Contingency (electrical Grid)
   HOME

TheInfoList



OR:

In an
electrical grid An electrical grid is an interconnected network for electricity delivery from producers to consumers. Electrical grids vary in size and can cover whole countries or continents. It consists of:Kaplan, S. M. (2009). Smart Grid. Electrical Power ...
, contingency is an unexpected failure of a single principal component (e.g., an electrical generator or a power transmission line) that causes the change of the system state large enough to endanger the grid security. Some protective relays are set up in a way that multiple individual components are disconnected due to a single fault, in this case, taking out of all the units in a group counts as a single contingency. A scheduled outage (like maintenance) is not a contingency. The choice of term emphasizes the fact that a single fault can cause severe damage to the system so quickly that the operator will not have time to intervene, and therefore a reaction to the fault has to be defensively pre-built into the system configuration. Some sources use the term interchangeably with "disturbance" and "fault".


Contingency analysis

The contingency analysis application periodically runs on the computers at the operations centers providing suggestions to the operators based on the current state of the grid and the ''contingency selection''. The software provides answers to the "what if" scenarios in the form of "alarms": "Loss of component X will result in overload of Y by Z%". By the 1990s analysis of a large interconnected system involved testing of many thousands of contingency events (millions if double contingencies were considered). An effect of each contingency requires performing a
power flow In power engineering, the power-flow study, or load-flow study, is a numerical analysis of the flow of electric power in an interconnected system. A power-flow study usually uses simplified notations such as a one-line diagram and per-unit system ...
calculation. Due to the rapid change of the state of a power system the run of the application shall complete in minutes (up to 30) for the results to be useful. Typically only selected contingencies, mostly single ones with some double ones are considered to speed up the process. The selection of contingencies is using engineering judgment to choose the ones most likely to cause problems.


Credible contingencies

The foreseen and analyzed contingencies are called ''credible''. Examples of these are failures of: * a transmission line or tie line /
HVDC link A high-voltage direct current (HVDC) electric power transmission system (also called a power superhighway or an electrical superhighway) uses direct current (DC) for electric power transmission, in contrast with the more common alternating curren ...
; * a generator; * a transformer; * a variable renewable energy cluster; * a
voltage compensation Voltage control and reactive power management are two facets of an ancillary service that enables reliability of the Electric power transmission, transmission networks and facilitates the electricity market on these networks. Both aspects of this a ...
device. In continental Europe these contingencies are considered "normal", with "exceptional" credible contingencies being the failures of: * a
double circuit transmission line A double is a look-alike or doppelgänger; one person or being that resembles another. Double, The Double or Dubble may also refer to: Film and television * Double (filmmaking), someone who substitutes for the credited actor of a character * ...
; * two generators; * a
bus bar In electric power distribution, a busbar (also bus bar) is a metallic strip or bar, typically housed inside switchgear, panel boards, and busway enclosures for local high current power distribution. They are also used to connect high volt ...
. Non-credible (also called "out-of-range") contingencies are not used in planning, as they are rare and their effects are hard to predict, for example, failures of: * an entire
electrical substation A substation is a part of an electrical generation, transmission, and distribution system. Substations transform voltage from high to low, or the reverse, or perform any of several other important functions. Between the generating station and ...
; * a transmission tower that carries more than two lines.


N-X contingency planning

Reliability of the energy supply usually requires that any single major unit failure leaves the system with enough resources to supply the current load. The system that satisfies this requirement is described as meeting the N-1 contingency criterion (N designates the number of pieces of equipment). The N-2 and N-3 contingency refers to planning for a simultaneous loss of, respectively, 2 or 3 major units; this is sometimes done for the critical area (e.g.
downtown ''Downtown'' is a term primarily used in North America by English speakers to refer to a city's sometimes commercial, cultural and often the historical, political and geographic heart. It is often synonymous with its central business distric ...
). The N-1 requirement is used throughout the network, from generation to substations. At the
distribution Distribution may refer to: Mathematics *Distribution (mathematics), generalized functions used to formulate solutions of partial differential equations * Probability distribution, the probability of a particular value or value range of a vari ...
level, however, the planners frequently allow a more relaxed interpretation: a single failure should ensure uninterrupted delivery of power to almost all the customers at least at the "emergency level" (Range B of the ANSI C84.1), but a small section of the network that contains the original fault might require ''manual switching'' with a service interruption for about an hour. The popularity of ''contingency planning'' is based on its advantages: * each of the N elements in the system is analyzed separately, limiting the amount of work to be done and simplifying the failure options (e.g., generator failure, short circuit); * the process inherently provides a way to deal with the contingency if and when it will happen. The N-1 contingency planning is typically sufficient for the systems with the usual ratio of peak load to capacity (below 70%). For a system with a substantially higher ratio, the N-1 planning will not deliver satisfactory reliability, and even N-2 and N-3 criteria might not be sufficient; therefore the ''reliability-based planning'' is used that considers the probabilities of the individual contingencies.


References


Sources

* * * * * * {{electric-stub Power engineering