HOME

TheInfoList



OR:

Estlink is a set of
HVDC A high-voltage direct current (HVDC) electric power transmission system (also called a power superhighway or an electrical superhighway) uses direct current (DC) for electric power transmission, in contrast with the more common alternating curren ...
submarine power cable A submarine power cable is a transmission cable for carrying electric power below the surface of the water.Estonia Estonia, formally the Republic of Estonia, is a country by the Baltic Sea in Northern Europe. It is bordered to the north by the Gulf of Finland across from Finland, to the west by the sea across from Sweden, to the south by Latvia, a ...
and
Finland Finland ( fi, Suomi ; sv, Finland ), officially the Republic of Finland (; ), is a Nordic country in Northern Europe. It shares land borders with Sweden to the northwest, Norway to the north, and Russia to the east, with the Gulf of B ...
. Estlink 1 is the first interconnection between the
Baltic Baltic may refer to: Peoples and languages * Baltic languages, a subfamily of Indo-European languages, including Lithuanian, Latvian and extinct Old Prussian *Balts (or Baltic peoples), ethnic groups speaking the Baltic languages and/or originati ...
and Nordic
electricity market In a broad sense, an electricity market is a system that facilitates the exchange of electricity-related goods and services. During more than a century of evolution of the electric power industry, the economics of the electricity markets had un ...
s followed by Estlink 2 in 2014. The main purpose of the Estlink connection is to secure power supply in both regions to integrate the Baltic and Nordic energy markets.


Estlink 1


History

First plans for a submarine power cable between the Baltic and the Nordic regions were proposed in 1990s. Negotiations between
Eesti Energia Eesti Energia AS is a public limited energy company in Estonia with its headquarters in Tallinn. It is the world's biggest oil shale to energy company. The company was founded in 1939. As of 2014, it operates in Estonia, Latvia, Lithuania, Fi ...
,
Pohjolan Voima Pohjolan Voima Oy (PVO; English: Northern Power Company Ltd.) is the second biggest Finnish energy company, which owns hydropower and thermal power plants (including biofuel-fired power plants). Shareholders Pohjolan Voima is a founder and main sh ...
,
Helsingin Energia Helen Oy, stylized as HELEN, formerly known as Helsingin Energia (Finnish) and ''Helsingfors Energi'' (Swedish), is one of the largest energy companies in Finland. The company, founded in 1909 produces and sells electricity, district heating and ...
, Graninge (now E.ON Sverige),
Latvenergo Latvenergo is a state-owned electric utility company in Latvia. Latvenergo Group provides energy supply services in the Baltics. The Group comprises the parent company Latvenergo AS, with decisive influence, and five subsidiaries. Latvenergo ...
, Statkraft and TXE Nordic Energy, a subsidiary of TXU (now
Energy Future Holdings Corporation Energy Future Holdings Corporation is an electric utility company headquartered in Energy Plaza in Downtown Dallas, Texas, United States. The majority of the company's power generation is through coal and nuclear power plants. From 1998 to 2007 ...
) started In 1999, and on 9 October 2001 a contract was signed in Tallinn. However, only after the harsh winter of 2002–2003 which resulted in an increased demand for power, the project of the submarine cable between Estonia and Finland got a boost. The letter of intention for underwater sea cable was signed between Eesti Energia, Pohjolan Voima, Helsingin Energia and Latvenergo on 31 March 2003. In May 2004, the Lithuanian power company
Lietuvos Energija Ignitis Group (Ignitis grupė AB; former name: Lietuvos Energija UAB) is a state-controlled energy holding company located in Vilnius, Lithuania. Its subsidiaries are involved in power and heat generation and distribution, natural gas trade and di ...
agreed to participate in the project, shortly after which the project company AS Nordic Energy Link was established. On 29 April 2005, the Estlink project was launched. Construction of Harku converter station and land cable installation begins on 5 April 2006. The submarine cable was laid in September 2006. The Estlink cable was inaugurated on 4 December 2006 and it became fully operational on 5 January 2007. The Estlink 1 cable was operated by AS Nordic Energy Link company, founded by Baltic and Finnish power companies. The main shareholder was Eesti Energia with 39.9% of the shares, Latvenergo and Lietuvos Energija had 25% each, and the remaining 10.1% was divided between Pohjolan Voima and Helsingin Energia (operating through their joint project company Finestlink). On 30 December 2013 the interconnector was sold to the
transmission system operator File:Electricity grid simple- North America.svg, 380px, Simplified diagram of AC electricity grid from generation stations to consumers rect 2 243 235 438 Power station rect 276 317 412 556 Transformer rect 412 121 781 400 Electric power transmis ...
s
Elering Elering AS (former name: OÜ Põhivõrk) is a national transmission system operator for electricity and natural gas with headquarters in Tallinn, Estonia. The managing director of Elering is Taavi Veskimägi. History Elering was established on ...
and
Fingrid Fingrid Oyj is a Finnish national electricity transmission grid operator. It is owned by the Finnish state (53.1 %) and various financial and insurance institutions (46.9 %). In 2011, power companies Fortum Power and Heat Oy and Pohjolan Voima sol ...
.


