Overview
The time constraint refers to the amount of time available to complete a project. The cost constraint refers to the budgeted amount available for the project. The scope constraint refers to what must be done to produce the project's end result. These three constraints are often competing constraints: increased scope typically means increased time and increased cost, a tight time constraint could mean increased costs and reduced scope, and a tight budget could mean increased time and reduced scope. The discipline ofSTR Model
The ''STR model'' is a mathematical model which views the "triangle model" as a graphic abstraction of the relationship: Scope refers to complexity (which can also mean quality or performance). Resources includes humans (workers), financial, and physical. Note that these values are not considered unbounded. For instance, if one baker can make a loaf of bread in an hour in an oven, that does not mean that ten bakers could make ten loaves in one hour in the same oven, due to the oven's limited capacity.Project management triangle topics
Time
For analytical purposes, the time required to produce a deliverable isDefine Activities
#Inputs: Management Plan, Scope Baseline, Enterprise environmental factors, Organizational process assets #Tools: Decomposition, Rolling Wave Planning, Expert Judgment #Outputs: Activity list, Activity attributes,Activity sequencing
#Inputs: Project Scope Statement, Activity List, Activity Attributes, Milestones List, Approved change requests #Tools: Precedence Diagramming Method (PDM), Arrow Diagramming Method (ADM), Schedule Network templates, dependency degeneration, applying leads and lags #Outputs: Project Schedule Network diagrams, Activity List Updates, Activity Attributes updates, Request ChangesActivity resource estimating
#Inputs: Enterprise Environmental factoring, Organizational process assets, Activity list, Activity attributes, Resources Availability, Project Management Plan #Tools: Expert Judgment Collections, Alternative Analysis, Publishing estimating data, Project management software implementation, Bottom up estimating #Outputs: Activity resource requirements, Activity attributes, Resource breakdown structure, resource calendars, request change updates.Activity duration estimating
#Inputs: Enterprise environmental factors, organization process assets, Project scope statement, activity list, activity attributes, activity resource requirements, resource calendars, project management plan, risk register, activity cost estimates #Tools: Expert judgment collection, analogous estimating, parametric estimating, Bottom up Estimation, Two-Point estimation, Three-point estimation, reserve analysis #Outputs: Activity duration estimates, activity attribute updates and estimatesSchedule development
#Inputs: Organizational process assets, Project scope Statement, Activity list, Activity attributes, project Schedule Network diagrams, Activity resource requirements, Resource calendars, Activity duration estimates, project management plan, risk register #Tools: Schedule Network Analysis, Critical path method, schedule compression, what if scenario analysis, resources leveling, critical chain method, project management software, applying calendars, adjusting leads and lags, schedule model #Outputs: Project schedule, Schedule model data, schedule baseline, resource requirements update, activity attributes, project calendar updates, request changes, project management plan updates, schedule management plan updatesSchedule control
#Inputs: Schedule management plan, schedule baseline, performance reports, approved change requests #Tools: Progressive elaboration reporting, schedule change control system, performance measurement, project management software, variance, analysis, schedule comparison bar charts #Outputs: Schedule model data updates, schedule baseline. performance measurement, requested changes, recommended corrective actions, organizational process assets, activity list updates, activity attribute updates, project management plan updates Due to the complex nature of the 'Time' process group the project management credential ''PMI Scheduling Professional'' (PMI-SP) was created.Cost
To develop an approximation of a project cost depends on several variables including: resources, work packages such as labor rates and mitigating or controlling influencing factors that create cost variances. Tools used in cost are, risk management, cost contingency,Cost Process Areas
* Cost Estimating is an approximation of the cost of all resources needed to complete activities. * Cost budgeting aggregating the estimated costs of resources, work packages and activities to establish a cost baseline. * Cost Control – factors that create cost fluctuation and variance can be influenced and controlled using various cost management tools.= Project Management Cost Estimating Tools
= * Analogous Estimating: Using the cost of similar project to determine the cost of the current project * Determining Resource Cost rates: The cost of goods and labor by unit gathered through estimates or estimation. * Bottom Up estimating: Using the lowest level of work package detail and summarizing the cost associated with it. Then rolling it up to a higher level aimed and calculating the entire cost of the project. * Parametric Estimating: Measuring the statistical relationship between historical data and other variable or flow. * Vendor Bid Analysis: taking the average of several bids given by vendors for the project. * Reserve Analysis: Aggregate the cost of each activity on the network path then add a contingency or reserve to the end result of the analysis by a factor determined by the project manager. * Cost of Quality Analysis: Estimating the cost at the highest quality for each activity. Project management software can be used to calculate the cost variances for a project.Scope
