Delhi–Meerut Expressway or National Expressway 3 is
India India, officially the Republic of India ( Hindi: ), is a country in South Asia. It is the seventh-largest country by area, the second-most populous country, and the most populous democracy in the world. Bounded by the Indian Ocean on the ...
's widest 96 km long controlled-access expressway, connecting
Delhi Delhi, officially the National Capital Territory (NCT) of Delhi, is a city and a union territory of India containing New Delhi, the capital of India. Straddling the Yamuna river, primarily its western or right bank, Delhi shares borders w ...
with
Meerut Meerut (, IAST: ''Meraṭh'') is a city in Meerut district of the western part of the Indian state of Uttar Pradesh. The city lies northeast of the national capital New Delhi, within the National Capital Region and west of the state capit ...
via Dasna in
Ghaziabad Ghaziabad () is a city in the Indian state of Uttar Pradesh and a part of Delhi NCR. It is the administrative headquarters of Ghaziabad district and is the largest city in western Uttar Pradesh, with a population of 1,729,000. Ghaziabad Mun ...
in India. The 8 lanes old stretch of National Highway 9 (NH-9) up to Dasna is widened to 14 lanes(widest expressway in India). The fourth phase of the expressway is built on a new alignment from Dasna to
Meerut Meerut (, IAST: ''Meraṭh'') is a city in Meerut district of the western part of the Indian state of Uttar Pradesh. The city lies northeast of the national capital New Delhi, within the National Capital Region and west of the state capit ...
– a six-lane stretch joining Meerut bypass. The stretch between Nizamuddin Bridge and Dasna is one of the most congested areas in the NCR.The total project cost is estimated to be between 8,000–10,000
crore A crore (; abbreviated cr) denotes ten million (10,000,000 or 107 in scientific notation) and is equal to 100 lakh in the Indian numbering system. It is written as 1,00,00,000 with the local 2,2,3 style of digit group separators (one lakh i ...
s.