Description

The long (including under water) +/-150 kV, 350 MW HVDC link cable is connected to the Estonian electrical system at the Harku 330 kV converter station and to the Finnish transmission network at
Espoo Espoo (, ; sv, Esbo) is a city and municipality in the region of Uusimaa in the Republic of Finland. It is located on the northern shore of the Gulf of Finland, bordering the cities of Helsinki, Vantaa, Kirkkonummi, Vihti and Nurmijärvi ...
400 kV converter station in Järvikylä using HVDC Light transmission technology. The installation of land cable began on 4 May 2006 in
Harku Harku (german: Hark) is a Populated places in Estonia, small borough ( et, alevik) in Harku Parish, Harju County, northern Estonia. As of 2011 Estonia Census, 2011 Census, the settlement's population was 868, of which the Estonians were 539 (62 ...
. The submarine cable was laid on the seabed of the
Gulf of Finland The Gulf of Finland ( fi, Suomenlahti; et, Soome laht; rus, Фи́нский зали́в, r=Finskiy zaliv, p=ˈfʲinskʲɪj zɐˈlʲif; sv, Finska viken) is the easternmost arm of the Baltic Sea. It extends between Finland to the north and E ...
in the autumn of 2006. The cable's maximum depth on the seabed is . The cable is constructed by
ABB ABB Ltd. is a Swedish- Swiss multinational corporation headquartered in Zürich, Switzerland. The company was formed in 1988 when Sweden's Allmänna Svenska Elektriska Aktiebolaget (ASEA) and Switzerland's Brown, Boveri & Cie merged to crea ...
. The submarine cable was laid by
Global Marine Systems Global Marine Group is a British-headquartered specialist provider of installation, maintenance and repairs of submarine communications cable for the telecommunications, oil & gas and deep sea research industries. To this end, they operate their ...
using the ''Sovereign'' service vessel. The project cost €110 million.


