The Karuma Hydroelectric Power Station is a 600 MW hydroelectric power project under construction in
Uganda }), is a landlocked country in East Africa East Africa, Eastern Africa, or East of Africa, is the eastern subregion of the African continent. In the United Nations Statistics Division scheme of geographic regions, 10-11-(16*) territor ...
. When completed, it will be the largest power-generating installation in the country.


Location

The power station is located on the
Victoria Nile The White Nile ( ar, النيل الأبيض ') is a river in Africa, one of the two main tributaries of the Nile, the other being the Blue Nile. The name comes from the clay sediment carried in the water that changes the water to a pale color. ...
, at the former location of the
Karuma Falls Karuma Falls is a town in Uganda. Location Karuma Falls is on the Kampala–Gulu Highway, immediately south of where the highway crosses the River Nile. Karuma Falls is approximately , by road, northeast of Masindi and approximately , by road, ...
. This location is approximately upstream of where the
Masindi Masindi is a town in the Western Region of Uganda. It is on the road between Kampala and the Murchison Falls National Park. It is the site of the headquarters of the Masindi District. Location Masindi is approximately northwest of Kampala, Ug ...
-
Gulu Gulu is a city in the Northern Region of Uganda. It is the commercial and administrative centre of Gulu District. The coordinates of the city of Gulu are 2°46'54.0"N 32°17'57.0"E. The distance from Gulu to Kampala, Uganda's capital and large ...
Highway crosses the Nile. By road, it is approximately northeast of
Masindi Masindi is a town in the Western Region of Uganda. It is on the road between Kampala and the Murchison Falls National Park. It is the site of the headquarters of the Masindi District. Location Masindi is approximately northwest of Kampala, Ug ...
and south of
Gulu Gulu is a city in the Northern Region of Uganda. It is the commercial and administrative centre of Gulu District. The coordinates of the city of Gulu are 2°46'54.0"N 32°17'57.0"E. The distance from Gulu to Kampala, Uganda's capital and large ...
. The geographical coordinates of Karuma Hydroelectric Power Station are:02°14'51.0"N, 32°16'05.0"E (Latitude:2.247500; Longitude:32.268056). The electrical-mechanical installations of the power station are located approximately underground, with of underground access roads, making Karuma, the 14th largest underground power station in the world.


History

As far back as 1995, the
government of Uganda Uganda is a presidential republic in which the President of Uganda is the head of state and the prime minister is the head of government business. There is a multi-party system. Executive power is exercised by the government. Legislative power is ...
planned to construct a hydropower station at the site of the Karuma Falls. Initially, Norpak, a Norwegian energy company, was awarded the contract to perform the feasibility study and the environmental impact assessment (EIA) for the dam. The
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Interna ...
promised to make a loan available to pay for the construction. The feasibility study report was made available in October 2006. Bids for construction of the project went out in November 2006. Initially, the plan was to build a 200-250 megawatt power station. In 2009, the plans were redrawn, calling for a much larger project of 750 megawatts. Sometime during 2009, Norpak pulled out of the negotiations with the Ugandan government, citing the Global Recession of 2008 to 2012. The Ugandan government then contracted with Energy Infratech Private Limited to perform a new feasibility study and a new EIA, given that a larger power station was now being planned. At that time, construction was expected to start in 2012 and last six years. In July 2011, media reports indicated that the maximum capacity of the project had been scaled back to 600 megawatts from 750 megawatts. Some international development partners wanted to scale back even further, to a maximum capacity of 400 to 450 megawatts.


Technical specifications

Karuma Power Station comprises a roller compacted concrete gravity dam, that measures high and long. There are six water intake towers, each measuring high and wide. The underground chamber housing the six vertical Francis turbines of 100MW each, measures long, wide, and high.