Requirements specified to achieve the end result. The overall definition of what the project is supposed to accomplish, and a specific description of what the end result should be or accomplish. A major component of scope is the quality of the final product. The amount of time put into individual tasks determines the overall quality of the project. Some tasks may require a given amount of time to complete adequately, but given more time could be completed exceptionally. Over the course of a large project, quality can have a significant impact on time and cost (or vice versa). Together, these three constraints have given rise to the phrase "On Time, On Spec, On Budget." In this case, the term "scope" is substituted with "spec(ification)."Evolution of the Project Constraint Model
Traditionally the Project Constraint Model recognised three key constraints; "Cost", "Time" and "Scope". These constraints construct a triangle with geometric proportions illustrating the strong interdependent relationship between these factors. If there is a requirement to shift any one of these factors then at least one of the other factors must also be manipulated.() With mainstream acceptance of the Triangle Model, "Cost" and "Time" appear to be represented consistently. "Scope" however is often used interchangeably given the context of the triangle's illustration or the perception of the respective project. Scope / Goal / Product / Deliverable / Quality / Performance / Output are all relatively similar and generic variation examples of this, while the above suggestion of 'People Resources' offers a more specialised interpretation. This widespread use of variations implies a level of ambiguity carried by the nuance of the third constraint term and of course a level of value in the flexibility of the Triangle Model. This ambiguity allows blurred focus between a project's output and project's process, with the example terms above having potentially different impetus in the two contexts. Both "Cost" and "Time" / "Delivery" represent the top level project's inputs. The ‘Project Diamond’ model engenders this blurred focus through the inclusion of "Scope" and "Quality" separately as the ‘third’ constraint. While there is merit in the addition of "Quality" as a key constraining factor, acknowledging the increasing maturity of project management, this model still lacks clarity between output and process. The Diamond Model does not capture the analogy of the strong interrelation between points of the triangles however. PMBOK 4.0 offered an evolved model based on the triple constraint with 6 factors to be monitored and managed. This is illustrated as a 6 pointed Star that maintains the strength of the triangle analogy (two overlaid triangles), while at the same time represents the separation and relationship between project inputs/outputs factors on one triangle and the project processes factors on the other. The star variables are: #Input-Output Triangle #* Scope #* Cost #* Time #Process Triangle #* Risk #* Quality #* Resources When considering the ambiguity of the third constraint and the suggestions of the "Project Diamond"; it is possible to consider instead the Goal or Product of the project as the third constraint, being made up of the sub factors "Scope" and "Quality". In terms of a project's output both "Scope" and "Quality" can be adjusted resulting in an overall manipulation of the Goal/Product. This interpretation includes the four key factors in the original triangle inputs/outputs form. This can even be incorporated into the PMBOK Star illustrating that "Quality" in particular may be monitored separately in terms of project outputs and process. Further to this suggestion, the use of term "Goal" may best represent change initiative outputs, while Product may best represent more tangible outputs.Evolution of Project Success Criteria
The triple constraints represent a minimum number of project success criteria which are not adequate by themselves. Thus, a number of studies have been carried out to define and expand the various criteria of project success based on the theory of change which is the basic input-process-output chain. Bannerman (2008) proposed the multilevel project success framework which comprises five L Levels of project success i.e. team, project management, deliverable, business and strategic. The UNDP in 2012 proposed the results framework which has six stages of project success i.e. input, process, output, outcome and impact. Zidane et al (2016) expanded the results framework into the PESTOL framework to plan and assess project success which can be used to evaluate "value for money" spent on each project in terms of efficiency and effectiveness.Zidane (2016) https://www.researchgate.net/publication/308727415_PESTOL_-_Framework_for_Project_Evaluation_on_Strategic_Tactical_and_Operational_Levels Hence, the triple constraints has been developed into various frameworks to plan and appraise project success as holistically as possible.See also
* Quality, cost, delivery * Trilemma *References