Sites


Estlink 2


History

A preliminary agreement on EstLink 2 was signed between Elering and Fingrid on 15 February 2010 in Tallinn. Capital investment decision by Fingrid was made on 20 May 2010. A construction agreement was signed on 1 November 2010. On 23 December 2010, the contract to manufacture and install the subsea and underground cables was awarded to
Nexans Nexans S.A. is a global company in the cable and optical fiber industry headquartered in Paris, France. The group is active in four main business areas: buildings and territories (construction, local infrastructure, smart cities / grids, e-mobil ...
, the contract to build converter stations was awarded to
Siemens Siemens AG ( ) is a German multinational conglomerate corporation and the largest industrial manufacturing company in Europe headquartered in Munich with branch offices abroad. The principal divisions of the corporation are ''Industry'', '' ...
, the contract to build the Nikuviken cable terminal station and to expand the Anttila substation in Finland was awarded to Empower Oy, and the contract to build the transmission line between Anttila and Nikuviken was awarded to ETDE, a part of
Bouygues Bouygues S.A. () is a French industrial group headquartered in the 8th arrondissement of Paris, 8th arrondissement of Paris, France. Bouygues is listed on the Euronext, Euronext Paris exchange and is a blue chip (stock market), blue chip in the C ...
. Laying of the cable started on 15 October 2012 and it is laid by the cable ship ''Nexans Skagerrak''. The cable testing started on 22 October 2013. A trial operation started on 6 December 2013 and continued until 6 February 2014 after which it started commercial operations. It was officially inaugurated on 6 March 2014.


Description

The total length of Estlink 2 would be , including a long offshore cable, a long onshore cable in Estonia, and of overhead lines in Finland. The long underground cable starts at the Püssi substation and runs the coast of the Gulf of Finland at
Aseri Aseri (german: Asserin) is a small borough ( et, alevik) in Viru-Nigula Parish, Lääne-Viru County, in northeastern Estonia. As of 2011 Census, the settlement's population was 1,439, of which the Estonians Estonians or Estonian people ( ...
. From there the long offshore cable runs to the Nikuviken cable terminal station in Finland. The Nikuviken cable terminal station will be connected with the Attila converter station by the long overhead line. Estlink 2 will be a classic bidirectional monopolar high-voltage direct current connection with line-commutated converter
thyristor A thyristor () is a solid-state semiconductor device with four layers of alternating P- and N-type materials used for high-power applications. It acts exclusively as a bistable switch (or a latch), conducting when the gate receives a current ...
s. Its maximum transmission rate will be 650 MW and it will operate with a voltage of 450 kV. Its estimated cost is about €320 million, of which converter stations cost €100 million and cable €180 million. The European Commission has decided to allocate €100 million to the project.


Sites


Waypoints of overhead line in Finland

* * * * * * * * * * * * * * * * * * *


Estlink 3

On June 28, 2022, Elering and Fingrid signed a memorandum of understanding to begin planning for a third submarine cable, EstLink3, with a capacity of up to 1000 MW, expected to be completed by 2035.


See also

*
Baltic Cable The Baltic Cable is a monopolar HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden. Its maximum transmission power is 600 megawatts (MW). The Baltic Cable uses a transmission voltag ...
(between Germany and Sweden) *
Balticconnector Balticconnector is a bi-directional natural gas pipeline between Ingå, Finland and Paldiski, Estonia. It connects Estonian and Finnish gas grids. The pipeline provides Finland with access to the Latvian natural gas storage facility at Inču ...
(proposed gas pipeline between Estonia and Finland) * Fenno-Skan (between Finland and Sweden) *
NordBalt NordBalt (also formerly known as SwedLit) is a submarine power cable between Klaipėda in Lithuania and Nybro in Sweden. The purpose of the cable is to facilitate the trading of power between the Baltic and Nordic electricity markets, and to in ...
(between Lithuania and Sweden) * SwePol (between Poland and Sweden) *
List of HVDC projects This is a list of notable high-voltage direct-current power transmission projects. HVDC projects for long-distance transmission have two (or rarely, more) converter stations and a transmission line interconnecting them. Generally overhead lines ...


References


External links


Nordic Energy Link

Estlink 2 Newsletter. issue 2, May 2011
(PDF) {{GeoGroup Electrical interconnectors to and from the Baltic grid Electrical interconnectors to and from the Nordic grid Energy infrastructure completed in 2006 Energy infrastructure completed in 2014 HVDC transmission lines Submarine power cables Connections across the Baltic Sea Electric power infrastructure in Estonia Electric power infrastructure in Finland Estonia–Finland relations 2006 establishments in Estonia 2006 establishments in Finland