Construction costs

In January 2011, Energy Infratech Private Limited, the Indian company contracted to perform the feasibility study for the project, said the estimated total cost for the dam and power plant was approximately US $2.2 billion. That figure included the cost needed to build a transmission line from
Karuma Karuma is a settlement in the Western Region of Uganda. Location Karuma is in Kiryandongo District, Bunyoro sub-region. The town is approximately , by road, north of Karuma Falls. The town is also approximately , by road, west of Kamdini, on ...
to a location where the power will be integrated into the national power grid. The power generated will be transmitted via high voltage wires to three substations as follows: (a) a 400 kilovolt line to Kawanda UETCL Substation in
Wakiso District Wakiso District is a district in the Central Region of Uganda that partly encircles Kampala, Uganda's capital city. The town of Wakiso is the site of the district headquarters. Kira, the country's second largest city and suburb of Kampala, is in ...
(b) an 132 kilovolt line to
Lira Lira is the name of several currency units. It is the current currency of Turkey and also the local name of the currencies of Lebanon and of Syria. It is also the name of several former currencies, including those of Italy, Malta and Israe ...
and (c) a 400 kilovolt line to a substation in Olwiyo,
Nwoya District Nwoya District is a district in Northern Uganda. Like most districts in Uganda, it is named after its main municipal, administrative and commercial center, Nwoya, the location of the district headquarters. Location Nwoya District is bordered by ...
. The construction costs for the high voltage transmission lines are estimated at US$250 million. In June 2013, the Ugandan government awarded the construction contract to
Sinohydro Sinohydro ( Chinese: 中国水电; long form: 中国水利水电建设集团公司) is a Chinese state-owned hydropower engineering and construction company. In the 2012 Engineering News-Record Top 225 Global Contractors, a ranking by annual rev ...
, a Chinese construction company. Work began in the second half of 2013 and is expected to last five years. Construction costs will be jointly funded by the Ugandan and Chinese governments. In June 2014, the
Exim Bank of China The Export–Import Bank of China (Chexim - China Exim Bank) () is one of two institutional banks in China chartered to implement the state policies in industry, foreign trade, economy, and foreign aid to other developing countries, and prov ...
committed in writing to fund 85 percent of the construction costs, in the form of a concessionary loan repayable in five years. The Ugandan government will fund the remaining 15 percent of the cost. In March 2015, the Ugandan Parliament assented to two loans totalling US$1.435 billion, from the Export-Import (EXIM) Bank of China, for the construction of the power station. Of that amount, US$789.3 million will be loaned at 2 percent per annum, repayable over 20 years, while US$645.82 million will attract 4 percent interest, payable over 15 years, effective the day the dam is fully commissioned. Uganda has already invested US$253.26 million to start the construction. That brings the total funds committed to the project as, of March 2015, to US $1,688,380,000. As of June 2018, with approximately 76 percent of the work completed, the total construction budget was quoted at US$1.7 billion, with US$1.4 billion for construction of the power station, and US$300 million going towards the new transmission lines and new substations.


