in a NASA reporting structure (2001)).NASA NPR 9501.2D
May 23, 2001.
Beside WBS for project scope management, there are organizational breakdown structure (chart), cost breakdown structure and
risk breakdown structure A Risk Breakdown Structure (RBS) within risk management is a hierarchically organised depiction of the identified project risks arranged by category. An Introduction to the Risk Breakdown Structure When planning a project to meet targets for c ...
. A WBS can be developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, sub-tasks, and work packages), which include all steps necessary to achieve the objective. The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established. The work breakdown structure can be displayed in two forms, as a table with subdivision of tasks or as an organizational chart whose lowest nodes are referred to as "work packages". It is an essential element in assessing the quality of a plan, and an initial element used during the planning of the project. For example, a WBS is used when the project is scheduled, so that the use of work packages can be recorded and tracked. Similarly to Work Breakdown Structure WBS, other decomposition techniques and tools are: Organization Breakdown Structure OBS, Product Breakdown Structure PBS, Cost Breakdown Structure CBS, Risk Breakdown Structure RBS, Resource Breakdown Structure ResBS.


International standards

There are several project management standards, including: * The ISO standards
ISO 9000 The ISO 9000 family is a set of five quality management systems (QMS) standards that help organizations ensure they meet customer and other stakeholder needs within statutory and regulatory requirements related to a product or service. ISO 90 ...
, a family of standards for quality management systems, and the
ISO 10006 ISO 10006:2018, Quality management systems - Guidelines for quality management in projects, is an international standard developed by the International Organization for Standardization. ISO 10006:2018 gives guidance on the application of quality ...
:2003, for Quality management systems and guidelines for quality management in projects. * ISO 21500:2012 – ''Guidance on project management''. This is the first International Standard related to project management published by ISO. Other standards in the 21500 family include 21503:2017 ''Guidance on programme management''; 21504:2015 ''Guidance on portfolio management''; 21505:2017 ''Guidance on governance''; 21506:2018 ''Vocabulary''; 21508:2018 ''Earned value management in project and programme management''; and 21511:2018 ''Work breakdown structures for project and programme management.'' *
ISO 31000 ISO 31000 is a family of standards relating to risk management codified by the International Organization for Standardization. ISO 31000:2018 provides principles and generic guidelines on managing risks that could be negative faced by organizatio ...
:2009 – Risk management. *ISO/IEC/IEEE 16326:2009 – Systems and Software Engineering—Life Cycle Processes—Project Management *Individual Competence Baseline (ICB) from the International Project Management Association (IPMA). * Capability Maturity Model (CMM) from the
Software Engineering Institute The Software Engineering Institute (SEI) is an American research and development center headquartered in Pittsburgh, Pennsylvania. Its activities cover cybersecurity, software assurance, software engineering and acquisition, and component capabi ...
. * GAPPS, Global Alliance for Project Performance Standards – an open source standard describing COMPETENCIES for project and program managers. * HERMES method, Swiss general project management method, selected for use in Luxembourg and international organizations. *The
logical framework approach The Logical Framework Approach (LFA) is a methodology mainly used for designing, monitoring, and evaluating international development projects. Variations of this tool are known as Goal Oriented Project Planning (GOPP) or Objectives Oriented Proje ...
(LFA), which is popular in international development organizations. *
PMBOK Guide The Project Management Body of Knowledge (PMBOK) is a set of standard terminology and guidelines (a body of knowledge) for project management. The body of knowledge evolves over time and is presented in ''A Guide to the Project Management Body of ...
from the Project Management Institute (PMI). *
PRINCE2 PRINCE2 (PRojects IN Controlled Environments) is a structured project management method and practitioner certification programme. PRINCE2 emphasises dividing projects into manageable and controllable stages. It is adopted in many countries wor ...
from AXELOS. * PM²: The Project Management methodology developed by the uropean Commission * Procedures for Project Formulation and Management (PPFM) by the Indian Ministry of Defence *
Team Software Process In combination with the personal software process (PSP), the team software process (TSP) provides a defined operational process framework that is designed to help teams of managers and engineers organize projects and produce software for products ...
(TSP) from the
Software Engineering Institute The Software Engineering Institute (SEI) is an American research and development center headquartered in Pittsburgh, Pennsylvania. Its activities cover cybersecurity, software assurance, software engineering and acquisition, and component capabi ...
. * Total Cost Management Framework, AACE International's Methodology for Integrated Portfolio, Program and Project Management. *
V-Model The V-model is a graphical representation of a systems development lifecycle. It is used to produce rigorous development lifecycle models and project management models. The V-model falls into three broad categories, the German ''V-Modell'', a g ...
, an original systems development method.