History

A proposal for a
Ghaziabad Ghaziabad () is a city in the Indian state of Uttar Pradesh and a part of Delhi NCR. It is the administrative headquarters of Ghaziabad district and is the largest city in western Uttar Pradesh, with a population of 1,729,000. Ghaziabad Mun ...
to Meerut expressway was mentioned in the
Lok Sabha The Lok Sabha, constitutionally the House of the People, is the lower house of India's bicameral Parliament, with the upper house being the Rajya Sabha. Members of the Lok Sabha are elected by an adult universal suffrage and a first-p ...
by the then Minister of State for Urban Affairs and Employment in March 1999. The proposal again found mention in a February 2000 seminar speech by the then Union Urban Development Minister. An expressway from Delhi to Meerut via Ghaziabad was then proposed under the NCR Transport Plan 2021, which was notified in September 2005. The Delhi to Ghaziabad section was to be taken up in 2001–11 with the Ghaziabad to Meerut scheduled 2011–21. In February 2006, the committee on infrastructure gave approval for a feasibility study for the expressway. The decision to build the expressway was announced in the 2006 budget speech by then
Finance Minister A finance minister is an executive or cabinet position in charge of one or more of government finances, economic policy and financial regulation. A finance minister's portfolio has a large variety of names around the world, such as "treasury", ...
P. Chidambaram Palaniappan Chidambaram (born 16 September 1945), better known as P. Chidambaram, is an Indian politician and lawyer who currently serves as Member of Parliament, Rajya Sabha. He served as the Chairman of the Parliamentary Standing Committee ...
. Construction of 1,000 km of expressways under National Highway Development Program (NHDP) Phase-VI was approved in November 2006. In December 2006, it was reported that 600 km of expressways would be chosen from among the proposed expressways including the Delhi-Meerut expressway for the first stage of NHDP Phase-VI on the basis of a prioritization study being taken up by the NHAI. In April 2008, it was reported that proposals had been invited from consultants for deciding the alignment of the expressway. In November 2009, it was reported that the alignment study had been completed and a consultant had been appointed for the feasibility study for the project, with the expected completion of the study by May 2010. In August 2011, it was reported that the expressway was targeted for completion by December 2015. In October 2011, it was reported that the feasibility report was under progress and the project was to be taken up under NHDP Phase-VI. The alignment proposed was to be along NH-24 from Nizammuddin to Dasna and then to Meerut. In December 2011, the December 2015 targeted completion date was reaffirmed and the feasibility report submitted by the appointed consultant was said to be under study. In May 2012, it was reported that the original target of awarding concession by 2009–10 was not completed due to various problems regarding alignment finalisation, and the consequent delay in feasibility reports. In July 2013, the Steering Group appointed by the
Prime Minister A prime minister, premier or chief of cabinet is the head of the cabinet and the leader of the ministers in the executive branch of government, often in a parliamentary or semi-presidential system. Under those systems, a prime minister is ...
to accelerate Infrastructure Investment decided on 15 March 2014 as the last date for awarding of contract for the expressway. In August 2013, it was reported that the expressway was targeted for the contemporary financial year. In November 2013, it was reported that the stretch from Delhi up to UP Gate was to be converted from six lanes to fourteen lanes with six lanes grade-separated exclusively for traffic moving towards Meerut. The stretch from UP Gate to Dasna was to be eight laned and a new six lane alignment was to come up from Dasna to Meerut bypass on National Highway – 58. The project cost, including land acquisition, was estimated at . On 18 November 2013, it was confirmed that Centre, not the Uttar Pradesh State Government, would build the much delayed Delhi–Meerut Expressway starting from Nizamuddin Bridge on
Ring Road A ring road (also known as circular road, beltline, beltway, circumferential (high)way, loop, bypass or orbital) is a road or a series of connected roads encircling a town, city, or country. The most common purpose of a ring road is to assist i ...
. Once complete, commuters will be able to reach Meerut in 45 to 60 minutes and cut travel time to
Haridwar Haridwar (; ) is a city and municipal corporation in the Haridwar district of Uttarakhand, India. With a population of 228,832 in 2011, it is the second-largest city in the state and the largest in the district. The city is situated on the rig ...
and
Dehradun Dehradun () is the capital and the most populous city of the Indian state of Uttarakhand. It is the administrative headquarters of the eponymous district and is governed by the Dehradun Municipal Corporation, with the Uttarakhand Legislative ...
by almost an hour. The Cabinet Committee on Economic Affairs (CCEA) under the government of India Chaired by Prime Minister
Narendra Modi Narendra Damodardas Modi (; born 17 September 1950) is an Indian politician serving as the 14th and current Prime Minister of India since 2014. Modi was the Chief Minister of Gujarat from 2001 to 2014 and is the Member of Parliament fro ...
approved the Delhi–Meerut Expressway (4 laning) with construction of connected roads to be undertaken in July 2014. CCEA under PM Modi again approved the widening of these roads 8/6 laning in May 2016. There will be six- to eight-laning of NH 24 (Hapur bypass), six laning of NH 58 (Delhi-UP border), six-laning of NH 235 (Delhi-UP). The total cost is about . The deadline set for the project is three years. Construction of the Nizamuddin to Dasna road was scheduled to begin on 31 December 2015.


Project

National Highway Authority of India (NHAI) divided the 96 km stretch starting from Nizamuddin bridge in the outer ring road in New Delhi to Meerut bypass into four packages:


Package I: Nizamuddin Bridge to Delhi-UP border

This section is 8.7 km long, 14 Lane (6 Lane Expressway, 8 Lane Normal Highway, 2.5 m Bicycle Track on Both Side) with 4 flyovers and 3 vehicle underpass. The project involved development of expressway from Nizamuddin Bridge (km-0.000) to existing Delhi-Uttar Pradesh Border (km-8.360) section of NH-24 Development of Package I of Delhi–Meerut Expressway in length of 8.7 km in Delhi was awarded to
concessionaire A concession or concession agreement is a grant of rights, land or property by a government, local authority, corporation, individual or other legal entity. Public services such as water supply may be operated as a concession. In the case of a p ...
Welspun Delhi Meerut Expressway Private Limited. Total project cost was estimated to be . This phase of the expressway was inaugurated on 27 May 2018 by Prime Minister Narendra Modi.


