Labour Efficiency Variance
Difference between the amount of labor time that should have been used and the labor that was actually used, multiplied by the standard rate. For example, assume that the standard cost of direct labor per unit of product A is 2.5 hours x $14 = $35. Assume further that during the month of March the company recorded 4500 hours of direct labor time. The actual cost of this labor time was $64,800, or an average of $14.40 per hour. The company produced 2000 units of product A during the month. The labor efficiency variance is (4500 - 5000) x $14 = $7000, where 5000 hours = 2.5 hours x 2000 units of output. This variance is favorable since the actual hours used are less than the standard hours allowed. This may be the result of efficient use of labor time due to automation or the use of improved production methods.References