Construction work

The construction of the dam and power station officially started on 12 August 2013. In March 2015,
Sinohydro Sinohydro ( Chinese: 中国水电; long form: 中国水利水电建设集团公司) is a Chinese state-owned hydropower engineering and construction company. In the 2012 Engineering News-Record Top 225 Global Contractors, a ranking by annual rev ...
, the lead contractor on the project, contracted with
Alstom Alstom SA is a French multinational rolling stock manufacturer operating worldwide in rail transport markets, active in the fields of passenger transportation, signalling, and locomotives, with products including the AGV, TGV, Eurostar, Avelia ...
to provide equipment and technical services to the power station, in a deal worth US$65 million. The equipment includes six 100 megawatt
Francis turbines The Francis turbine is a type of water turbine. It is an inward-flow reaction turbine that combines radial and axial flow concepts. Francis turbines are the most common water turbine in use today, and can achieve over 95% efficiency. The proc ...
and related equipment. At the peak of construction, it is expected that a total of 2,500 casual and permanent workers will be hired. The power station is expected to be commissioned in 2018. As of March 2016, about 30 percent of the work had been completed. In October 2016, it was estimated that about 1,000 Chinese nationals and about 5,000 Ugandans were working at the power station. In February 2018, the Red Pepper Newspaper reported that work equivalent to 74 percent of the entire project had been completed and commissioning of the power station was expected in December 2018. As of June 2018, fifty-six months since the beginning of construction, an estimated 76 percent of the physical work had been completed. Of the 6,000 workers, 5,300 are Ugandan. The first 200 MW of power are expected online in December 2018, and the rest in 2019. Each unit of power is expected to cost the consumer US$0.049 for the first 10 years of the life of the power station, after which the price will drop down to US$0.020 per unit, for the next 15 years. Three new substations, one each at Karuma, Kawanda and Olwiyo, are part of the construction contract. The substation at Lira will also undergo an upgrade to accommodate power from Karuma. As of April 2019, the
Daily Monitor The ''Daily Monitor'' is a Ugandan independent daily newspaper. Its name is shared by the ''Saturday Monitor'' and ''Sunday Monitor'', which are also published by Monitor Publications Limited. ''Daily Monitor'' averaged a daily circulation of 24,2 ...
newspaper reported that the work on the power station was approximately 80 percent complete, while the three high voltage transmission lines were 80 to 85 percent complete. Commissioning of the completed power station is expected in December 2019. In September 2019, an estimated 95 percent of construction had been completed. This included 100 percent completion of the Karuma–Lira High Voltage Line, 100 percent of the
Karuma–Kawanda High Voltage Power Line The Karuma–Kawanda High Voltage Power Line is a high voltage electricity power line, under construction, connecting the high voltage substation at Karuma Hydroelectric Power Station, in the Western Region of Uganda, to another high voltage sub ...
and 98 percent of the Karuma–Olwiyo High Voltage Line. Commissioning of the power station is planned for December 2019.


Recent developments

In addition to the high voltage transmission lines to Lira, Olwiyo and Kawanda, that belong to
Uganda Electricity Transmission Company Limited The Uganda Electricity Transmission Company Limited (UETCL) is a parastatal company whose primary purpose is to make bulk electricity purchases and transmit the electricity along high voltage wires to local and foreign distribution points. UETCL ...
(UETCL),
Umeme Umeme Limited is the largest energy distributor in Uganda, distributing about 97 percent of all electricity used in the country. The shares of the stock of the company are listed on the Uganda Securities Exchange (USE) and are cross listed on ...
, the largest national distributor will spend USh4 billion (US$1.1 million) to construct a network of 33kV lines from Karuma to
Kigumba Kigumba is a town in Kiryandongo District, northwestern Uganda. It is one of the urban centers in the district. The other urban centres in Kiryandongo District include: (a) Karuma b) Kiryandongo (c) Bweyale and (d) Masindi Port. Location Kig ...
and on to the districts of
Lira Lira is the name of several currency units. It is the current currency of Turkey and also the local name of the currencies of Lebanon and of Syria. It is also the name of several former currencies, including those of Italy, Malta and Israe ...
, Gulu,
Masindi Masindi is a town in the Western Region of Uganda. It is on the road between Kampala and the Murchison Falls National Park. It is the site of the headquarters of the Masindi District. Location Masindi is approximately northwest of Kampala, Ug ...
and Hoima. Commissioning of the power station had been moved to November 2020. In May 2021, following touring of the work site, the chairperson of the board of
Uganda Electricity Generation Company Limited The Uganda Electricity Generation Company Limited (UEGCL) is a parastatal company whose primary purpose is to generate electric power for use in Uganda and for sale to neighboring countries. As of December 2017, UEGCL's generation capacity was 380 ...
(UEGCL), Engineer Proscovia Margaret Njuki, set the date of commissioning as 22 June 2022. In June 2021 it was reported that 98.8 percent of the work was complete with the contractor having already addressed some of the works that didn't conform with the plans and actively working on the rest. In July 2022, the
Daily Monitor The ''Daily Monitor'' is a Ugandan independent daily newspaper. Its name is shared by the ''Saturday Monitor'' and ''Sunday Monitor'', which are also published by Monitor Publications Limited. ''Daily Monitor'' averaged a daily circulation of 24,2 ...
reported that the power station would be brought online, one turbine at a time, with the first 100 MW unit starting in October 2022 and the sixth and final unit commissioned in June 2023.


