1999 Cherry Hills Subdivision Landslide
   HOME

TheInfoList



OR:

On the night of August 2, 1999, a massive
landslide Landslides, also known as landslips, are several forms of mass wasting that may include a wide range of ground movements, such as rockfalls, deep-seated grade (slope), slope failures, mudflows, and debris flows. Landslides occur in a variety of ...
occurred in Cherry Hills subdivision in
Antipolo Antipolo, officially known as the City of Antipolo ( fil, Lungsod ng Antipolo), is a 1st class component city and capital of the province of Rizal, Philippines. According to the 2020 census, it has a population of 887,399 people. It is the mo ...
,
Rizal Rizal, officially the Province of Rizal ( fil, Lalawigan ng Rizal), is a Provinces of the Philippines, province in the Philippines located in the Calabarzon region in Luzon. Its capital is the city of Antipolo. It is about east of Manila. The p ...
,
Philippines The Philippines (; fil, Pilipinas, links=no), officially the Republic of the Philippines ( fil, Republika ng Pilipinas, links=no), * bik, Republika kan Filipinas * ceb, Republika sa Pilipinas * cbk, República de Filipinas * hil, Republ ...
that resulted to about 60 deaths and 378 houses buried. The landslide was primarily caused by the heavy rains associated with Typhoon Ising (Olga) and neglect by the developers and government officials in assessing the site's vulnerability to geohazards.


Background

Cherry Hills subdivision was home to hundreds of families paying-off low cost,
concrete Concrete is a composite material composed of fine and coarse aggregate bonded together with a fluid cement (cement paste) that hardens (cures) over time. Concrete is the second-most-used substance in the world after water, and is the most wi ...
house A house is a single-unit residential building. It may range in complexity from a rudimentary hut to a complex structure of wood, masonry, concrete or other material, outfitted with plumbing, electrical, and heating, ventilation, and air condi ...
s. The subdivision was owned and developed by Tirso Santillan, president of Philippine-Japan Solidarity (Philjas) Corporation, which had previously been given a contract by the Housing and Land Use Regulatory Board (HLURB) to develop the area by 1992 but was given an extension of up to March 1999 due to delays. Following complaints by lot buyers, an inspection by the HLURB had previously found that Philjas failed to follow the plan in its contract, including amenities such as landscaping, entrance gate and water tanks.


Topography

The subdivision was located in Antipolo, Rizal and was situated in an elevated terrain cut along the perches of the Sierra Madre mountains. It was also flanked by two subdivisions on its sides. The eastern summit was at elevation of 255 meters while the western side was at elevation of 233 meters. The subdivision cut from the mountain side was approximately 26 meters at its deepest. The subdivision encompassed five
hectare The hectare (; SI symbol: ha) is a non-SI metric unit of area equal to a square with 100-metre sides (1 hm2), or 10,000 m2, and is primarily used in the measurement of land. There are 100 hectares in one square kilometre. An acre is a ...
s with paved roads. The subdivision consisted of light-roofed one or two-storey houses with hollow block wall construction that are either single-detached or row houses.


Event

Before the landslide, several residents started evacuating the area when cracks began manifesting on the walls of their houses. Tell-tale signs about a possible impending slide was rumored, and ominous signs of changes in elevation and ground movements were observed. Three days before the landslide, rainfall measurements totaled 523.3 millimeters, equivalent to 120 days of normal rainfall during the rainy season, and was reported to have broken a 35-year record. This was primarily due to the onslaught of Typhoon Ising (Olga) and its enhancement of the
southwest monsoon A monsoon () is traditionally a seasonal reversing wind accompanied by corresponding changes in precipitation but is now used to describe seasonal changes in atmospheric circulation and precipitation associated with annual latitudinal oscill ...
. On August 3, 1999, the landslide occurred as other residents were preparing to evacuate due to heavy rain, trapping them inside their homes as uphill houses and 45,000 cubic meters of mud, rocks, and concrete buried low-lying areas. At least 58 people died, while 300 homes were destroyed and 378 families were left homeless.