Package II: Delhi-UP Border to Dasna

This section is 19.2 km long, 14 lane (6 lane expressway, 8 lane normal highway, 2.5 m bicycle track on both sides) with 13 vehicle underpasses and 6 foot-underpasses. Tender for this section was awarded to Apco Chetak JV (A JV between Apco Infratech Ltd and Chetak Enterprises Ltd), at a cost of (cost of shifting of transmission lines: , cost of shifting water pipeline: , 22,027 trees was estimated to be cut and compensation given to district forest department) The work was carried out under
National Highways Development Project The National Highways Development Project (NHDP) is a project to upgrade, rehabilitate and widen major highways in India to a higher standard. The project was started in 1998 under the leadership of Prime Minister, Atal Bihari Vajpayee. Nation ...
(NHDP): Phase-VI. A total nine underpasses and three flyovers are planned on the 20 km stretch to Dasna. But following a revision in the detailed project report, the plan was amended to 15 underpasses and a just one flyover, at Lal Kuan. The underpasses has been built in such a way that there is no crisscrossing traffic on the expressway and traffic flow at intersections will be altered accordingly. This section was completed on 1 April 2021 and opened for public.


Package III: Dasna to Hapur

This section is 22.2 km long, 8 lane normal highway, from existing km 27.500 to existing km 49.923 of NH 24. 1 flyover and 12 underpass will be constructed on this segment. Previously it was 6 lane but in Sep–Oct 2016 board meeting it was updated to 8 lanes. Contract for this section was awarded to Apco-Chetak JV, at a cost of . This section was formally inaugurated on 30 September 2019 by
Nitin Gadkari Nitin Jairam Gadkari (; born 27 May 1957) is an Indian politician from Maharashtra who is the current Minister for Road Transport & Highways in the Government of India. He is also the longest serving Minister for Road Transport & Highways cur ...
, Union Minister of MoRTH


Package IV: Dasna to Meerut

46 km long, 6 lane expressway is a new greenfield alignment. The alignment stretched from Dasna in Ghaziabad district to Meerut Bypass at Partapur. Earlier, the 45-km-long Ghaziabad to Meerut section of NH-58 was also part of project but due to the decision of Rapid Rail Transit System (RRTS) to use dividers on NH-58 for trains' elevated corridor, the highway was not used and new alignment was proposed. The tender for the above alignment was awarded to GR Infraprojects for a contract value of ₹1,087.07 crores. This section was completed on 1 April 2021 and opened for public.


Funding

Of the total project cost, 40% was funded by the
National Highways Authority of India The National Highways Authority of India or NHAI (Hindi: भारतीय राष्ट्रीय राजमार्ग प्राधिकरण) is an autonomous agency of the Government of India, set up in 1995 (Act 1988) and i ...
(NHAI) under the new 'Hybrid Annuity Model'. The remaining 60% was arranged by the concessionaire by way of mix of debt/equity of 48:12, 12% being the promoter's contribution and rest will be funded by
Punjab National Bank Punjab National Bank (abbreviated as PNB) is an Indian public sector bank headquartered in Delhi. The bank was founded in May 1894 and is the second largest government-owned bank in India, both in terms of its business volumes and its network ...
-led
consortium A consortium (plural: consortia) is an association of two or more individuals, companies, organizations or governments (or any combination of these entities) with the objective of participating in a common activity or pooling their resources fo ...
.