Program management and project networks

Some projects, either identical or different, can be managed as program management. Programs are collections of projects that support a common objective and set of goals. While individual projects have clearly defined and specific scope and timeline, a program’s objectives and duration are defined with a lower level of granularity. Besides programs and portfolios, additional structures that combine their different characteristics are: project networks, mega-projects, or mega-programs. A project network is a temporary project formed of several different distinct evolving phases, crossing organizational lines. Mega-projects and mega-programs are defined as exceptional in terms of size, cost, public and political attention, and competencies required.


Project portfolio management

An increasing number of organizations are using what is referred to as
project portfolio management Project portfolio management (PPM) is the centralized management of the processes, methods, and technologies used by project managers and project management offices (PMOs) to analyze and collectively manage current or proposed projects based on num ...
(PPM) as a means of selecting the right projects and then using project management techniquesAlbert Hamilton (2004). ''Handbook of Project Management Procedures.'' TTL Publishing, Ltd. as the means for delivering the outcomes in the form of benefits to the performing public, private or not-for-profit organization. Portfolios are collections of similar projects. Portfolio management supports efficiencies of scale, increasing success rates, and reducing project risks, by applying similar standardized techniques to all projects in the portfolio, by a group of project management professionals sharing common tools and knowledge. Organizations often create Project Management Offices as an organizational structure to support project portfolio management in a structured way. Thus, PPM is usually performed by a dedicated team of managers organized within an Enterprise Project Management Office (PMO), usually based within the organization, and headed by a PMO director or Chief Project Officer. In cases where strategic initiatives of an organization form the bulk of the PPM, the head of the PPM is sometimes titled as the chief initiative officer.


Project management software

Project management software Project management software (PMS) has the capacity to help plan, organize, and manage resource tools and develop resource estimates. Depending on the sophistication of the software, it can manage estimation and planning, scheduling, cost control ...
is software used to help plan, organize, and manage resource pools, develop resource estimates and implement plans. Depending on the sophistication of the software, functionality may include
estimation Estimation (or estimating) is the process of finding an estimate or approximation, which is a value that is usable for some purpose even if input data may be incomplete, uncertain, or unstable. The value is nonetheless usable because it is de ...
and planning,
scheduling A schedule or a timetable, as a basic time-management tool, consists of a list of times at which possible tasks, events, or actions are intended to take place, or of a sequence of events in the chronological order in which such things are ...
,
cost control Cost accounting is defined as "a systematic set of procedures for recording and reporting measurements of the cost of manufacturing goods and performing services in the aggregate and in detail. It includes methods for recognizing, classifying, al ...
and budget management,
resource allocation In economics, resource allocation is the assignment of available resources to various uses. In the context of an entire economy, resources can be allocated by various means, such as markets, or planning. In project management, resource allocati ...
,
collaboration software Collaborative software or groupware is application software designed to help people working on a common task to attain their goals. One of the earliest definitions of groupware is "intentional group processes plus software to support them". As re ...
,
communication Communication (from la, communicare, meaning "to share" or "to be in relation with") is usually defined as the transmission of information. The term may also refer to the message communicated through such transmissions or the field of inqui ...
, decision-making,
workflow A workflow consists of an orchestrated and repeatable pattern of activity, enabled by the systematic organization of resources into processes that transform materials, provide services, or process information. It can be depicted as a sequence o ...
,
risk In simple terms, risk is the possibility of something bad happening. Risk involves uncertainty about the effects/implications of an activity with respect to something that humans value (such as health, well-being, wealth, property or the environm ...
, quality, documentation, and/or administration systems.


Virtual project management

Virtual program management (VPM) is management of a project done by a
virtual team A virtual team (also known as a geographically dispersed team, distributed team, or remote team) usually refers to a group of individuals who work together from different geographic locations and rely on communication technology such as email, ins ...
, though it rarely may refer to a project implementing a virtual environment It is noted that managing a virtual project is fundamentally different from managing traditional projects, combining concerns of remote work and global collaboration (culture, time zones, language).