Investigation

Philjas claimed that the landslide was trigged by excess rainwater that had seeped into Hill 255 and was aggravated by ground fissures caused by renovations done by residents, who in turn accused Philjas of using substandard materials. However, Philjas officials later acknowledged that quarrying by the company on a mountain that left a 20-foot high hanging wall made the site unstable and that they had failed to present a geohazard assessment before commencing construction. It was also later found that the subdivision was built on a 27% slope rather than the 15% claimed that Philjas. A study by geologists at the
University of the Philippines The University of the Philippines (UP; fil, Pamantasan ng Pilipinas Unibersidad ng Pilipinas) is a state university system in the Philippines. It is the country's national university, as mandated by Republic Act No. 9500 (UP Charter of 200 ...
also attributed the cause to the geological setting of the area, noting that its soil was oversaturated with water as it consisted of alternating porous and impervious rocks as well as a significant amount of clays "of probably the swelling type." They also cited the natural slope of the ground, sparse vegetation, and pre-existing fractures in the bedrock, and concluded that a geological survey could have avoided the event, which geologists said was probably not conducted to save on construction costs. A further inspection by the
Mines and Geosciences Bureau The Mines and Geo-sciences Bureau (MGB) is a government agency of the Philippines under the Department of Environment and Natural Resources (DENR). The MGB is responsible for the conservation, management, development and use of the country's mi ...
found that the site also did not have a proper drainage system and was vulnerable to ground slippage because of the dangerous slope to its west. An investigation by the
Philippine Senate The Senate of the Philippines (Filipino language, Filipino: ''Senado ng Pilipinas'', also ''Mataas na Kapulungan ng Pilipinas'' or "upper chamber") is the upper house of Congress of the Philippines, Congress of the bicameral legislature of the ...
concluded that the disaster was not caused by
force majeure In contract law, (from Law French: 'overwhelming force', ) is a common clause in contracts which essentially frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties, such ...
, but occurred as a result of the negligence of Philjas and government agencies, which failed to enforce rules on the construction of low–cost housing. Among those named in its report were the HLURB and the Antipolo city government.


Aftermath

In December 1999, the
Office of the Ombudsman An ombudsman (, also ,), ombud, ombuds, ombudswoman, ombudsperson or public advocate is an official who is usually appointed by the government or by parliament (usually with a significant degree of independence) to investigate complaints and at ...
recommended the dismissal of five housing and environment officials for "gross neglect" and the suspension of 13 other housing, environment and city officials in relation to the disaster. In 2001, a court ordered the arrest of Philjas president Santillan, his general manager Hiroshi Ogawa, and assistant general manager Eleazar Rodriguez. The charges were dismissed by the Antipolo prosecutor's office before it was reopened by the
Justice Department A justice ministry, ministry of justice, or department of justice is a ministry or other government agency in charge of the administration of justice. The ministry or department is often headed by a minister of justice (minister for justice in a ...
in 2002. In 2004, Santillan and Rodriguez pleaded not guilty to charges of reckless imprudence, while Ogawa went into hiding, followed later by Rodriguez. As of 2011, the case had not yet been resolved. In 2002, the HLURB ordered Philjas to pay damages estimated at P89 million and return payments previously made by the residents. Philjas then gave each family P15,000, and another P10,000 to those who lost a member. The disaster led the
Department of Environment and Natural Resources The Department of Environment and Natural Resources ( fil, Kagawaran ng Kapaligiran at Likas na Yaman, DENR or KKLY) is the executive department of the Philippine government responsible for governing and supervising the exploration, developmen ...
to issue an administrative order in 2000 requiring developers of housing projects and other infrastructure projects to conduct a geohazard assessment before they are issued a license. The unaffected parts of the subdivision continue to be an inhabited residential area.


References


External links

* * *{{cite journal, last=Catane, first=Sandra, author2=Mark Albert Zarco, author3=Ricarido Saturay, Jr, year=2006, title=Landslide-Risk Reduction Strategies and Practices in the Philippines, journal=University of the Philippines, publisher=University of the Philippines, location=Quezon City, url=http://150.217.73.85/wlfpdf/02_Catane.pdf, archive-url=https://web.archive.org/web/20090902205433/http://150.217.73.85/wlfpdf/02_Catane.pdf, url-status=dead, archive-date=September 2, 2009, accessdate=June 27, 2009 Landslides in the Philippines 1999 disasters in the Philippines History of Rizal Antipolo Landslides in 1999 August 1999 events in Asia