Historical Timeline

* Prime Minister
Narendra Modi Narendra Damodardas Modi (; born 17 September 1950) is an Indian politician serving as the 14th and current Prime Minister of India since 2014. Modi was the Chief Minister of Gujarat from 2001 to 2014 and is the Member of Parliament fro ...
laid the foundation stone for the expressway on 30 December 2015.


Section 1: Nizamuddin Bridge to Delhi-UP Border

* 2017 Mar: 15% work completed. * 2017 Aug: 60% work completed. * 2017 Nov: 75% work completed. * 2018 Apr: 100% work completed * 27 May 2018: Inaugurated by the Prime Minister of India,
Narendra Modi Narendra Damodardas Modi (; born 17 September 1950) is an Indian politician serving as the 14th and current Prime Minister of India since 2014. Modi was the Chief Minister of Gujarat from 2001 to 2014 and is the Member of Parliament fro ...
.


Section 2: Delhi-UP Border to Dasna

* 2017 Mar: Contract is yet to be awarded to developer. * 2017 Aug: Apco-Chetak (joint venture between Apco Infra from Uttar Pradesh and Chetak from Rajasthan) the developer for this section is not able to complete financial closure for this section i.e. not able to get it financed by banks. *2017 Nov: Work has finally started on this section. Leveling work has started and separator boards have been enacted for proposed flyover at Lal Kuan by Apco Infra. * 2018 May: 15% work completed. * 2018 Oct: 24% work completed. * 2019 Jan: 35% work completed. * 2019 Feb: UP border to Dasna will be completed By December 2019 i.e. before the official deadline of May 2020. * 2019 Apr: 46% work completed on UP-Border – Vijaynagar stretch of 8 km. * 2019 July: 53% work completed on UP-Border – Vijaynagar stretch of 8 km. To be inaugurated by December 2019. * 2019 Aug: 53% work completed on UP-Border – portion from UP Gate to Pratap Vihar will be opened by October 2019. Full stretch to be inaugurated by December 2019, however, rail over-bridge at LalKuan will be completed by May 2020. *2020 Feb:70% work completed. *2020 Aug: 85% work completed. *2021 Apr: Completed on 1 April 2021 and opened for public.


Section 3: Dasna to Hapur

* 2017 Mar: Work started. * 2017 Aug: 15% work completed. * 2018 May: 60% work completed. * 2019 Jan: 85% work completed. * 2019 July: 95% work completed. 5 km-long Pilkhuwa elevated road opened. * 2019 Aug 10: 97% work completed. Masuri bridge opened. * 2019 Aug 19: 97% work completed. * 2019 Sep 02: Dasna to Hapur section opened for traffic. * 2019 Sep 30, 2019: Section formally inaugurated by
Nitin Gadkari Nitin Jairam Gadkari (; born 27 May 1957) is an Indian politician from Maharashtra who is the current Minister for Road Transport & Highways in the Government of India. He is also the longest serving Minister for Road Transport & Highways cur ...
, Union Minister of MoRTH


Section 4: Dasna to Meerut

* 2018 May: 3% work completed. * 2018 Dec: 25% work completed * 2019 July: 51% work completed * 2019 Sep: The stretch to get delayed as no work has started on 4 km of track due to land not handed over to authority because of on going land scam enquiry. * 2019 Dec: The Ghaziabad District Administration handed over 71 hectares of land to NHAI for construction of Meerut Expressway, clearing the land hurdle. * 2020 Feb: 60% work completed. * 2020 Aug: 75% work completed. *2021 Apr: Completed on 1 April 2021 and opened for public.


Green initiatives

The National Highways Authority of India (NHAI) utilised the solid waste from
Ghazipur Ghazipur is a city in the state of Uttar Pradesh, India. Ghazipur city is the administrative headquarters of the Ghazipur district, one of the four districts that form the Varanasi division of Uttar Pradesh. The city of Ghazipur also constitu ...
landfill in construction of Delhi–Meerut Expressway to curb pollution.