Photos and diagrams


Photo of Karuma Falls at Gorillatales.com


Lira–Gulu–Agago High Voltage Power Line

The Lira–Gulu–Agago High Voltage Power Line is a planned high voltage power line in the Northern Region of
Uganda }), is a landlocked country in East Africa East Africa, Eastern Africa, or East of Africa, is the eastern subregion of the African continent. In the United Nations Statistics Division scheme of geographic regions, 10-11-(16*) territor ...
.


Location

The 132 kilovolt power line would start at the 132 kV
Uganda Electricity Transmission Company Limited The Uganda Electricity Transmission Company Limited (UETCL) is a parastatal company whose primary purpose is to make bulk electricity purchases and transmit the electricity along high voltage wires to local and foreign distribution points. UETCL ...
(UETCL) substation at
Lira Lira is the name of several currency units. It is the current currency of Turkey and also the local name of the currencies of Lebanon and of Syria. It is also the name of several former currencies, including those of Italy, Malta and Israe ...
. The line would travel in a general northeast direction to the city of
Gulu Gulu is a city in the Northern Region of Uganda. It is the commercial and administrative centre of Gulu District. The coordinates of the city of Gulu are 2°46'54.0"N 32°17'57.0"E. The distance from Gulu to Kampala, Uganda's capital and large ...
, approximately away, by road. From Gulu, the power line would travel in a general easterly direction for about , to end at Agago. The total distance traveled by the power line is estimated at approximately , since the line does not follow the road all the time.


Overview

This power line is intended to distribute electricity generated from power stations on the
Victoria Nile The White Nile ( ar, النيل الأبيض ') is a river in Africa, one of the two main tributaries of the Nile, the other being the Blue Nile. The name comes from the clay sediment carried in the water that changes the water to a pale color. ...
to the Northern Region of Uganda. It is also intended to evacuate power from the ''Achwa Hydroelectricity Power Station Complex'', including
Achwa 2 Hydroelectric Power Station Achwa 2 Hydroelectric Power Station is a hydroelectric power plant, in Uganda. Location The power station is located across the Achwa River, in Gulu District, Northern Uganda. This location is at the border between Gulu District and Pader Dist ...
, under construction as of January 2018, and
Achwa 3 Hydroelectric Power Station Achwa 3 Hydroelectric Power Station, also Achwa 3, is a proposed hydroelectric power project in Uganda. Location The power station is near the settlement of Aswa, off of the Acholibur–Gulu–Olwiyo Road, approximately , north-east of Gulu, ...
, under development. The main objective is to improve the quantity, quality and reliability of electricity supplied to the region.


Construction

As of June 2017, the website of the
Electricity Regulatory Authority The Electricity Regulatory Authority (ERA) is a government agency that regulates, licenses, and supervises the generation, transmission, distribution, sale, export, and importation of electrical energy in Uganda. Location The offices of the ERA ...
, stated that (a) preparation for implementation of the population resettlement plan were underway, (b) the updated feasibility study was in its final stages, (c) the pre-qualification of the contractors was ongoing and (d) the tender evaluation had been concluded. The scope of work involves the construction of a new 132kV electricity substation at Agago. In January 2016, the German government committed to lend €40 million, on soft terms, towards the construction of this power line.


See also


References


External links


Karuma Power Dam: Steering Committee Inspects Works With Progress At 94 Percent
As at 25 June 2019.
Environmental Impact Assessment By NEMA

Potential Hydropower Projects In Uganda
{{Kiryandongo District Hydroelectric power stations in Uganda Oyam District Kiryandongo District Underground power stations Dams under construction