See also

Related fields *
Agile construction Agile construction is an integrated system of principles and methods, and a philosophy of doing business adapted to jobsites and overall project delivery in the construction industry. It is born from agile manufacturing and project management, whi ...
*
Architectural engineering Architectural engineers apply and theoretical knowledge to the engineering design of buildings and building systems. The goal is to engineer high performance buildings that are sustainable, economically viable and ensure the safety health. Archi ...
* Construction management *
Cost engineering Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis". "Cost Engineers budget, plan and monitor inve ...
*
Facilitation (business) Facilitation in business, organizational development (OD) and consensus decision-making refers to the process of designing and running a meeting according to a previously agreed set of requirements. Facilitation concerns itself with all the tasks ...
*
Industrial engineering Industrial engineering is an engineering profession that is concerned with the optimization of complex processes, systems, or organizations by developing, improving and implementing integrated systems of people, money, knowledge, information a ...
* Project Production Management *
Project management software Project management software (PMS) has the capacity to help plan, organize, and manage resource tools and develop resource estimates. Depending on the sophistication of the software, it can manage estimation and planning, scheduling, cost control ...
*
Project portfolio management Project portfolio management (PPM) is the centralized management of the processes, methods, and technologies used by project managers and project management offices (PMOs) to analyze and collectively manage current or proposed projects based on num ...
*
Project workforce management Project workforce management is the practice of combining the coordination of all logistic elements of a project through a single software application (or workflow engine). This includes planning and tracking of schedules and mileposts, cost and rev ...
*
Software project management Software project management is an art and science of planning and leading software projects. It is a sub-discipline of project management in which software projects are planned, implemented, monitored and controlled. History In the 1970s and 1 ...
* Systems engineering Related subjects *
Agile management Agile management is the application of the principles of Agile software development and Lean Management to various management processes, particularly product development and project management. Following the appearance of the Manifesto for Agile ...
* Decision-making * Game theory *
Earned value management Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner. Overview Earned value manag ...
*
Human factors Human factors and ergonomics (commonly referred to as human factors) is the application of psychological and physiological principles to the engineering and design of products, processes, and systems. Four primary goals of human factors learnin ...
*
Kanban (development) Kanban ( Japanese: , meaning signboard or billboard) is a lean method to manage and improve work across human systems. This approach aims to manage work by balancing demands with available capacity, and by improving the handling of system-le ...
*
Operations research Operations research ( en-GB, operational research) (U.S. Air Force Specialty Code: Operations Analysis), often shortened to the initialism OR, is a discipline that deals with the development and application of analytical methods to improve decis ...
* Outline of project management *
Process architecture Process architecture is the structural design of general process systems. It applies to fields such as computers (software, hardware, networks, etc.), business processes ( enterprise architecture, policy and procedures, logistics, project managemen ...
*
Program management Program management, is the process of managing several related projects, often with the intention of improving an organization's performance. It is distinct from ''project'' management. In practice and in its aims, program management is oft ...
*
Project accounting Project accounting is a type of managerial accounting oriented toward the goals of project management and delivery. It involves tracking, reporting, and analyzing financial results and implications, and sometimes the creation of financial repor ...
* Project governance *
Project management office A project management office (abbreviated to PMO) is a group or department within a business, government agency, or enterprise that defines and maintains standards for project management within the organization. The PMO strives to standardize and in ...
*
Project management simulation Project management simulation is simulation used for project management training and analysis. Project management simulation is often used as training simulation for project managers. In other cases it is used for what-if analysis and for supporti ...
* Small-scale project management * Software development process * Social project management *
Systems development life cycle In systems engineering, information systems and software engineering, the systems development life cycle (SDLC), also referred to as the application development life cycle, is a process for planning, creating, testing, and deploying an informa ...
(SDLC) Lists *
Comparison of project management software The following is a comparison of project management software. General information Features Monetary features See also * Kanban (development) * Project management software * Project planning * Comparison of scrum software * Comparison ...
* Glossary of project management *
List of collaborative software This list is divided into proprietary or free software, and open source software, with several comparison tables of different product and vendor characteristics. It also includes a section of project collaboration software, which is a standard fea ...
*
List of project management topics The following outline is provided as an overview of and topical guide to project management: Project management – discipline of planning, organizing, securing, managing, leading, and controlling resources to achieve specific goals. A proj ...
* Timeline of project management


References


External links


Guidelines for Managing Projects
from the UK Department for Business, Enterprise and Regulatory Reform (BERR)

PM BLOG * {{DEFAULTSORT:Project Management Management by type IEEE standards ISO/IEC standards Product development